Resident Engineer Office Building Dam Safety Modification Project, East Branch Lake
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 10
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 LUMP SUM PAYMENT ITEMS
1.1.1 EROSION AND SEDIMENT CONTROLS
1.1.1.1 Payment
1.1.1.2 Unit of Measure
1.1.1.3 Payment Items
1.1.2 DESIGN AND CERTIFICATION OF BUILDING
1.1.2.1 Payment
1.1.2.2 Unit of Measure
1.1.2.3 Payment Items
1.1.3 CONSTRUCTION OF BUILDING
1.1.3.1 Payment
1.1.3.2 Unit of Measure
1.1.3.3 Payment Items
1.1.4 PAVEMNT MARKINGS
1.1.4.1 Payment
1.1.4.2 Unit of Measure
1.1.4.3 Payment Item
1.1.5 RESTORATION OF NON-PAVED AREA
1.1.5.1 Payment
1.1.5.2 Unit of Measure
1.1.5.3 Payment Item
1.1.6 MECHANICAL WORK
1.1.6.1 Payment
1.1.6.2 Unit of Measure
1.1.6.3 Payment Item
1.1.7 ELECTRICAL WORK
1.1.7.1 Payment
1.1.7.2 Unit of Measure
1.1.7.3 Payment Item
1.2 UNIT PRICE PAYMENT ITEMS
1.2.1 PROGRESS PHOTOGRAPHS
1.2.1.1 Measurement and Payment
1.2.1.2 Unit of Measure
1.2.1.3 Payment Items
1.2.2 BITUMINOUS PAVEMENT CONSTRUCTION
1.2.2.1 Measurement and Payment
1.2.2.2 Unit of Measure
1.2.2.3 Payment Items
1.2.3 PARKING BUMPERS
1.2.3.1 Measurement and Payment
1.2.3.2 Unit of Measure
1.2.3.3 Payment Items
1.2.4 CHAIN LINK FENCE
1.2.4.1 Measurement and Payment
1.2.4.2 Unit of Measure
1.2.4.3 Payment Items
SECTION 01 22 00.00 10 Page 1
W911WN-12-R-0001 REVISED BY AMENDMENT 0001
1.2.5 SLIDING GATE
1.2.5.1 Measurement and Payment
1.2.5.2 Unit of Measure
1.2.5.3 Payment Items
1.2.6 CONCRETE SIDEWALK
1.2.6.1 Measurement and Payment
1.2.6.2 Unit of Measure
1.2.6.3 Payment Items
-- End of Section Table of Contents --
SECTION 01 22 00.00 10 Page 2
SECTION 01 22 00.00 10
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 LUMP SUM PAYMENT ITEMS
Payment items for the work of this contract for which contract lump sum payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, shall be included in the listed lump sum item most closely associated with the work involved. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.1.1 EROSION AND SEDIMENT CONTROLS
1.1.1.1 Payment
This work is specified in Section 01 57 23.00 10 STORM WATER POLLUTION PREVENTION MEASURES. Payment will be made for costs associated with furnishing, installing, maintaining and removing sediment and erosion controls measures; including but not limited to silt/filter fabric fence/sock, filter bags, dewatering, dust control, etc.; as shown on the drawings or as defined in the Erosion and Sediment Control Plan. Price shall include all materials, labor, equipment, and supplies associated with this work.
1.1.1.2 Unit of Measure
Unit of measure: Lump Sum
1.1.1.3 Payment Items
0003 - Erosion and Sediment Controls
1.1.2 DESIGN AND CERTIFICATION OF BUILDING
1.1.2.1 Payment
This work is specified in Section 01 11 00 PERFORMANCE WORK STATEMENT and Section 26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS. Payment will be made for costs associated with the design and certification of the new permanent office building including, but not limited to, permits, inspections, foundation design, structure design and building layout.
Payment shall also include all electrical and mechanical design including;
but not limited to; water/sewer/gas utilities, HVAC, electrical wiring, panels, breakers, switches, receptacles, lighting, etc.
Payment of 75% of the lump sum will be made after initial submittal of shop
SECTION 01 22 00.00 10 Page 3 drawings and design. Remaining 25% will be paid after approval and certification of shop drawings and design.
1.1.2.2 Unit of Measure
Unit of measure: Lump Sum
1.1.2.3 Payment Items
0004 - Design and Certification of New Permanent Office Building
1.1.3 CONSTRUCTION OF BUILDING
1.1.3.1 Payment
This work is specified in Section 01 11 00 PERFORMANCE WORK STATEMENT and Section 26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS. Payment will be made for costs associated with the the construction of the foundation, framing , structure and all interior and exterior features of the new building; including but not limited to; excavation for the foundation and footers, foundation aggregate base, foundation drains, formwork and concrete placement for foundation, erection of building framing structure and siding, roofing, windows and doors, finishes on walls and floors, drop ceiling, signage, kitchen cabinets and appliances, plumbing fixtures, lighting fixtures, mechanical and electrical work, utilities within 5-feet of the building, and any other work related to the building construction. Price shall include all materials, labor, equipment, and supplies associated with this work.
1.1.3.2 Unit of Measure
Unit of measure: Lump Sum
1.1.3.3 Payment Items
Item 0005 - Construction of New Permanent Office Building
1.1.4 PAVEMNT MARKINGS
1.1.4.1 Payment
This work is specified in Section 32 17 24.00 10 PAVEMENT MARKINGS.
Payment will be made for costs associated with surface preparation, protection and placement of pavement markings of width, color and locations indicated in the contract drawings, details and specifications. Price shall include all materials, labor, equipment, and supplies associated with this work.
1.1.4.2 Unit of Measure
Unit of measure: Lump Sum
1.1.4.3 Payment Item
Item 0008 - Paint Pavement Lines/Markings
SECTION 01 22 00.00 10 Page 4
1.1.5 RESTORATION OF NON-PAVED AREA
1.1.5.1 Payment
This work is specified in Section 01 11 00 PERFORMANCE WORK STATEMENT and Section 32 92 19 SEEDING. Payment will be made for costs associated with removal and disposal of aggregate base in this area, furnishing acceptable topsoil (if not stockpiled onsite), preparation of indicated areas, placement of topsoil to the required depth, mixing in indicated soil supplements, and seeding and mulching of all disturbed areas, as shown on drawings. Price shall include all materials, labor, equipment, and supplies associated with this work.
1.1.5.2 Unit of Measure
Unit of measure: Lump Sum
1.1.5.3 Payment Item
Item 0013 - Restoration of Non-Paved Area
1.1.6 MECHANICAL WORK
1.1.6.1 Payment
This work is specified in Section 01 11 00 PERFORMANCE WORK STATEMENT.
Payment will be made for costs associated with providing water, sewage, and gas lines to new building from existing nearby utilities, as shown on drawings. Cost shall not include any utility/mechanical work done within 5-FT of building. Payment shall include any excavation, pipe installation/testing, and backfill placement for new water service line, sewer line, manholes, and gas line outside of the new building. Price shall include all materials, labor, equipment, and supplies associated with this work.
1.1.6.2 Unit of Measure
Unit of measure: Lump Sum
1.1.6.3 Payment Item
Item 0014 - Mechanical Utilities & Site Workk
1.1.7 ELECTRICAL WORK
1.1.7.1 Payment
This work is specified in Section 01 11 00 PERFORMANCE WORK STATEMENT and Section 26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS. Payment will be made for costs associated with providing electrical power to new building and parking area from existing nearby power pole, as shown on drawings. Cost shall not include any utility/electrical work done within 5-FT of building. Payment shall include overhead power lines, wood pole, all conduits and circuit wiring, handhole, concrete encasement, parking area lighting, cables, and all required grounding. Price shall include all materials, labor, equipment, and supplies associated with this work.
SECTION 01 22 00.00 10 Page 5
1.1.7.2 Unit of Measure
Unit of measure: Lump Sum
1.1.7.3 Payment Item
Item 0015 - Electrical Utilities, Site Work & Parking Lighting
1.2 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
1.2.1 PROGRESS PHOTOGRAPHS
1.2.1.1 Measurement and Payment
This work is specified in Section 01 32 33 DIGITAL PROGRESS IMAGES.
Payment will be made for costs associated with furnishing monthly digital progress images, as specified. Price shall include all materials, labor, equipment, and supplies associated with this work.
Measurement will be made of the number of sets of photographs taken and delivered to the Contracting Officer as approved or directed by the Contracting Officer or authorized representative. Each set shall consist of all specified hard copies and electronic copies of each photographic session as specified.
1.2.1.2 Unit of Measure
Unit of measure: Sets
1.2.1.3 Payment Items
Item 0002 - Digital Progress Images
1.2.2 BITUMINOUS PAVEMENT CONSTRUCTION
1.2.2.1 Measurement and Payment
This work is specified in Section 32 22 16 BITUMINOUS PAVEMENT CONSTRUCTION; and shall comply with PDT 408, Item 305 for Bituminous Concrete Base Course. Payment will be made for costs associated with the construction of new bituminous pavement parking, as shown on drawings.
Payment shall also include placement, rolling and compaction, and finishing of the materials to the depth specified in the contract drawings. Price shall include all materials, labor, equipment, and supplies associated with this work. Payment for the Bituminous Prime Coat shall be included in the Bituminous Binder Course payment item. Payment for the Bituminous Tack Coat shall be included in the Bituminous Wearing Course payment item.
Measurement for pavement will be the actual area of surface constructed and
SECTION 01 22 00.00 10 Page 6 accepted.
1.2.2.2 Unit of Measure
Unit of measure: Square Yard
1.2.2.3 Payment Items
Item 0006 - Bituminous Wearing Course, 1-1/2"
Item 0007 - Bituminous Binder Course, 2-1/2"
1.2.3 PARKING BUMPERS
1.2.3.1 Measurement and Payment
This work is specified in Section 32 30 00 INCIDENTAL CONSTRUCTION.
Payment will be made for costs associated with the removal and disposal of existing parking bumpers; and furnishing and installing precast concrete parking bumpers at designated parking areas. Price shall include all materials, labor, equipment, and supplies associated with this work.
Measurement for payment shall be by the actual amount of parking bumpers installed.
1.2.3.2 Unit of Measure
Unit of measure: Each
1.2.3.3 Payment Items
Item 0009 - Parking Bumpers/Wheelstops
1.2.4 CHAIN LINK FENCE
1.2.4.1 Measurement and Payment
This work is specified in Section 32 31 13.53 CHAIN LINK FENCES AND GATES.
Payment will be made for costs associated with furnishing and installing new chain link fence, including all appurtenances and hardware for the execution of this work. Price shall include all materials, labor, equipment, and supplies associated with this work.
Measurement for payment shall be by the length of fence installed and accepted by the Contracting Officer.
1.2.4.2 Unit of Measure
Unit of measure: Lineal Foot
1.2.4.3 Payment Items
Item 0010 - Chain Link Fence, 7' High
1.2.5 SLIDING GATE
1.2.5.1 Measurement and Payment
This work is specified in Section 32 31 13.53 CHAIN LINK FENCES AND GATES.
SECTION 01 22 00.00 10 Page 7
Payment will be made for costs associated with furnishing and installing new vehicular gate, including all appurtenances and hardware for the execution of this work, as specified and as shown on the contract drawings. Price shall include all materials, labor, equipment, and supplies associated with this work.
Measurement for payment shall be by the actual number of gates installed.
1.2.5.2 Unit of Measure
Unit of measure: Each
1.2.5.3 Payment Items
Item 0011 - Vehiculat Slide Gate, 25' Wide
1.2.6 CONCRETE SIDEWALK
1.2.6.1 Measurement and Payment
This work is specified in Section 32 16 13 CONCRETE SIDEWALKS. Payment will be made for costs associated with the construction of new concrete sidewalk including, but not be limited to, excavation, subbase placement, concrete slab, welded wire fabric, expansion joints, and all other appurtenances and incidentals complete in place as shown on the contract drawings. Price shall include all materials, labor, equipment, and supplies associated with this work.
Measurement for payment will be made based on the actual volume of concrete sidewalk constructed and accepted.
1.2.6.2 Unit of Measure
Unit of measure: Cubic Yard
1.2.6.3 Payment Items
Item 0012 - Concrete Sidewalk
-- End of Section --
SECTION 01 22 00.00 10 Page 8
| 01 22 00.00 10 - MEASUREMENT AND PAYMENT |
| 01 22 00.00 10 - MEASUREMENT AND PAYMENT |
| PART 1 GENERAL |
| 1.1 LUMP SUM PAYMENT ITEMS |
| 1.1.1 EROSION AND SEDIMENT CONTROLS |
| 1.1.1.1 Payment |
| 1.1.1.2 Unit of Measure |
| 1.1.1.3 Payment Items |
| 1.1.2 DESIGN AND CERTIFICATION OF BUILDING |
| 1.1.2.1 Payment |
| 1.1.2.2 Unit of Measure |
| 1.1.2.3 Payment Items |
| 1.1.3 CONSTRUCTION OF BUILDING |
| 1.1.3.1 Payment |
| 1.1.3.2 Unit of Measure |
| 1.1.3.3 Payment Items |
| 1.1.4 PAVEMNT MARKINGS |
| 1.1.4.1 Payment |
| 1.1.4.2 Unit of Measure |
| 1.1.4.3 Payment Item |
| 1.1.5 RESTORATION OF NON-PAVED AREA |
| 1.1.5.1 Payment |
| 1.1.5.2 Unit of Measure |
| 1.1.5.3 Payment Item |
| 1.1.6 MECHANICAL WORK |
| 1.1.6.1 Payment |
| 1.1.6.2 Unit of Measure |
| 1.1.6.3 Payment Item |
| 1.1.7 ELECTRICAL WORK |
| 1.1.7.1 Payment |
| 1.1.7.2 Unit of Measure |
| 1.1.7.3 Payment Item |
| 1.2 UNIT PRICE PAYMENT ITEMS |
| 1.2.1 PROGRESS PHOTOGRAPHS |
| 1.2.1.1 Measurement and Payment |
| 1.2.1.2 Unit of Measure |
| 1.2.1.3 Payment Items |
| 1.2.2 BITUMINOUS PAVEMENT CONSTRUCTION |
| 1.2.2.1 Measurement and Payment |
| 1.2.2.2 Unit of Measure |
| 1.2.2.3 Payment Items |
| 1.2.3 PARKING BUMPERS |
| 1.2.3.1 Measurement and Payment |
| 1.2.3.2 Unit of Measure |
| 1.2.3.3 Payment Items |
| 1.2.4 CHAIN LINK FENCE |
| 1.2.4.1 Measurement and Payment |
| 1.2.4.2 Unit of Measure |
| 1.2.4.3 Payment Items |
| 1.2.5 SLIDING GATE |
| 1.2.5.1 Measurement and Payment |
| 1.2.5.2 Unit of Measure |
| 1.2.5.3 Payment Items |
| 1.2.6 CONCRETE SIDEWALK |
| 1.2.6.1 Measurement and Payment |
| 1.2.6.2 Unit of Measure |
| 1.2.6.3 Payment Items |
File details come from the government source that posted it. Updated .