Bid Abstract - W911WN-10-B-0006 - EMSWORTH BACK CHANNEL SCOUR PROTECTION AND LEFT ABUTMENT STABILIZATION.xls
XLS spreadsheet 64 KB Posted
- Solicitation number
- W911WN10B0006
About this file
Detailed Abstract of Bids
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Summary Bid Schedule
| Emsworth Locks and Dams, Ohio River | |||||||||||
| Back Channel Left Abutment Stabilization and Scour Protection | |||||||||||
| Solicitation No. W911WN-10-B-0006 | |||||||||||
| Trumbull Corporation | Lakeshore Engineering Services, Inc. | Kokosing Construction Company, Inc. | Brayman Construction Corporation | ||||||||
| ITEM | DESCRIPTION | QUANTITY | U/M | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount |
| 0001 | ARRA Funded Items FFP LEFT BAY ABUTMENT STABILIZATION AND SCOUR PROTECTION IN GATE BAYS 12 THROUGH 14 | 1 | LUMP SUM | $3,406,781.00 | $3,406,781.00 | $20,025,100.00 | $20,025,100.00 | ||||
| 0001AA | ARRA - 'REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS, ARRA FUNDED ITEMS | 1 | LUMP SUM | $80,000.00 | $80,000.00 | $437,777.00 | $437,777.00 | $125,000.00 | $125,000.00 | $57,000.00 | $57,000.00 |
| 0001AB | ARRA - MOBILIZATION AND DEMOBILIZATION | 1 | LUMP SUM | $652,498.88 | $652,498.88 | $3,183,637.00 | $3,183,637.00 | $1,500,000.00 | $1,500,000.00 | $430,000.00 | $430,000.00 |
| 0001AC | ARRA - DIGITAL PROGRESS IMAGES | 20 | SETS | $375.00 | $7,500.00 | $398.00 | $7,960.00 | $500.00 | $10,000.00 | $500.00 | $10,000.00 |
| 0001AD | ARRA - PROJECT SIGNS | 1 | LUMP SUM | $3,000.00 | $3,000.00 | $11,356.00 | $11,356.00 | $6,000.00 | $6,000.00 | $5,000.00 | $5,000.00 |
| 0001AE | ARRA - SCOUR PROTECTION, DEMONSTRATION PROJECT | 1 | LUMP SUM | $1,000,000.00 | $1,000,000.00 | $306,611.00 | $306,611.00 | $600,000.00 | $600,000.00 | $950,000.00 | $950,000.00 |
| 0001AF | ARRA - SCOUR PROTECTION, REMOVAL, STAGING, AND REUSE OF EXISTING DERRICK STONE | 5,265 | CUBIC YARDS | $180.00 | $947,700.00 | $270.00 | $1,421,550.00 | $200.00 | $1,053,000.00 | $150.00 | $789,750.00 |
| 0001AG | ARRA - SCOUR PROTECTION, REMOVAL, STAGING, AND REUSE OF EXISTING 3'-0" GRADED STONE LAYER | 2,015 | CUBIC YARDS | $125.00 | $251,875.00 | $254.00 | $511,810.00 | $30.00 | $60,450.00 | $55.00 | $110,825.00 |
| 0001AH | ARRA - SCOUR PROTECTION, DREDGING FOR 3H:1V SLOPE AND DISPOSAL | 28,535 | CUBIC YARDS | $55.00 | $1,569,425.00 | $100.00 | $2,853,500.00 | $40.00 | $1,141,400.00 | $8.00 | $228,280.00 |
| 0001AJ | ARRA - SCOUR PROTECTION, GEOGRID REINFORCEMENT | 3,750 | SQUARE YARDS | $38.00 | $142,500.00 | $75.00 | $281,250.00 | $95.00 | $356,250.00 | $35.00 | $131,250.00 |
| 0001AK | ARRA - SCOUR PROTECTION, BEDDING MATERIAL | 1,825 | CUBIC YARDS | $190.00 | $346,750.00 | $107.00 | $195,275.00 | $150.00 | $273,750.00 | $55.00 | $100,375.00 |
| 0001AL | ARRA - SCOUR PROTECTION, FURNISH AND INSTALL GROUT BAGS WITH ACCESSORIES AND GROUT INFILL | 5,195 | CUBIC YARDS | $800.00 | $4,156,000.00 | $962.00 | $4,997,590.00 | $1,450.00 | $7,532,750.00 | $715.00 | $3,714,425.00 |
| 0001AM | ARRA - SCOUR PROTECTION, CAST-IN-PLACE APRON TIE-IN ELEMENT | 250 | CUBIC YARDS | $3,420.00 | $855,000.00 | $7,779.00 | $1,944,750.00 | $2,500.00 | $625,000.00 | $2,800.00 | $700,000.00 |
| 0001AN | ARRA - SCOUR PROTECTION, GROUT BAG FLANK PROTECTION | 3 | EACH | $100,000.00 | $300,000.00 | $10,221.00 | $30,663.00 | $65,000.00 | $195,000.00 | $60,000.00 | $180,000.00 |
| 0001AP | ARRA - EXISTING DAM APRON, DRILLING OF GROUT HOLES | 75 | LINEAR FEET | $880.00 | $66,000.00 | $89.00 | $6,675.00 | $325.00 | $24,375.00 | $800.00 | $60,000.00 |
| 0001AQ | ARRA - EXISTING DAM APRON, DRILLING OF VENT HOLES | 15 | LINEAR FEET | $250.00 | $3,750.00 | $112.00 | $1,680.00 | $225.00 | $3,375.00 | $800.00 | $12,000.00 |
| 0001AR | ARRA - EXISTING DAM APRON, GROUT PLACEMENT | 75 | CUBIC YARDS | $2,000.00 | $150,000.00 | $886.00 | $66,450.00 | $700.00 | $52,500.00 | $200.00 | $15,000.00 |
| 0001AS | ARRA - 'INSTRUMENTATION - INSTALLATION, MONITORING, DATA REDUCTION AND INTERPRETATION, AND REPORTING | 1 | LUMP SUM | $25,000.00 | $25,000.00 | $136,294.00 | $136,294.00 | $50,000.00 | $50,000.00 | $10,000.00 | $10,000.00 |
| 0001AT | ARRA - LAYDOWN AND STAGING AREA | 1 | LUMP SUM | $150,000.00 | $150,000.00 | $96,526.00 | $96,526.00 | $869,490.00 | $869,490.00 | $20,000.00 | $20,000.00 |
| 0001AU | ARRA - DEMOLITION OF POSTS AND CABLES | 70 | LINEAR FEET | $50.00 | $3,500.00 | $155.00 | $10,850.00 | $25.00 | $1,750.00 | $50.00 | $3,500.00 |
| 0001AV | ARRA - EARTHWORK - WORK PLATFORM BEHIND ABUTMENT WALL | 214 | CUBIC YARDS | $250.00 | $53,500.00 | $1,363.00 | $291,682.00 | $50.00 | $10,700.00 | $20.00 | $4,280.00 |
| 0001AW | ARRA - WORK PLATFORM, AGGREGATE BASE COURSE | 320 | SQUARE YARDS | $70.00 | $22,400.00 | $746.00 | $238,720.00 | $75.00 | $24,000.00 | $30.00 | $9,600.00 |
| 0001AX | ARRA - WORK PLATFORM RESTORATION, GROUTED R-3 RIPRAP OVER FS-1 FILTER STONE ON PLATFORM | 320 | SQUARE YARDS | $175.00 | $56,000.00 | $515.00 | $164,800.00 | $120.00 | $38,400.00 | $85.00 | $27,200.00 |
| 0001AY | ARRA - WORK PLATFORM RESTORATION, TRENCH DRAIN | 130 | LINEAR FEET | $85.00 | $11,050.00 | $568.00 | $73,840.00 | $40.00 | $5,200.00 | $30.00 | $3,900.00 |
| 0001AZ | ARRA - NON-CONTAMINATED MATERIAL, TEMPORARY STORAGE | 110 | CUBIC YARDS | $140.00 | $15,400.00 | $568.00 | $62,480.00 | $100.00 | $11,000.00 | $85.00 | $9,350.00 |
| 0001BA | ARRA - CONTAMINATED MATERIAL, TEMPORARY STORAGE AND OFFSITE DISPOSAL | 107 | CUBIC YARDS | $415.00 | $44,405.00 | $228.00 | $24,396.00 | $100.00 | $10,700.00 | $110.00 | $11,770.00 |
| 0001BB | ARRA - CHEMICAL DATA QUALITY CONTROL | 1 | LUMP SUM | $20,000.00 | $20,000.00 | $85,170.00 | $85,170.00 | $90,000.00 | $90,000.00 | $7,500.00 | $7,500.00 |
| 0001BC | ARRA - DRILLING HOLES IN CONCRETE FOR 7-INCH DIAMETER MICROPILES | 468 | LINEAR FEET | $100.00 | $46,800.00 | $169.00 | $79,092.00 | $100.00 | $46,800.00 | $325.00 | $152,100.00 |
| 0001BD | ARRA - DRILLING HOLES IN SOIL FOR 7-INCH DIAMETER MICROPILES | 544 | LINEAR FEET | $100.00 | $54,400.00 | $114.00 | $62,016.00 | $100.00 | $54,400.00 | $100.00 | $54,400.00 |
| 0001BE | ARRA - DRILLING HOLES IN ROCK FOR 7-INCH DIAMETER MICROPILES | 428 | LINEAR FEET | $100.00 | $42,800.00 | $171.00 | $73,188.00 | $100.00 | $42,800.00 | $175.00 | $74,900.00 |
| 0001BF | ARRA - PREGROUTING HOLES (ROCK SECTION) FOR MICROPILES | 257 | BAGS | $50.00 | $12,850.00 | $29.00 | $7,453.00 | $50.00 | $12,850.00 | $65.00 | $16,705.00 |
| 0001BG | ARRA - REDRILLING GROUTED HOLES FOR WATERTIGHTNESS TESTING FOR 7-INCH DIAMETER MICROPILES | 428 | LINEAR FEET | $100.00 | $42,800.00 | $57.00 | $24,396.00 | $75.00 | $32,100.00 | $200.00 | $85,600.00 |
| 0001BH | ARRA - WATERTIGHTNESS TESTING FOR 7-INCH DIAMETER MICROPILES | 20 | EACH | $500.00 | $10,000.00 | $1,136.00 | $22,720.00 | $250.00 | $5,000.00 | $200.00 | $4,000.00 |
| 0001BJ | ARRA - 7-INCH DIAMETER MICROPILES AT LANDSIDE | 7 | EACH | $10,000.00 | $70,000.00 | $17,034.00 | $119,238.00 | $6,000.00 | $42,000.00 | $9,500.00 | $66,500.00 |
| 0001BK | ARRA - 7-INCH DIAMETER MICROPILES AT RIVERSIDE | 13 | EACH | $8,500.00 | $110,500.00 | $17,034.00 | $221,442.00 | $7,000.00 | $91,000.00 | $10,000.00 | $130,000.00 |
| 0001BL | ARRA - ABANDONMENT OF HOLES FOR MICROPILES AT LANDSIDE | 2 | EACH | $2,500.00 | $5,000.00 | $2,839.00 | $5,678.00 | $2,000.00 | $4,000.00 | $7,500.00 | $15,000.00 |
| 0001BM | ARRA - ABANDONMENT OF HOLES FOR MICROPILES AT RIVERSIDE | 2 | EACH | $2,500.00 | $5,000.00 | $2,839.00 | $5,678.00 | $2,000.00 | $4,000.00 | $7,500.00 | $15,000.00 |
| 0001BN | ARRA - CLEAN OUT EXISTING WEEP HOLES THROUGH ABUTMENT WALL | 4 | EACH | $1,700.00 | $6,800.00 | $568.00 | $2,272.00 | $3,000.00 | $12,000.00 | $500.00 | $2,000.00 |
| 0001BP | ARRA - DRILL NEW 4-INCH DIAMETER WEEP HOLES THROUGH ABUTMENT WALL | 4 | EACH | $3,600.00 | $14,400.00 | $653.00 | $2,612.00 | $5,000.00 | $20,000.00 | $3,500.00 | $14,000.00 |
| 0001BQ | ARRA - ABUTMENT COMBINATION WALL, 48-INCH DIAMETER BY 1/2-INCH THICK PIPE PILE/CASING, TOP EL. 695.0 (K1 TO K9) | 342 | LINEAR FEET | $3,000.00 | $1,026,000.00 | $313.00 | $107,046.00 | $850.00 | $290,700.00 | $600.00 | $205,200.00 |
| 0001BR | ARRA - ABUTMENT COMBINATION WALL, 48-INCH DIAMETER BY 1/2-INCH THICK PIPE PILE/CASING, TOP EL. 700.0 (K10 TO K24) | 645 | LINEAR FEET | $2,000.00 | $1,290,000.00 | $313.00 | $201,885.00 | $850.00 | $548,250.00 | $600.00 | $387,000.00 |
| 0001BS | ARRA - ABUTMENT COMBINATION WALL, PZC 18 METAL SHEET PILING, TOP EL. 695.0 (K1 TO K9) | 798 | LINEAR FEET | $250.00 | $199,500.00 | $142.00 | $113,316.00 | $250.00 | $199,500.00 | $125.00 | $99,750.00 |
| 0001BT | ARRA - ABUTMENT COMBINATION WALL, PZC 18 METAL SHEET PILING, TOP EL. 700.0 (K10 TO K24) | 1,204 | LINEAR FEET | $225.00 | $270,900.00 | $142.00 | $170,968.00 | $250.00 | $301,000.00 | $120.00 | $144,480.00 |
| 0001BU | ARRA - ABUTMENT COMBINATION WALL, HP12X53 END PILE | 38 | LINEAR FEET | $400.00 | $15,200.00 | $228.00 | $8,664.00 | $1,000.00 | $38,000.00 | $120.00 | $4,560.00 |
| 0001BV | ARRA - ABUTMENT COMBINATION WALL, W33X263 KING PILE, TIP EL. 635.0 (PILES K1 TO K6 AND K19 TO K24) | 12 | EACH | $20,000.00 | $240,000.00 | $55,764.00 | $669,168.00 | $15,000.00 | $180,000.00 | $9,000.00 | $108,000.00 |
| 0001BW | ARRA - ABUTMENT COMBINATION WALL, STIFFENED W33x263 KING PILE, TIP EL. 635.0 (PILES K7 TO K9 AND K14 TO K18) | 8 | EACH | $25,000.00 | $200,000.00 | $56,568.00 | $452,544.00 | $20,000.00 | $160,000.00 | $12,000.00 | $96,000.00 |
| 0001BX | ARRA - ABUTMENT COMBINATION WALL, STIFFENED W33x263 KING PILE, TIP EL. 631.0 (PILES K10 TO K13) | 4 | EACH | $27,000.00 | $108,000.00 | $58,438.00 | $233,752.00 | $21,000.00 | $84,000.00 | $12,000.00 | $48,000.00 |
| 0001BY | ARRA - ABUTMENT COMBINATION WALL, 42-INCH DIAMETER ROCK SOCKET | 544 | LINEAR FEET | $600.00 | $326,400.00 | $228.00 | $124,032.00 | $500.00 | $272,000.00 | $240.00 | $130,560.00 |
| 0001BZ | ARRA - ABUTMENT COMBINATION WALL, CONCRETE FOR SOCKETED PIPE PILES | 637 | CUBIC YARDS | $700.00 | $445,900.00 | $625.00 | $398,125.00 | $500.00 | $318,500.00 | $525.00 | $334,425.00 |
| 0001CA | ARRA - ABUTMENT COMBINATION WALL, REINFORCED CONCRETE CAP/SLAB | 98 | CUBIC YARDS | $1,200.00 | $117,600.00 | $3,407.00 | $333,886.00 | $750.00 | $73,500.00 | $600.00 | $58,800.00 |
| 0001CB | ARRA - DRILLING CASED HOLES IN CONCRETE FOR ROCK ANCHORS | 94 | LINEAR FEET | $90.00 | $8,460.00 | $130.00 | $12,220.00 | $85.00 | $7,990.00 | $525.00 | $49,350.00 |
| 0001CC | ARRA - DRILLING CASED HOLES IN SOIL FOR ROCK ANCHORS | 116 | LINEAR FEET | $85.00 | $9,860.00 | $57.00 | $6,612.00 | $70.00 | $8,120.00 | $125.00 | $14,500.00 |
| 0001CD | ARRA - DRILLING HOLES IN ROCK FOR ROCK ANCHORS (PARTLY CASED) | 522 | LINEAR FEET | $85.00 | $44,370.00 | $86.00 | $44,892.00 | $50.00 | $26,100.00 | $100.00 | $52,200.00 |
| 0001CE | ARRA - PREGROUTING HOLES (BOND ZONE) FOR ROCK ANCHORS | 313 | BAGS | $40.00 | $12,520.00 | $114.00 | $35,682.00 | $25.00 | $7,825.00 | $60.00 | $18,780.00 |
| 0001CF | ARRA - REDRILLING GROUTED HOLES FOR WATERTIGHTNESS TESTING OF ROCK ANCHORS | 522 | LINEAR FEET | $50.00 | $26,100.00 | $114.00 | $59,508.00 | $50.00 | $26,100.00 | $95.00 | $49,590.00 |
| 0001CG | ARRA - WATERTIGHTNESS TESTING FOR ROCK ANCHORS | 6 | EACH | $500.00 | $3,000.00 | $568.00 | $3,408.00 | $250.00 | $1,500.00 | $300.00 | $1,800.00 |
| 0001CH | ARRA - FURNISH AND INSTALL ROCK ANCHORS (INCLUDING ALL COMPONENTS) | 6 | EACH | $45,000.00 | $270,000.00 | $17,034.00 | $102,204.00 | $40,000.00 | $240,000.00 | $35,000.00 | $210,000.00 |
| 0001CJ | ARRA - PERFORMANCE TESTS FOR ROCK ANCHORS (INCLUDING ALL TEST COMPONENTS, RECORDS, DATA REDUCTION, REPORTING, RETESTING, AND LIFTOFF AND LOCKOFF) | 1 | EACH | $6,000.00 | $6,000.00 | $1,136.00 | $1,136.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 |
| 0001CK | ARRA - PROOF TESTS FOR ROCK ANCHORS (INCLUDING ALL TEST COMPONENTS, RECORDS, DATA REDUCTION, REPORTING, RETESTING, AND LIFTOFF AND LOCKOFF) | 5 | EACH | $2,500.00 | $12,500.00 | $852.00 | $4,260.00 | $2,000.00 | $10,000.00 | $2,000.00 | $10,000.00 |
| 0001CL | ARRA - ABUTMENT COMBINATION WALL, REPLACE SALVAGED GRADED RIPRAP AND DERRICK STONE AGAINST ABUTMENT SECTION AND BEHIND SLOPE SECTION OF COMBINATION WALL | 1 | LUMP SUM | $25,000.00 | $25,000.00 | $283,899.00 | $283,899.00 | $50,000.00 | $50,000.00 | $35,000.00 | $35,000.00 |
| 0001CM | ARRA - RESTORATION OF WORK PLATFORM AND DISTURBED AREAS | 1 | LUMP SUM | $25,000.00 | $25,000.00 | $119,238.00 | $119,238.00 | $20,000.00 | $20,000.00 | $3,500.00 | $3,500.00 |
| 0001CN | ARRA - ABUTMENT WALL REPAIR AND ROCK ANCHOR RECESSES, CONCRETE REMOVAL AND OTHER DEMOLITION | 139 | CUBIC YARDS | $1,100.00 | $152,900.00 | $4,494.00 | $624,666.00 | $600.00 | $83,400.00 | $2,000.00 | $278,000.00 |
| 0001CP | ARRA - ABUTMENT WALL REPAIR, DOWELED AND REINFORCED CONCRETE REPAIRS, ROCK ANCHOR ENCASEMENT, AND MISCELLANEOUS CONCRETE REPAIR WORK | 159 | CUBIC YARDS | $2,500.00 | $397,500.00 | $3,036.00 | $482,724.00 | $2,000.00 | $318,000.00 | $2,000.00 | $318,000.00 |
| 0001CQ | ARRA - ABUTMENT WALL REPAIR, INSTALL NEW HANDRAIL | 122 | LINEAR FEET | $250.00 | $30,500.00 | $298.00 | $36,356.00 | $225.00 | $27,450.00 | $200.00 | $24,400.00 |
| 0001CR | ARRA - DISPOSAL OF EXCESS NON-CONTAMINATED MATERIAL AT COMMERCIALLY AVAILABLE, PERMITTED FACILITY | 1,645 | CUBIC YARDS | $190.00 | $312,550.00 | $101.00 | $166,145.00 | $125.00 | $205,625.00 | $15.00 | $24,675.00 |
| 0001CS | ARRA - ALTERNATE 1, DISPOSAL OF NON-CONTAMINATED MATERIAL AT COMMERCIALLY AVAILABLE, PERMITED FACILITY | 27,000 | CUBIC YARDS | $27.00 | $729,000.00 | $57.00 | $1,539,000.00 | No Bid | No Bid | No Bid | No Bid |
| 0001CT | ARRA - ALTERNATE 2, DISPOSAL OF NON-CONTAMINATED MATERIAL AT PHILLIS ISLAND MAIN CHANNEL AND GEORGETOWN ISLAND MAIN CHANNEL DISPOSAL SITES | 27,000 | CUBIC YARDS | No Bid | No Bid | No Bid | No Bid | $55.00 | $1,485,000.00 | $13.00 | $351,000.00 |
| TOTAL, BASE CONTRACT, ARRA-FUNDED ITEMS 0001AA THROUGH 0001CR, INCLUSIVE AND DISPOSAL ALTERNATE 1 ITEM 0001CS | $17,659,363.88 | $27,811,194.00 | No Bid | No Bid | |||||||
| TOTAL, BASE CONTRACT, ARRA-FUNDED ITEMS 0001AA THROUGH 0001CR, INCLUSIVE AND DISPOSAL ALTERNATE 2 ITEM 0001CT | No Bid | No Bid | $20,024,600.00 | $11,293,780.00 | |||||||
| 0002 | AWARDABLE OPTION - NON-ARRA-FUNDED ITEMS - SCOUR PROTECTION IN GATE BAYS 9 THROUGH 11 | 1 | $3,406,781.00 | $3,406,781.00 | $11,524,900.00 | $11,524,900.00 | $0.00 | ||||
| 0002AA | REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS, NON-ARRA FUNDED ITEMS | 1 | $53,000.00 | $53,000.00 | $269,728.00 | $269,728.00 | $80,000.00 | $80,000.00 | $30,000.00 | $30,000.00 | |
| 0002AB | SCOUR PROTECTION, REMOVAL, STAGING, AND REUSE OF EXISTING DERRICK STONE | 4,815 | CUBIC YARDS | $170.00 | $818,550.00 | $228.00 | $1,097,820.00 | $200.00 | $963,000.00 | $130.00 | $625,950.00 |
| 0002AC | SCOUR PROTECTION, REMOVAL, STAGING, AND REUSE OF EXISTING 3'-0" GRADED STONE LAYER | 1,530 | CUBIC YARDS | $115.00 | $175,950.00 | $228.00 | $348,840.00 | $30.00 | $45,900.00 | $45.00 | $68,850.00 |
| 0002AD | SCOUR PROTECTION, DREDGING FOR 3H:1V SLOPE AND DISPOSAL | 21,695 | CUBIC YARDS | $55.00 | $1,193,225.00 | $103.00 | $2,234,585.00 | $40.00 | $867,800.00 | $8.00 | $173,560.00 |
| 0002AE | SCOUR PROTECTION, GEOGRID REINFORCEMENT | 3,485 | SQUARE YARDS | $35.00 | $121,975.00 | $75.00 | $261,375.00 | $95.00 | $331,075.00 | $20.00 | $69,700.00 |
| 0002AF | SCOUR PROTECTION, BEDDING MATERIAL | 1,695 | CUBIC YARDS | $170.00 | $288,150.00 | $107.00 | $181,365.00 | $150.00 | $254,250.00 | $55.00 | $93,225.00 |
| 0002AG | SCOUR PROTECTION, FURNISH AND INSTALL GROUT BAGS WITH ACCESSORIES AND GROUT INFILL | 5,015 | CUBIC YARDS | $800.00 | $4,012,000.00 | $962.00 | $4,824,430.00 | $1,450.00 | $7,271,750.00 | $715.00 | $3,585,725.00 |
| 0002AH | SCOUR PROTECTION, CAST-IN-PLACE APRON TIE-IN ELEMENT | 260 | CUBIC YARDS | $3,400.00 | $884,000.00 | $8,158.00 | $2,121,080.00 | $2,500.00 | $650,000.00 | $1,200.00 | $312,000.00 |
| 0002AJ | SCOUR PROTECTION, GROUT BAG FLANK PROTECTION | 3 | EACH | $100,000.00 | $300,000.00 | $10,221.00 | $30,663.00 | $65,000.00 | $195,000.00 | $35,000.00 | $105,000.00 |
| 0002AK | EXISTING DAM APRON, DRILLING OF GROUT HOLES | 75 | LINEAR FEET | $800.00 | $60,000.00 | $284.00 | $21,300.00 | $325.00 | $24,375.00 | $800.00 | $60,000.00 |
| 0002AL | EXISTING DAM APRON, DRILLING OF VENT HOLES | 15 | LINEAR FEET | $225.00 | $3,375.00 | $284.00 | $4,260.00 | $225.00 | $3,375.00 | $800.00 | $12,000.00 |
| 0002AM | EXISTING DAM APRON, GROUT PLACEMENT | 75 | CUBIC YARDS | $1,750.00 | $131,250.00 | $886.00 | $66,450.00 | $700.00 | $52,500.00 | $160.00 | $12,000.00 |
| 0002AN | DISPOSAL OF EXCESS NON-CONTAMINATED MATERIAL AT COMMERCIALLY AVAILABLE, PERMITTED FACILITY | 3,695 | CUBIC YARDS | $190.00 | $702,050.00 | $97.00 | $358,415.00 | $125.00 | $461,875.00 | $15.00 | $55,425.00 |
| 0002AP | ALTERNATE 1, DISPOSAL OF NON-CONTAMINATED MATERIAL AT COMMERCIALLY AVAILABLE, PERMITED FACILITY | 18,000 | CUBIC YARDS | $27.00 | $486,000.00 | $63.00 | $1,134,000.00 | No Bid | No Bid | No Bid | No Bid |
| 0002AQ | ALTERNATE 2, DISPOSAL OF NON-CONTAMINATED MATERIAL AT PHILLIS ISLAND BACK CHANNEL AND GEORGETOWN ISLAND BACK CHANNEL DISPOSAL SITES | 18,000 | CUBIC YARDS | No Bid | No Bid | No Bid | No Bid | $18.00 | $324,000.00 | $7.00 | $126,000.00 |
| TOTAL, AWARDABLE OPTION, NON-ARRA FUNDED ITEMS 0002AA THROUGH 0002AN, INCLUSIVE AND DISPOSAL ALTERNATE 1 ITEM 0002CP | $9,229,525.00 | $16,361,092.00 | No Bid | No Bid | |||||||
| TOTAL, AWARDABLE OPTION, NON-ARRA FUNDED ITEMS 0002AA THROUGH 0002AN, INCLUSIVE AND DISPOSAL ALTERNATE 2 ITEM 0002CQ | No Bid | No Bid | $11,524,900.00 | $5,329,435.00 | |||||||
| Total Base Contract Plus Awardable Option, Items 0001AA thru 0002AQ | $26,888,888.88 | $44,172,286.00 | $31,549,500.00 | $16,623,215.00 |