Attachment L2
Question/Comment # Document in Question
(SF 1449, PWS, TE, etc.)
Page/Paragraph in Question (be as specific as possible)
Question/Comment (one per line)
Government Response/Disposition
TE_2_Deliverables
TE3 & L3 CAT_1_REPORTS
1.6.5 & 1.6.9.2 QCP and Key Control Plan Can you provide a previous acceptable example of the afformentioned deliverables?
Pages 6-9 of 11._L3_-_CAT_1_REPORTS
You may use an existing commercial QCP but,at a minimum, the QCP shall address the items required in paragraph 1.6.5.
There is no example of an existing key control plan. The key control plan shall address the items required in paragraph 1.6.9.2.
Document 5._TE__3_Elevator_Escalator_Listing doesn't list any escalators but document 11._L3_-_CAT_1_REPORTS shows 2 escalators. Please confirm equipment.
Will we be provided a period of time after commencement of contract to conduct a more detailed unit by unit review and qualify maintenance deficiencies that would be classified as pre-maintenance?
TE #3 does list all four escalators (ESCL-1 through ESCL-4).
NAVFAC has not issued the inspection report for two of the escalators because they are waiting on inspection information from the incumbent contractor.
Reference PWS para 5.3.1. No specified time frame is given, but it shall start at the beginning of the contract by reviewing the most recent inspection reports and determining which deficiencies have been corrected and what is still outstanding. There will be deficiencies (e.g. no seismic fish plates) which will remain unresolved.