01 22 00.00 10.pdf

PDF 405 KB Posted

Attached to
Braddock Tow Hauling System Federal contract opportunity
Solicitation number
W911WN09B0023
Issued by
Department of the Army Corps of Engineers Engineering District Pittsburgh

About this file

Revised Section 01 22 00.10

View the file

Other files for this federal contract opportunity

Other files attached to Braddock Tow Hauling System, newest first.
File Type Posted
BID RESULTS.doc DOC document
41 24 40.pdf PDF
W911WN-09-B-0023-0001.pdf PDF
Conformed Price Schedule.pdf PDF
W911WN-09-B-0023-0001.zip ZIP file
33 40 15.pdf PDF
Braddock Tow Haul Site Visit Attendence Register.doc DOC document
W911WN-09-B-0023.pdf PDF
PA080004.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Braddock Locks and Dam - Tow Haulage Unit Installation

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00.00 10

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 LUMP SUM PAYMENT ITEMS

1.1.1 Removal of Existing Equipment and Other Items

1.1.1.1 Payment

1.1.1.2 Unit of Measure

1.1.1.3 Payment Items

1.1.2 Trench Drainage System

1.1.2.1 Payment

1.1.2.2 Unit of Measure

1.1.2.3 Payment Item

1.1.3 Jib Crane

1.1.3.1 Payment

1.1.3.2 Unit of Measure

1.1.3.3 Payment Item

1.1.4 Install Government Furnished Tow Haulage System

1.1.4.1 Payment

1.1.4.2 Unit of Measure

1.1.4.3 Payment Item

1.1.5 Tow Haulage Equipment Manufacturer's Representative

1.1.5.1 Payment

1.1.5.2 Unit of Measure

1.1.5.3 Payment Item

1.1.6 Electrical Work

1.1.6.1 Payment

1.1.6.2 Unit of Measure

1.1.6.3 Payment Item

1.1.7 New Equipment Building

1.1.7.1 Payment

1.1.7.2 Unit of Measure

1.1.7.3 Payment Item

1.2 UNIT PRICE PAYMENT ITEMS

1.2.1 Digital Progress Images

1.2.1.1 Payment

1.2.1.2 Measurement

1.2.1.3 Unit of Measure

1.2.1.4 Payment Item

1.2.2 Removal of Concrete Esplanade

1.2.2.1 Payment

1.2.2.2 Unit of Measure

1.2.2.3 Measurement

1.2.2.4 Payment Item

1.2.3 Excavation

1.2.3.1 Payment

1.2.3.2 Measurement

1.2.3.3 Unit of Measure

1.2.3.4 Payment Item

1.2.4 Steel Reinforcement

SECTION 01 22 00.00 10 Page 1 W911WN-09-B-0023 Revised by Amendment 0001

1.2.4.1 Payment

1.2.4.2 Measurement

1.2.4.3 Unit of Measure

1.2.4.4 Payment Items

1.2.5 Drill Holes and Grout Dowels

1.2.5.1 Payment

1.2.5.2 Measurement

1.2.5.3 Unit of Measure

1.2.5.4 Payment Item

1.2.6 Concrete

1.2.6.1 Payment

1.2.6.2 Measurement

1.2.6.3 Unit of Measure

1.2.6.4 Payment Items

1.2.7 Aggregate Base Course

1.2.7.1 Payment

1.2.7.2 Measurement

1.2.7.3 Unit of Measure

1.2.7.4 Payment Item

1.2.8 Check Posts

1.2.8.1 Payment

1.2.8.2 Measurement

1.2.8.3 Unit of Measure

1.2.8.4 Payment Item

1.2.9 Guard Fence

1.2.9.1 Payment

1.2.9.2 Measurement

1.2.9.3 Unit of Measure

1.2.9.4 Payment Item

1.2.10 Single Swing Gate

1.2.10.1 Payment

1.2.10.2 Measurement

1.2.10.3 Unit of Measure

1.2.10.4 Payment Item

1.2.11 Aluminum Planking

1.2.11.1 Payment

1.2.11.2 Measurement

1.2.11.3 Unit of Measure

1.2.11.4 Payment Items

1.2.12 Equipment Shelters

1.2.12.1 Payment

1.2.12.2 Measurement

1.2.12.3 Unit of Measure

1.2.12.4 Payment Item

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION (NOT APPLICABLE)

-- End of Section Table of Contents --

SECTION 01 22 00.00 10 Page 2

SECTION 01 22 00.00 10

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 LUMP SUM PAYMENT ITEMS

Payment items for the work of this contract for which contract lump sum payments will be made are listed in the BIDDING SCHEDULE in Section 00010 SUPPLIES OR SERVICES AND PRICES/COSTS and described below. All costs for items of work, which are not specifically mentioned to be included in a particular lump sum payment item, shall be included in the listed lump sum item most closely associated with the work involved. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.1.1 Removal of Existing Equipment and Other Items

1.1.1.1 Payment

Payment for this item shall constitute full compensation for all labor, equipment, material and disposal costs to remove and dispose of or store the items specified or shown on the drawings to be removed..

Removal of Miscellaneous Items and Appurtenances - this item includes removal and disposal of recess covers, guard fence, check posts, and related items.

Removal of Miscellaneous Electrical Fixtures, Equipment and Machinery -this item includes removal and storage of the existing light standards and removal and disposal of the existing jib crane and path lights.

Removal of Existing Tow Haulage System - This item includes removal of the existing tow haulage winches, rails, sheaves, and related items.

1.1.1.2 Unit of Measure

Unit of measure: Lump Sum.

1.1.1.3 Payment Items

00030001AC Removal of Miscellaneous Items and Appurtenances 00040001AD Removal of Miscellaneous Electrical Fixtures, Equipment and Machinery 00050001AE Removal of Existing Tow Haulage System

1.1.2 Trench Drainage System

1.1.2.1 Payment

Payment for these items shall constitute full compensation for furnishing all materials, equipment, plant, and tools; and for labor and other incidentals necessary to complete the work as shown and as specified, SECTION 01 22 00.00 10 Page 3 including furnishing and placing the item and testing of sewer piping.

Payment for the trench drain will also include costs of furnishing and placing the concrete bedding. Payment for removal of concrete and excavation will be made separately.

1.1.2.2 Unit of Measure

Unit of measure: Lump Sum.

1.1.2.3 Payment Item

00050001AR Trench Drain System

1.1.3 Jib Crane

1.1.3.1 Payment

Payment for this item shall constitute full compensation for all labor, equipment, material and supply costs to furnish, install and test the new jib crane.

1.1.3.2 Unit of Measure

Unit of measure: Lump Sum.

1.1.3.3 Payment Item

000220001AX Furnish and Install Government-Furnished Jib Crane

1.1.4 Install Government Furnished Tow Haulage System

1.1.4.1 Payment

Payment for this item shall constitute full compensation for all labor, equipment, material and costs to install and test the Government furnished tow haulage system. Payment shall also include furnishing and installing any materials required for installation that are not included in the Government furnished equipment. Payment for replacement or repair of any Government furnished equipment that was damaged during storage, before being turned over to the Contractor will be made in accordance with Contract Clause "Changes".

1.1.4.2 Unit of Measure

Unit of measure: Lump Sum.

1.1.4.3 Payment Item

000230001AY Install Government-Furnished Tow Haulage System

1.1.5 Tow Haulage Equipment Manufacturer's Representative

1.1.5.1 Payment

Payment for this item shall constitute full compensation for all costs associated with providing the services of the equipment manufacturer's representative as specified in Section 41 24 40 TOW HAULAGE SYSTEMS.

SECTION 01 22 00.00 10 Page 4

1.1.5.2 Unit of Measure

Unit of measure: Lump Sum.

1.1.5.3 Payment Item

000240001AZ Tow Haulage Equipment Manufacturer's Representative

1.1.6 Electrical Work

1.1.6.1 Payment

Payment for this item shall constitute full compensation for all labor, equipment, material and costs for all electrical work. Payment shall include, but not limited to, electric service for the tow haulage system and equipment enclosures, reinstalling the light standards.

1.1.6.2 Unit of Measure

Unit of measure: Lump Sum.

1.1.6.3 Payment Item

000250001BA Electrical Work

1.1.7 New Equipment Building

1.1.7.1 Payment

Payment for this item shall constitute full compensation for all labor, equipment, material and costs for removing and disposing of the existing pedestal mounted tow haulage equipment building and constructing a new equipment building. Payment for new electrical equipment in the building will be included in lump sum price for electrical work.

1.1.7.2 Unit of Measure

Unit of measure: Lump Sum.

1.1.7.3 Payment Item

00025 Electrical Work0001BB New Equipment Building

1.2 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular unit price payment item, shall be included in the listed unit price item most closely associated with the work involved. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.

SECTION 01 22 00.00 10 Page 5

1.2.1 Digital Progress Images

1.2.1.1 Payment

Payment for monthly progress images shall constitute full compensation for all labor, equipment, material and supply costs for furnishing monthly digital progress images, as specified in Section 01 32 33 PROGRESS

PHOTOGRAPHS.

1.2.1.2 Measurement

Measurement will be made of the number of sets of progress images satisfactorily furnished as specified or directed.

1.2.1.3 Unit of Measure

Unit of measure: Sets.

1.2.1.4 Payment Item

00020001AB Digital Progress Images

1.2.2 Removal of Concrete Esplanade

1.2.2.1 Payment

Payment for this item shall constitute full compensation for all labor, equipment, material and disposal costs to remove and dispose of the concrete esplanade pavement within the limits shown on the drawings.

1.2.2.2 Unit of Measure

Unit of measure: Square Yards.

1.2.2.3 Measurement

Measurement shall be made on the basis of square yards of material furnished and placed as specified and as shown on the drawings.

1.2.2.4 Payment Item

00060001AF Removal of Concrete Esplanade

1.2.3 Excavation

1.2.3.1 Payment

Payment for this item shall constitute full compensation for all labor, equipment, material and disposal costs to perform all excavation required for installation of the trench drain system and Government furnished tow haulage system. Payment shall also include backfill where applicable and disposal of excess and unsuitable excavated material.

1.2.3.2 Measurement

Measurement will be made by the cubic yard of material excavated.

Measurement will be made between the surface after removal of the concrete pavement and the final approved excavated surface.

SECTION 01 22 00.00 10 Page 6

1.2.3.3 Unit of Measure

Unit of measure: Cubic Yard.

1.2.3.4 Payment Item

00070001AG Unclassified Excavation, Esplanade

1.2.4 Steel Reinforcement

1.2.4.1 Payment

Payment for reinforcing steel and dowels shall constitute full compensation for furnishing and installing the reinforcing as shown and specified.

Payment shall include all labor, equipment, materials and supplies to complete these items of work.

1.2.4.2 Measurement

Concrete reinforcing and dowels will be measured for payment by the pound in place. The measured lengths of bars and dowels will be converted to weights for the size of bars listed by the use of the nominal weights per lineal foot specified in the respective material specifications. The weight of welded wire fabric will be determined by weighing, or by manufacturer's or catalog weights when weighing is not practicable. Steel in laps indicated on the drawings or required by the Contracting Officer will be paid for at the contract unit price. No payment will be made for the additional steel in laps which are authorized for the convenience of the Contractor.

1.2.4.3 Unit of Measure

Unit of measure: Pound.

1.2.4.4 Payment Items

00080001AH Steel Bars, Concrete Reinforcement 00090001AJ Steel Welded Wire Fabric, Concrete Reinforcement 00100001AK Dowels

1.2.5 Drill Holes and Grout Dowels

1.2.5.1 Payment

Payment for this item shall include the cost of furnishing all equipment, labor, and materials, except dowels, and all other incidental costs in connection with completing the item of work as shown and as specified. No payment will be made for holes improperly drilled or grouted nor for repairs required due to damage caused by the drilling and grouting operations.

1.2.5.2 Measurement

Drilling holes and grouting dowels will be measured by the linear foot of hole actually drilled and grouted to the depths indicated on the drawings or otherwise directed by the Contracting Officer.

SECTION 01 22 00.00 10 Page 7

1.2.5.3 Unit of Measure

Unit of measure: Linear Foot.

1.2.5.4 Payment Item

00110001AL Drill Holes and Grout Dowels

1.2.6 Concrete

1.2.6.1 Payment

Payment for these items shall include the cost of all labor, materials, and the use of all equipment and tools required to complete the concrete work, including the bond breaker; except the reinforcement, and embedded parts that are specified to be paid for separately. No separate payment will be made for concrete bedding for the trench drain system which will be included in lump sum price for the trench drain system.

1.2.6.2 Measurement

Measurement of concrete shall be made on the basis of the actual volume of concrete within the pay lines of the structures as indicated on the drawings. Measurement of concrete placed against the sides of any excavation without the use of intervening forms shall be made only within the pay lines of the structure, and within the tolerances specified. No measurement will be made of concrete placed outside the tolerances specified or for the excavation unless otherwise approved by the Contracting Officer. No deduction shall be made for rounded or beveled edges or space occupied by metal work, reinforcing steel, electrical conduits or other items, nor for voids or embedded items that are either less than 5 cubic feet in volume or 1 square foot in cross section.

Miscellaneous concrete includes concrete for ramps, steps, cable trench, winch and sheave thrust blocks, and concrete pedestals.

1.2.6.3 Unit of Measure

Unit of measure: Cubic Yard.

1.2.6.4 Payment Items

00120001AM Concrete, Land Wall Overlay 00130001AN Concrete, Esplanade 00140001AP Concrete, Miscellaneous

1.2.7 Aggregate Base Course

1.2.7.1 Payment

Payment for this items shall constitute full compensation for all labor, equipment, material and supply costs to construct the aggregate base course. The payment shall constitute full compensation for all labor, equipment, materials and supplies for furnishing and placing crushed aggregate material, including compaction; shall include any required field and laboratory testing; shall include performing measurements for payment;

and all other incidental costs in connection with these aspects of the work under this contract.

SECTION 01 22 00.00 10 Page 8

1.2.7.2 Measurement

Measurement of concrete shall be made on the basis of the actual volume of aggregate place within the limits as indicated on the drawings.

1.2.7.3 Unit of Measure

Unit of measure: Cubic Yard.

1.2.7.4 Payment Item

00150001AQ Aggregate Base Course

1.2.8 Check Posts

1.2.8.1 Payment

Payment for installing the Government furnished check post assemblies shall include receiving and delivering the posts from the Government's PEWARS facility, and installing the check post assemblies; furnishing and installing anchorages; field-painting; and cement grout fill, complete, as shown on the contract drawings and as specified.

1.2.8.2 Measurement

Measurement will be made by the number of Government furnished check posts acceptably installed.

1.2.8.3 Unit of Measure

Unit of measure: Each.

1.2.8.4 Payment Item

00170001AS Install Government-Furnished Check Posts

1.2.9 Guard Fence

1.2.9.1 Payment

Payment for for this item shall constitute full compensation for all costs necessary to complete this item of work as shown and as specified, including fabricating, delivering, and installing the guard fence, complete, including connection to the existing guard rail, as shown on the drawings, including posts, caps, cables, straps, turn buckles, chains, pins, galvanizing, and accessories.

1.2.9.2 Measurement

Measurement for guard fence will be by the linear foot of guard fence installed.

1.2.9.3 Unit of Measure

Unit of measure: Linear Feet.

1.2.9.4 Payment Item

00180001AT Guard Fence

SECTION 01 22 00.00 10 Page 9

1.2.10 Single Swing Gate

1.2.10.1 Payment

Payment for for this item shall constitute full compensation for all costs necessary to complete this item of work as shown and as specified, including fabricating, delivering, painting, and installing the spring-loaded gates,, as shown on the drawings.

1.2.10.2 Measurement

Measurement will be made by the number of swing gates acceptably installed.

1.2.10.3 Unit of Measure

Unit of measure:. Each

1.2.10.4 Payment Item

00190001AU Single Swing Gate

1.2.11 Aluminum Planking

1.2.11.1 Payment

Payment for these items shall constitute full compensation for all costs necessary to complete these items of work as shown and as specified, including furnishing and installing all aluminum planking, hardware, rabbet angles, coatings, and anchorages.

1.2.11.2 Measurement

Measurement of the aluminum rabbet angles will be by the linear foot installed.

Measurement of the planking will be by the square foot installed and accepted.

1.2.11.3 Unit of Measure

Unit of measure: Linear Feet, Square Feet.

1.2.11.4 Payment Items

00200001AV Aluminum Rabbet Angles 00210001AW Aluminum Planking

1.2.12 Equipment Shelters

1.2.12.1 Payment

Payment for this item shall constitute full compensation for all costs necessary to complete these items of work as shown and as specified.

1.2.12.2 Measurement

Measurement will be made by the number of equipment shelters acceptably constructed.

SECTION 01 22 00.00 10 Page 10

1.2.12.3 Unit of Measure

Unit of measure:. Each

1.2.12.4 Payment Item

00260002AB Equipment Shelters

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION (NOT APPLICABLE)

-- End of Section --