AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Re: Resident Engineer Off ice Building, Dam Safety Modif ication Project, East Branch Lake, Clarion River, Elk County, PA

This amendment is being issued to: 1) Provide a response to a question received, and 2) Revise Technical Specif ication Section 01 11 00 Performance Work Statement.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 25-Apr-2012

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911WN-12-R-0001

X 9B. DATED (SEE ITEM 11)

29-Mar-2012

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

25-Apr-2012

CODE

U.S. ARMY ENGINEER DISTRICT, PITTSBURGH

ATTN CECT-LRP

W S MOORHEAD FEDERAL BUILDING

1000 LIBERTY AVENUE ROOM 2203

PITTSBURGH PA 15222-4186

W911WN 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W911WN-12-R-0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

THE FOLLOWING SPECIFICATION SECTION IS REPLACED/ADDED WITH THE ATTACHED

SECTION INCLUDED WITH THIS AMENDMENT, AS FOLLOWS:

SECTION 01 11 00 Performance Work Statement; (revisions to section are underlined)

THE FOLLOWING QUESTION WAS RECEIVED AND A RESPONSE IS PROVIDED BELOW:

1. Since no foundation design was provided; is this requirement to assure that the building has concrete floors at grade? If this requirement is fulfilled utilizing a slab minimally below grade would this be acceptable.

Section 01 11 00, paragraph 2.1.2.2 “Foundation” states that the foundation designs must be provided by the contractor, and signed by a Professional Engineer. The foundation shall consist of a concrete slab with all-concrete footers and foundation wall. The finished floor elevation for the building and the grade elevations around the building are shown on drawing C-3082. The finished floor elevation is approximate and can change, but must be above grade. The top of the slab-on-grade shall also be above grade.

If the flooring system includes floor joists, pressure-treated lumber must be used. Vents for moisture control in the voids between joists must be included, along with varmint controls. The subfloor must be double-layer tongue-and-groove with staggered joints. Utilities must be brought up through the slab-on-grade, and insulated/heated to prevent freezing. Once inside the building, utilities shall not be run below floor between joists.

Regardless of foundation system, a concrete slab-on-grade must be used.

Section 01 11 00, paragraph 2.1.2.2 “Foundation” has been revised to include these clarifications.

(End of Summary of Changes)