Comparison of Bids
| EMSWORTH LOCKS AND DAMS | |||||||||
| MAIN CHANNEL REHABILITATION | |||||||||
| Joseph B. Fay | American Bridge | OCCI | |||||||
| ITEM | DESCRIPTION | Quantity | Unit | Unit Price | Total | Unit Price | Total | Unit Price | Total |
| BASE CONTRACT ITEMS | |||||||||
| 0001 | REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS, BASE CONTRACT | NOT TO EXCEED | $236,000.00 | $410,000.00 | $273,000.00 | ||||
| 0002 | MOBILIZATION AND DEMOBILIZATION | 1 | LS | JB | $3,000,000.00 | JB | $2,500,000.00 | JB | $980,000.00 |
| 0003 | MONTHLY PROGRESS IMAGES | 36 | SE | $130.00 | $4,680.00 | $150.00 | $5,400.00 | $500.00 | $18,000.00 |
| 0004 | COORDINATION AND MANAGEMENT OF BULKHEADS | 1 | LS | JB | $250,000.00 | JB | $100,000.00 | JB | $235,000.00 |
| 0005 | LAYDOWN AND STAGING AREA | 1 | LS | JB | $170,000.00 | JB | $500,000.00 | JB | $380,000.00 |
| 0006 | FENCE AND GATE MODIFICATION | 1 | LS | JB | $80,000.00 | JB | $25,000.00 | JB | $65,000.00 |
| 0007 | GOVERNMENT ROAD | 1 | LS | JB | $50,000.00 | JB | $20,000.00 | JB | $85,000.00 |
| 0008 | GOVERNMENT FACILITIES | 1 | LS | JB | $120,000.00 | JB | $250,000.00 | JB | $133,000.00 |
| 0009 | CONCRETE REMOVAL, PIERS 1 AND 9 | 22 | CY | $5,000.00 | $110,000.00 | $10,000.00 | $220,000.00 | $6,700.00 | $147,400.00 |
| 0010 | CONCRETE REMOVAL, PIERS 6 AND 7 | 32 | CY | $4,000.00 | $128,000.00 | $8,000.00 | $256,000.00 | $6,700.00 | $214,400.00 |
| 0011 | CONCRETE REMOVAL, PIERS 2 THRU 5, AND 8 | 56 | CY | $5,000.00 | $280,000.00 | $8,000.00 | $448,000.00 | $6,700.00 | $375,200.00 |
| 0012 | CONCRETE REPAIRS AND OTHER CONCRETE WORK, PIERS 1 AND 9 | 8 | CY | $12,000.00 | $96,000.00 | $10,000.00 | $80,000.00 | $4,000.00 | $32,000.00 |
| 0013 | CONCRETE REPAIRS AND OTHER CONCRETE WORK, PIERS 6 AND 7 | 25 | CY | $4,000.00 | $100,000.00 | $8,000.00 | $200,000.00 | $4,000.00 | $100,000.00 |
| 0014 | CONCRETE REPAIRS AND OTHER CONCRETE WORK, PIERS 2 THRU 5, AND 8 | 24 | CY | $10,000.00 | $240,000.00 | $8,000.00 | $192,000.00 | $4,000.00 | $96,000.00 |
| 0015 | SECOND PLACEMENT CONCRETE, PIERS 1 AND 9 | 2 | CY | $10,000.00 | $20,000.00 | $16,000.00 | $32,000.00 | $10,000.00 | $20,000.00 |
| 0016 | SECOND PLACEMENT CONCRETE, PIERS 6 AND 7 | 4 | CY | $10,000.00 | $40,000.00 | $16,000.00 | $64,000.00 | $10,000.00 | $40,000.00 |
| 0017 | SECOND PLACEMENT CONCRETE, PIERS 2 THRU 5, AND 8 | 10 | CY | $10,000.00 | $100,000.00 | $16,000.00 | $160,000.00 | $10,000.00 | $100,000.00 |
| 0018 | EMBEDDED METAL, PIERS 1 AND 9 | 1,410 | LB | $24.00 | $33,840.00 | $16.00 | $22,560.00 | $30.00 | $42,300.00 |
| 0019 | EMBEDDED METAL, PIERS 6 AND 7 | 2,815 | LB | $24.00 | $67,560.00 | $16.00 | $45,040.00 | $30.00 | $84,450.00 |
| 0020 | EMBEDDED METAL, PIERS 2 THRU 5, AND 8 | 7,040 | LB | $24.00 | $168,960.00 | $16.00 | $112,640.00 | $30.00 | $211,200.00 |
| 0021 | MISCELLANEOUS METAL, PIERS 1 AND 9 | 5,035 | LB | $34.00 | $171,190.00 | $15.00 | $75,525.00 | $30.00 | $151,050.00 |
| 0022 | MISCELLANEOUS METAL, PIERS 2 THRU 8 | 21,655 | LB | $34.00 | $736,270.00 | $15.00 | $324,825.00 | $30.00 | $649,650.00 |
| 0023 | DEMOLITION OF EXISTING MACHINERY HOUSES, PIERS 1 AND 9 | 2 | EA | $30,000.00 | $60,000.00 | $15,000.00 | $30,000.00 | $58,000.00 | $116,000.00 |
| 0024 | DEMOLITION OF EXISTING MACHINERY HOUSES, PIERS 2 THRU 8 | 7 | EA | $30,000.00 | $210,000.00 | $15,000.00 | $105,000.00 | $68,000.00 | $476,000.00 |
| 0025 | CONSTRUCT NEW MACHINERY HOUSES, PIERS 1 AND 9 | 2 | EA | $250,000.00 | $500,000.00 | $200,000.00 | $400,000.00 | $350,000.00 | $700,000.00 |
| 0026 | CONSTRUCT NEW MACHINERY HOUSES, PIERS 2 THRU 8 | 7 | EA | $300,000.00 | $2,100,000.00 | $250,000.00 | $1,750,000.00 | $380,000.00 | $2,660,000.00 |
| 0027 | DEMOLITION OF EXISTING LIFT GATES AND ASSOCIATED ITEMS, GATE BAYS 1 THRU 5, 7 AND 8 | 7 | EA | $100,000.00 | $700,000.00 | $100,000.00 | $700,000.00 | $106,000.00 | $742,000.00 |
| 0028 | MODIFICATION OF EXISTING LIFT GATE AND ASSOCIATED ITEMS, GATE BAY 6 | 1 | LS | $700,000.00 | $700,000.00 | $600,000.00 | $600,000.00 | $312,000.00 | $312,000.00 |
| 0029 | FURNISH NEW LIFT GATE AND ASSOCIATED ITEMS | 3 | EA | $1,200,000.00 | $3,600,000.00 | $1,700,000.00 | $5,100,000.00 | $1,680,000.00 | $5,040,000.00 |
| 0030 | INSTALL NEW LIFT GATE AND ASSOCIATED ITEMS, GATE BAYS 1 THRU 5, 7 AND 8 | 7 | EA | $400,000.00 | $2,800,000.00 | $250,000.00 | $1,750,000.00 | $627,857.00 | $4,394,999.00 |
| 0031 | FURNISH AND INSTALL NEW LIFT GATE OPERATING MACHINERY, GATES 1 THRU 8 | 8 | EA | $1,570,000.00 | $12,560,000.00 | $1,800,000.00 | $14,400,000.00 | $1,845,000.00 | $14,760,000.00 |
| 0032 | POWER, LIGHTING AND HVAC SYSTEMS | 1 | LS | $3,250,000.00 | $3,250,000.00 | $3,500,000.00 | $3,500,000.00 | $1,780,000.00 | $1,780,000.00 |
| 0033 | CONTROL AND INSTRUMENTATION SYSTEMS | 1 | LS | $280,000.00 | $280,000.00 | $5,000,000.00 | $5,000,000.00 | $2,500,000.00 | $2,500,000.00 |
| 0034 | NEW MAIN CHANNEL DAM ELECTRICAL SERVICE | 1 | LS | $16,000.00 | $16,000.00 | $1,500,000.00 | $1,500,000.00 | $1,630,000.00 | $1,630,000.00 |
| 0035 | FURNISH AND INSTALL PRE-ENGINEERED METAL BUILDING AND FOUNDATION | 1 | LS | JB | $110,000.00 | JB | $100,000.00 | JB | $256,000.00 |
| 0036 | MAIN CHANNEL GENERATOR SET | 1 | LS | JB | $210,000.00 | JB | $200,000.00 | JB | $365,000.00 |
| 0037 | MAIN CHANNEL GENERATOR PLATFORM | 1 | LS | JB | $85,000.00 | JB | $60,000.00 | JB | $89,000.00 |
| 0038 | BACK CHANNEL GENERATOR PLATFORM | 1 | LS | JB | $55,000.00 | JB | $50,000.00 | JB | $78,000.00 |
| 0039 | BACK CHANNEL BELLOWS COVERS, PIERS 10 AND 16 | 2 | EA | $20,000.00 | $40,000.00 | $2,500.00 | $5,000.00 | $25,000.00 | $50,000.00 |
| 0040 | BACK CHANNEL BELLOWS COVERS, PIERS 11 THRU 15 | 5 | EA | $25,000.00 | $125,000.00 | $2,500.00 | $12,500.00 | $50,000.00 | $250,000.00 |
| TOTAL BASE CONTRACT, ITEMS 0001 THRU 0040 | $33,603,500.00 | $41,305,490.00 | $40,631,649.00 | ||||||
| AWARDABLE OPTION A, ABUTMENT COMBINATION WALL | |||||||||
| 0041AA | REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS, AWARDABLE OPTION A | NOT TO EXCEED | $7,800.00 | $10,000.00 | $15,000.00 | ||||
| 0041AB | ABUTMENT COMBINATION WALL, 4'-0" DIAMETER X 1/2" THICK PIPE PILES | 715 | LF | $200.00 | $143,000.00 | $225.00 | $160,875.00 | $240.00 | $171,600.00 |
| 0041AC | ABUTMENT COMBINATION WALL, PZC 18 METAL SHEET PILING | 1,460 | LF | $60.00 | $87,600.00 | $35.00 | $51,100.00 | $180.00 | $262,800.00 |
| 0041AD | ABUTMENT COMBINATION WALL, W12 X 53 END PILE | 1,590 | LB | $5.00 | $7,950.00 | $6.00 | $9,540.00 | $5.00 | $7,950.00 |
| 0041AE | ABUTMENT COMBINATION WALL, W33 X 263 KING PILES - (PILES 1 THRU 6) | 6 | EA | $2,000.00 | $12,000.00 | $1,500.00 | $9,000.00 | $4,000.00 | $24,000.00 |
| 0041AF | ABUTMENT COMBINATION WALL, W33 X 263 KING PILES - (PILES 7 THRU 21) | 15 | EA | $3,000.00 | $45,000.00 | $1,500.00 | $22,500.00 | $5,000.00 | $75,000.00 |
| 0041AG | ABUTMENT COMBINATION WALL, 3'-6' DIAMETER ROCK SOCKETS | 335 | LF | $600.00 | $201,000.00 | $875.00 | $293,125.00 | $2,400.00 | $804,000.00 |
| 0041AH | ABUTMENT COMBINATION WALL, CONCRETE FOR SOCKETED PIPE PILES | 455 | CY | $350.00 | $159,250.00 | $250.00 | $113,750.00 | $800.00 | $364,000.00 |
| 0041AJ | ABUTMENT COMBINATION WALL, M CONCRETE FOR CAP AND SLAB | 505 | CY | $600.00 | $303,000.00 | $200.00 | $101,000.00 | $300.00 | $151,500.00 |
| 0041AK | ABUTMENT COMBINATION WALL, FURNISH AND INSTALL ROCK ANCHORS | 7 | EA | $80,000.00 | $560,000.00 | $40,000.00 | $280,000.00 | $100,000.00 | $700,000.00 |
| 0041AL | ABUTMENT COMBINATION WALL, RIPRAP BACKFILL BEHIND WALL | 630 | CY | $75.00 | $47,250.00 | $90.00 | $56,700.00 | $58.00 | $36,540.00 |
| TOTAL AWARDABLE OPTION A, ITEMS 0041AA THRU 0041AL | $1,573,850.00 | $1,107,590.00 | $2,612,390.00 | ||||||
| AWARDABLE OPTION B, ABUTMENT WALL REPAIR | |||||||||
| 0042AA | REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS, AWARDABLE OPTION B | NOT TO EXCEED | $1,700.00 | $1,500.00 | $3,500.00 | ||||
| 0042AB | ABUTMENT WALL REPAIR, ESPLANADE CONCRETE SLAB | 130 | CY | $500.00 | $65,000.00 | $450.00 | $58,500.00 | $1,000.00 | $130,000.00 |
| 0042AC | ABUTMENT WALL REPAIR, CONCRETE REMOVAL | 70 | CY | $600.00 | $42,000.00 | $300.00 | $21,000.00 | $1,500.00 | $105,000.00 |
| 0042AD | ABUTMENT WALL REPAIR, CONCRETE REPAIRS AND OTHER CONCRETE WORK | 70 | CY | $3,500.00 | $245,000.00 | $1,000.00 | $70,000.00 | $5,000.00 | $350,000.00 |
| TOTAL AWARDABLE OPTION B, ITEMS 0042AA THRU 0042AD | $353,700.00 | $151,000.00 | $588,500.00 | ||||||
| AWARDABLE OPTION C, SCOUR PROTECTION GATE BAYS 7 AND 8 | |||||||||
| 0043AA | REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS, AWARDABLE OPTION C | NOT TO EXCEED | $23,000.00 | $50,000.00 | $38,000.00 | ||||
| 0043AB | SCOUR PROTECTION, DEMONSTRATION PROJECT | 1 | LS | JB | $550,000.00 | JB | $1,000,000.00 | JB | $1,050,000.00 |
| 0043AC | SCOUR PROTECTION, REMOVAL AND DISPOSAL OF EXISTING CONCRETE BLOCKS IN GATE BAY 7 | 60 | CY | $300.00 | $18,000.00 | $50.00 | $3,000.00 | $43.00 | $2,580.00 |
| 0043AD | SCOUR PROTECTION, REMOVAL, STAGING, AND REUSE OF EXISTING DERRICK STONE | 3,520 | CY | $70.00 | $246,400.00 | $75.00 | $264,000.00 | $80.00 | $281,600.00 |
| 0043AE | SCOUR PROTECTION, REMOVAL, STAGING, AND REUSE OF EXISTING 3'-0" GRADED STONE LAYER | 1,640 | CY | $60.00 | $98,400.00 | $60.00 | $98,400.00 | $56.00 | $91,840.00 |
| 0043AF | SCOUR PROTECTION, DREDGING FOR 3H:1V SLOPE AND DISPOSAL | 10960 | CY | $44.00 | $482,240.00 | $40.00 | $438,400.00 | $38.00 | $416,480.00 |
| 0043AG | SCOUR PROTECTION, GEOGRID REINFORCEMENT | 2,680 | SY | $65.00 | $174,200.00 | $60.00 | $160,800.00 | $20.00 | $53,600.00 |
| 0043AH | SCOUR PROTECTION, BEDDING MATERIAL | 990 | CY | $100.00 | $99,000.00 | $50.00 | $49,500.00 | $500.00 | $495,000.00 |
| 0043AJ | SCOUR PROTECTION, FURNISH AND INSTALL GROUT BAGS WITH ACCESSORIES AND GROUT INFILL | 2,680 | CY | $750.00 | $2,010,000.00 | $760.00 | $2,036,800.00 | $1,000.00 | $2,680,000.00 |
| 0043AK | SCOUR PROTECTION, CAST-IN-PLACE APRON TIE-IN ELEMENT | 170 | CY | $5,000.00 | $850,000.00 | $3,300.00 | $561,000.00 | $5,000.00 | $850,000.00 |
| 0043AL | SCOUR PROTECTION, GROUT BAG FLANK PROTECTION | 1 | EA | $45,000.00 | $45,000.00 | $50,000.00 | $50,000.00 | $45,000.00 | $45,000.00 |
| 0043AM | EXISTING DAM APRON, DRILLING OF GROUT HOLES | 110 | LF | $150.00 | $16,500.00 | $550.00 | $60,500.00 | $400.00 | $44,000.00 |
| 0043AN | EXISTING DAM APRON, DRILLING OF EXPLORATORY HOLES | 10 | LF | $250.00 | $2,500.00 | $275.00 | $2,750.00 | $550.00 | $5,500.00 |
| 0043AP | EXISTING DAM APRON, GROUT PLACEMENT | 330 | CY | $300.00 | $99,000.00 | $725.00 | $239,250.00 | $400.00 | $132,000.00 |
| 0043AQ | MOBILIZATION AND DEMOBILIZATION FOR AWARDABLE OPTION C | 1 | EA | $15,000.00 | $15,000.00 | $5,000.00 | $5,000.00 | $20,000.00 | $20,000.00 |
| TOTAL AWARDABLE OPTION C, ITEMS 0043AA THRU 0043AQ | $4,729,240.00 | $5,019,400.00 | $6,205,600.00 | ||||||
| AWARDABLE OPTION D, SCOUR PROTECTION GATE BAYS 5 AND 6 | |||||||||
| 0044AA | REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS, AWARDABLE OPTION D | NOT TO EXCEED | $21,500.00 | $40,000.00 | $27,000.00 | ||||
| 0044AB | SCOUR PROTECTION, REMOVAL AND DISPOSAL OF EXISTING CONCRETE BLOCKS IN GATE BAY 6 | 370 | CY | $300.00 | $111,000.00 | $50.00 | $18,500.00 | $43.00 | $15,910.00 |
| 0044AC | SCOUR PROTECTION, REMOVAL, STAGING, AND REUSE OF EXISTING DERRICK STONE | 4,490 | CY | $70.00 | $314,300.00 | $75.00 | $336,750.00 | $80.00 | $359,200.00 |
| 0044AD | SCOUR PROTECTION, REMOVAL, STAGING, AND REUSE OF EXISTING 3'-0" GRADED STONE LAYER | 2,160 | CY | $60.00 | $129,600.00 | $60.00 | $129,600.00 | $56.00 | $120,960.00 |
| 0044AE | SCOUR PROTECTION, DREDGING FOR 3H:1V SLOPE AND DISPOSAL | 7,200 | CY | $44.00 | $316,800.00 | $40.00 | $288,000.00 | $38.00 | $273,600.00 |
| 0044AF | SCOUR PROTECTION, GEOGRID REINFORCEMENT | 2,940 | SY | $65.00 | $191,100.00 | $60.00 | $176,400.00 | $20.00 | $58,800.00 |
| 0044AG | SCOUR PROTECTION, BEDDING MATERIAL | 1,150 | CY | $100.00 | $115,000.00 | $50.00 | $57,500.00 | $400.00 | $460,000.00 |
| 0044AH | SCOUR PROTECTION, FURNISH AND INSTALL GROUT BAGS WITH ACCESSORIES AND GROUT INFILL | 2,940 | CY | $750.00 | $2,205,000.00 | $760.00 | $2,234,400.00 | $800.00 | $2,352,000.00 |
| 0044AJ | SCOUR PROTECTION, CAST-IN-PLACE APRON TIE-IN ELEMENT | 164 | CY | $5,000.00 | $820,000.00 | $3,300.00 | $541,200.00 | $3,000.00 | $492,000.00 |
| 0044AK | SCOUR PROTECTION, GROUT BAG FLANK PROTECTION | 1 | EA | $45,000.00 | $45,000.00 | $50,000.00 | $50,000.00 | $45,000.00 | $45,000.00 |
| 0044AL | EXISTING DAM APRON, DRILLING OF GROUT HOLES | 90 | LF | $150.00 | $13,500.00 | $550.00 | $49,500.00 | $400.00 | $36,000.00 |
| 0044AM | EXISTING DAM APRON, DRILLING OF EXPLORATORY HOLES | 10 | LF | $250.00 | $2,500.00 | $275.00 | $2,750.00 | $550.00 | $5,500.00 |
| 0044AN | EXISTING DAM APRON, GROUT PLACEMENT | 270 | CY | $300.00 | $81,000.00 | $725.00 | $195,750.00 | $400.00 | $108,000.00 |
| 0044AP | MOBILIZATION AND DEMOBILIZATION FOR AWARDABLE OPTION D | 1 | EA | $15,000.00 | $15,000.00 | $5,000.00 | $5,000.00 | $10,000.00 | $10,000.00 |
| TOTAL AWARDABLE OPTION D, ITEMS 0044AA THRU 0044AP | $4,381,300.00 | $4,125,350.00 | $4,363,970.00 | ||||||
| AWARDABLE OPTION E, SCOUR PROTECTION GATE BAYS 3 AND 4 | |||||||||
| 0045AA | REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS, AWARDABLE OPTION E | NOT TO EXCEED | $21,000.00 | $42,000.00 | $25,000.00 | ||||
| 0045AB | SCOUR PROTECTION, REMOVAL AND DISPOSAL OF EXISTING GROUT BAGS GATE BAY 4 | 520 | CY | $150.00 | $78,000.00 | $50.00 | $26,000.00 | $43.00 | $22,360.00 |
| 0045AC | SCOUR PROTECTION, REMOVAL AND DISPOSAL OF EXISTING GROUTED RIPRAP IN GATE BAYS 3 AND 4 | 160 | CY | $120.00 | $19,200.00 | $100.00 | $16,000.00 | $43.00 | $6,880.00 |
| 0045AD | SCOUR PROTECTION, REMOVAL, STAGING, AND REUSE OF EXISTING DERRICK STONE | 1,770 | CY | $70.00 | $123,900.00 | $75.00 | $132,750.00 | $80.00 | $141,600.00 |
| 0045AE | SCOUR PROTECTION, REMOVAL, STAGING, AND REUSE OF EXISTING 3'-0" GRADED STONE LAYER | 960 | CY | $60.00 | $57,600.00 | $60.00 | $57,600.00 | $56.00 | $53,760.00 |
| 0045AF | SCOUR PROTECTION, DREDGING FOR 3H:1V SLOPE AND DISPOSAL | 16,300 | CY | $44.00 | $717,200.00 | $40.00 | $652,000.00 | $38.00 | $619,400.00 |
| 0045AG | SCOUR PROTECTION, GEOGRID REINFORCEMENT | 2,940 | SY | $65.00 | $191,100.00 | $60.00 | $176,400.00 | $20.00 | $58,800.00 |
| 0045AH | SCOUR PROTECTION, BEDDING MATERIAL | 1,360 | CY | $100.00 | $136,000.00 | $50.00 | $68,000.00 | $300.00 | $408,000.00 |
| 0045AJ | SCOUR PROTECTION, FURNISH AND INSTALL GROUT BAGS WITH ACCESSORIES AND GROUT INFILL | 2,940 | CY | $750.00 | $2,205,000.00 | $760.00 | $2,234,400.00 | $700.00 | $2,058,000.00 |
| 0045AK | SCOUR PROTECTION, CAST-IN-PLACE APRON TIE-IN ELEMENT | 174 | CY | $3,000.00 | $522,000.00 | $3,300.00 | $574,200.00 | $2,500.00 | $435,000.00 |
| 0045AL | SCOUR PROTECTION, GROUT BAG FLANK PROTECTION | 1 | EA | $45,000.00 | $45,000.00 | $50,000.00 | $50,000.00 | $45,000.00 | $45,000.00 |
| 0045AM | EXISTING DAM APRON, DRILLING OF GROUT HOLES | 100 | LF | $150.00 | $15,000.00 | $550.00 | $55,000.00 | $400.00 | $40,000.00 |
| 0045AN | EXISTING DAM APRON, DRILLING OF EXPLORATORY HOLES | 15 | LF | $250.00 | $3,750.00 | $275.00 | $4,125.00 | $550.00 | $8,250.00 |
| 0045AP | EXISTING DAM APRON, GROUT PLACEMENT | 300 | CY | $300.00 | $90,000.00 | $725.00 | $217,500.00 | $400.00 | $120,000.00 |
| 0045AQ | MOBILIZATION AND DEMOBILIZATION FOR AWARDABLE OPTION E | 1 | EA | $15,000.00 | $15,000.00 | $5,000.00 | $5,000.00 | $10,000.00 | $10,000.00 |
| TOTAL AWARDABLE OPTION E, ITEMS 0045AA THRU 0045AQ | $4,239,750.00 | $4,310,975.00 | $4,052,050.00 | ||||||
| AWARDABLE OPTION F, SCOUR PROTECTION FIXED WEIR AND GATE BAYS 1 AND 2 | |||||||||
| 0046AA | REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS, AWARDABLE OPTION F | NOT TO EXCEED | $21,000.00 | $41,000.00 | $21,000.00 | ||||
| 0046AB | SCOUR PROTECTION, REMOVAL, STAGING, AND REUSE OF EXISTING DERRICK STONE | 2,800 | CY | $70.00 | $196,000.00 | $75.00 | $210,000.00 | $43.00 | $120,400.00 |
| 0046AC | SCOUR PROTECTION, REMOVAL, STAGING, AND REUSE OF EXISTING 3'-0" GRADED STONE LAYER | 1,280 | CY | $60.00 | $76,800.00 | $60.00 | $76,800.00 | $80.00 | $102,400.00 |
| 0046AD | SCOUR PROTECTION, DREDGING FOR 3H:1V SLOPE AND DISPOSAL | 8,380 | CY | $44.00 | $368,720.00 | $40.00 | $335,200.00 | $56.00 | $469,280.00 |
| 0046AE | SCOUR PROTECTION, GEOGRID REINFORCEMENT | 2,900 | SY | $65.00 | $188,500.00 | $60.00 | $174,000.00 | $20.00 | $58,000.00 |
| 0046AF | SCOUR PROTECTION, BEDDING MATERIAL | 1,130 | CY | $100.00 | $113,000.00 | $50.00 | $56,500.00 | $200.00 | $226,000.00 |
| 0046AG | SCOUR PROTECTION, FURNISH AND INSTALL GROUT BAGS WITH ACCESSORIES AND GROUT INFILL | 2900 | CY | $750.00 | $2,175,000.00 | $760.00 | $2,204,000.00 | $600.00 | $1,740,000.00 |
| 0046AH | SCOUR PROTECTION, CAST-IN-PLACE APRON TIE-IN ELEMENT | 200 | CY | $5,000.00 | $1,000,000.00 | $3,300.00 | $660,000.00 | $2,000.00 | $400,000.00 |
| 0046AJ | SCOUR PROTECTION, ANCHOR GROUT BAGS INTO BEDROCK WITH DOWELS | 5 | EA | $20,000.00 | $100,000.00 | $10,000.00 | $50,000.00 | $7,000.00 | $35,000.00 |
| 0046AK | EXISTING DAM APRON, DRILLING OF GROUT HOLES | 110 | LF | $150.00 | $16,500.00 | $550.00 | $60,500.00 | $400.00 | $44,000.00 |
| 0046AL | EXISTING DAM APRON, DRILLING OF EXPLORATORY HOLES | 15 | LF | $250.00 | $3,750.00 | $275.00 | $4,125.00 | $550.00 | $8,250.00 |
| 0046AM | EXISTING DAM APRON, GROUT PLACEMENT | 330 | CY | $300.00 | $99,000.00 | $725.00 | $239,250.00 | $400.00 | $132,000.00 |
| 0046AN | MOBILIZATION AND DEMOBILIZATION FOR AWARDABLE OPTION F | 1 | EA | $15,000.00 | $15,000.00 | $5,000.00 | $5,000.00 | $10,000.00 | $10,000.00 |
| 0046AP | SCOUR PROTECTION, GROUT BAG FLANK PROTECTION | 1 | EA | $45,000.00 | $45,000.00 | $50,000.00 | $50,000.00 | $45,000.00 | $45,000.00 |
| TOTAL AWARDABLE OPTION F, ITEMS 0046AA THRU 0046AP | $4,418,270.00 | $4,166,375.00 | $3,411,330.00 | ||||||
| BASE CONTRACT ITEMS | |||||||||
| 0048 | REPLACE RUBBER SEAL AT SILL BEAM, GATE BAYS 2 THRU 8 | 838 | LF | $200.00 | $167,600.00 | $350.00 | $293,300.00 | $250.00 | $209,500.00 |
| 0049 | REIMBURSEMENT FOR POWER COMPANY SERVICES | 1 | LS | JB | $10,000.00 | JB | $10,000.00 | JB | $10,000.00 |
| 0050 | FURNISH PIPE PILES FOR ABUTMENT COMBINATION WALL | 181,280 | LB | $1.50 | $271,920.00 | $1.00 | $181,280.00 | $2.50 | $453,200.00 |
| 0051 | FURNISH PZC METAL SHEET FOR ABUTMENT COMBINATION WALL | 73,685 | LB | $1.15 | $84,737.75 | $0.75 | $55,263.75 | $1.60 | $117,896.00 |
| 0052 | FURNISH W12 X 53 END PILE FOR ABUTMENT COMBINATION WALL | 1,800 | LB | $1.00 | $1,800.00 | $1.50 | $2,700.00 | $6.00 | $10,800.00 |
| 0053 | FURNISH W33 X 263 KING PILES FOR ABUTMENT COMBINATION WALL | 47,340 | LB | $1.00 | $47,340.00 | $0.75 | $35,505.00 | $1.50 | $71,010.00 |
| 0054 | FURNISH W33 X 263 KING PILES WITH FLANGE PLATES FOR ABUTMENT COMBINATION WALL | 159,470 | LB | $1.60 | $255,152.00 | $1.00 | $159,470.00 | $1.60 | $255,152.00 |
| TOTAL BASE CONTRACT, ITEMS 0048 THRU 0054 | $838,549.75 | $737,518.75 | $1,127,558.00 | ||||||
| TOTAL BASE CONTRACT, ITEMS 0001 THRU 0040 AND 0048 THRU 0054 | $34,442,049.75 | $42,043,008.75 | $41,759,207.00 | ||||||
| TOTAL AWARDABLE OPTION A, ITEMS 0041AA THRU 0041AL | $1,573,850.00 | $1,107,590.00 | $2,612,390.00 | ||||||
| TOTAL AWARDABLE OPTION B, ITEMS 0042AA THRU 0042AD | $353,700.00 | $151,000.00 | $588,500.00 | ||||||
| TOTAL AWARDABLE OPTION C, ITEMS 0043AA THRU 0043AQ | $4,729,240.00 | $5,019,400.00 | $6,205,600.00 | ||||||
| TOTAL AWARDABLE OPTION D, ITEMS 0044AA THRU 0044AP | $4,381,300.00 | $4,125,350.00 | $4,363,970.00 | ||||||
| TOTAL AWARDABLE OPTION E, ITEMS 0045AA THRU 0045AQ | $4,239,750.00 | $4,310,975.00 | $4,052,050.00 | ||||||
| TOTAL AWARDABLE OPTION F, ITEMS 0046AA THRU 0046AP | $4,418,270.00 | $4,166,375.00 | $3,411,330.00 | ||||||
| TOTAL, BASE CONTRACT PLUS AWARDABLE OPTIONS | $54,138,159.75 | $60,923,698.75 | $62,993,047.00 |