This document is a set of questions and answers related to Solicitation W911S024R0003 for the Enterprise Multimedia Center (EMC) Army Support Services Five Year Contract. The solicitation is a set-aside for 8(a) small businesses. Key details include:
The solicitation requires past performance within the last 3 years, but offerors requested the government extend this to 5 years to increase competition. The government declined. Offerors can provide past performance information from affiliated entities, as long as they demonstrate meaningful involvement. Travel may be required to military posts or commercial locations within the continental U.S. for services like filming or installing displays. All personnel must meet DoD information assurance/technology training requirements, with some roles requiring specific certifications. The government will manage and renew maintenance agreements and subscriptions. Offerors can submit up to 3 past performance references, which may be a combination of prime and subcontractor references. Proposals are due via email by 12:00 PM EDT on March 29, 2024.
View the file
Other files for this federal contract opportunity
Show all 27
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W911S024R0003 - Q&A
| Reference | Questions | Answers |
| Past Performance Assessment Questionnaire | 1) The Past Performance Questionnaire states must be returned to Government by 7 March. We request the Government relax the due date to Noon, March 29 to give our Government customers adequate time to complete their evaluation. | 1) Please refer to the updated Past Performance Questionnaire Attachment 2. |
| Solicitation W911S024R0003 | 2) The current solicitation requires past performance within 3 years. In an effort to increase the amount of qualified vendors that have extensive past performance and to increase market competition, would the Government consider extending the required past performance history from within 3 years to 5 years? | 2) No, the Government will not consider extending the required past performance history from within 3 years to 5 years. |
| Solicitation W911S024R0003 Page 27, 2. Past Performance Factor/Relevancy/Magnitude criteria | 3) "For references with performance periods that exceed one year in length, the dollar value of the reference will be divided by the total performance period to determine if it meets the required magnitude. In order for a dollar value of the reference to be considered of similar magnitude, the amount would have to be at least $7,000,000." To increase competition, will the government consider removing the threshold requirement, or at least lowering it to $5M to align with historic performance of this exact work? | 3) The Government believes that the level of effort for this contract matches the dollar amount for the magnitude in the current version of the solicitation. This is partly due to market condition changes since the historical contract and includes additional years in the period of performance when compared to the historical efforts. (Previous Contracts were for 3 years. This is anticipated to be 5 years.) |
| DD 254 Section 1b and 11b-d | 4) In Section 1b, it is identified that Safeguarding is Secret. Section 11b, c and d indicate that Contractor will receive, store and generate classified information at Contractor facility. However, in section 8 (attachment), it does not identify Contract facility as Actual Performance Location. Is safeguarding required (classified work performed at contractor facility)? If so, when is it required, pre- or post-award? | 4) DD 254 Section 1b and 11b-d do not state that the Contractor will receive, store and generate classified information at Contractor facility. All work (Secret or not) will be conducted at either the Enterprise Multimedia Center or other CONUS government facility. No work that falls within the scope of the contract will be conducted at a Contractor facility. Please see updated DD 254 for more information. |
| Solicitation W911S024R0003 Page 3-14 | 5) Will the Government provide plug numbers for the EMC Support Services CLINs? | 5) Please see updated Attachment 3 Pricing Worksheet. |
| Solicitation W911S024R0003 Page 61 (2.b.) | 6) We request the Government clarify whether the Offeror's submission is only electronic (via email) or a combination of electronic (email) and hard copy (CD/DVD). If hard copy is required, we request detailed instructions on what address to deliver the hard copy and hours the Government will accept delivery of proposals. | 6) Please refer to the updated verbiage in SF 1449, Amendment 2. |
| Solicitation W911S024R0003 Page 61 (2.b.) | 7) We request the Government clarify whether electronic document files must be delivered in native format (i.e. docx, ppt, etc.) or if they may be converted to pdf. We understand spreadsheets must be submitted innative Microsoft Excel and viewable in Microsoft Excel 2007 format. | 7) Please see SF 1449, Amendment 2. |
| Solicitation W911S024R0003 Page 62 (i) Vol. I (f) | 8) We request the government clarify whether one or two Past Performance Questionnaires are required for each contract Offerors are referencing. The instructions require we send a PPQ to both the Contracting Officer (CO) and the Contract Technical Representative (CTR). Should we request each organization submit two PPQs to the Government or only one (either the CO or the CTR). | 8) Please see SF 1449, Amendment 2. |
| Solicitation W911S024R0003 Page 62 (i)(b) VOLUME I – Past Performance | 9) In order to ensure bidders have the requisite experience required to support the EMC, will the Government disallow the use of meaningful involvement when evaluating both prime and subcontractor past performance? Reliance on the experience of an affiliate entity is misplaced if the affiliated concern does not contribute to performance of the contract. | 9) The Government will allow the information as set forth in the referenced paragraph. Please see SF 1449, Amendment 2. |
| Solicitation W911S024R0003 Page 64 (iv) Vol. IV (3) Tab B | 10) Will the Government be releasing a Standard Form 30 for the Amendment(s) released on sam.gov on Monday, March 4, 2024. If not, we request the Government provide guidance for how Offerors should acknowledge receipt of the new RFP documents. | 10) Contracting Office erroneously did not release the amended SF 1449 on SAM.gov. As such, the Contract Office does not require acknowledgement for Amendments 1 & 2 in SAM. SAM Amendment 3/1449 Amendment 1 was released 15 March 2024. The Contracting Office requests acknowledgement for SAM Amendment 4 which will take into account all of the questions received in response to the solicitation. Note that the SF 1449 will show Amendment 2 due to this error on the Contracting Office's part. |
| Solicitation W911S024R0003 Page 64 (iv) Vol. IV (3) Tab B | 11) If no SF 30 will be released, we request the Government state which SF 1449 should be completed in accordance with the RFP instructions. | 11) Please refer to the answer on question 10 as it answers this question. |
| Solicitation W911S024R0003 Page 65-66 (iv) Vol. IV (6) Tab E & PWS Sect. 1.1 | 12) The General Information Volume asks for the offeror's ability to access the required websites as referenced in PWS Paragraph 1.1. This paragraph references the Visual Information Ordering Site (VIOS), but no other websites. Please clarify what information the Government is seeking for this section. | 12) Please see SF 1449, Amendment 2. |
| Solicitation W911S024R0003 Page 65 & 94 (iv) Vol. IV (6) Tab E & PWS Sect. 5.3 | 13) The General Information Volume asks for the offeror's ability to travel to specific sites in accordance with PWS paragraph 5.3 This paragraph the work of the TV/Visual Services task. Please clarify what information the Government is seeking for this section. | 13) Travel is required when the Contractor must provide specific services on-location, e.g. filming a video where the subject matter is located or installing graphic displays/signage at the reimbursable customer's location/Army post. Travel locations are always military posts or commerial locations within CONUS. Trip length varies depending on the mission but is typically 3-10 days. See PWS Section 1.29, p. 16. |
| Solicitation W911S024R0003 Page 74 & 75 Part 1, Sects. 1.16.3, 1.17.7.1, and 1.17.7.2 | 14) We request the Government clarify if all personnel are now required to hold the Information Assurance Technician professional certification requirements. There is an apparent discrepancy between the requirements outlined in Section 1.16.3 and 1.17.7 (stating ALL contractors) vs. the requirements in Sections 1.17.7.1 & .2 (stating Contractors supporting IA/IT Level 1 & II functions): |
1.16.3 Special Qualifications. The Contractor is responsible for ensuring all employees possess and maintain current Information Assurance Technician (IAT) Level II and Level III professional certification training requirements throughout the duration of this contract.
1.17.7 Information Assurance / Information Technology Training. All Contractor employees and associated Subcontractor employees must complete the DoD Information Assurance (IA)/Information Technology (IT) training before issuance of network access and annually thereafter.
Versus :
1.17.7.1 IA/IT Level I. All Contractor employees supporting IA/IT Level I functions shall obtain IA/IT certification within thirty (30) days of contract award as stipulated in DoDD 8570.01–M, Information Assurance Workforce Improvement Program.
| 1.17.7.2 IA/IT Level II and Level III. All Contractor employees working IA/IT Level II and Level III functions must comply with DoD and Army training requirements in accordance with DoD 8570.01, Certification Requirements; DoD 8570.01–M; and AR 25–2, Information Assurance, within six (6) months of appointment to IA/IT functions. | 14) Please see updated PWS in Attachment 5. | ||
| Solicitation W911S024R0003 Page 90 Part 4, Section 4.3 | 15) We request clarification why Section 4.3 is included under Contractor-Furnished Items and Services if this requirement is handled by the Government: 4.3 Maintenance and Service Agreements and Subscriptions. The Government will manage and renew maintenance agreements, service agreements, and subscriptions for Visual Information production requirements to support the mission and goals of the EMC. | 15) Please see updated PWS in Attachment 5. | |
| Solicitation W911S024R0003 Page 133 PWS 7.2 | 16) The Deliverables Schedule references 5.1.8.2 After Action Reviews as a deliverable to be provided as requested. There is no 5.1.8.2 nor any reference to After Action Reviews in the PWS. Please clarify the Government's requirement for this deliverable. | 16) Please see updated PWS in Attachment 5. | |
| Attachment 3 Total Evaluated Price | 17) The total prices for each contract period in cells B4 through B8 of the Total Evaluated Price tab of Attachment 3 do not include the Not to Exceed (NTE) values for CLINs x002, x003, and x004. This results in the understatement of the Total Overall Evaluated Price in cell B9. Will the Government consider updating the calculations to include the NTE values? | 17) Please see updated Attachment 3 Pricing Worksheet. | |
| Attachment 3 Base Period Hours | 18) The Base Period Hours of 6,160 for the Mid-Level Fabrication Services Specialist/AudioVisual Services Specialist 3 are not divisible by 2,000, which is the factor used elsewhere to establish a contract full-time equivalent (CFTE). Please clarify or correct the 6,160 hours. | 18) Please see updated Attachment 3 Pricing Worksheet. | |
| Attachment 3 Service Contract Labor Standards | 19) Can an Offeror propose a different Service Contract Labor Standards (SCLS) classification, based on its internal policies, if it differs from the Government's guidance? | 19) Yes, Clause 52.222-42 is a guideline from the Government and suggested. Contractors may propose similar labor categories. | |
| Page 57 PWS 5.13.1.1 | 20) Please confirm the required CMRA Reporting is now conducted in sam.gov. | 20) Please see updated PWS in Attachment 5. | |
| Page 60 PWS PRS | 21) The first row of the Performance Requirements Summary table addresses PWS Section 5.1, which is a general overview of the contract. The Standard Performance requirements provide a specific focus on the work also referenced in Section 5.3. Would the Government consider revising the PRS table to either eliminate reference to Section 5.1 and combine the video services performance expectations listed in 5.1 into 5.3, or better clarify how it intends to measure the general expectations of work performed as it is described Section 5.1? Otherwise, it appears that TV/Video services are assessed twice in the PRS. | 21) Please see updated PWS in Attachment 5. | |
| RFP Pg 3-14, Reference CLINs x0001 | 22) This CLIN is listed as 1 Job – just confirming that the Government is expecting the annual price for the amount on these CLINs. | 22) Yes, the Government expects an annual price for all of the roles included in CLIN 0001. | |
| RFP Pg 55 and Attachment 3, Pricing Worksheet | 23) The Labor Category list in the table on Page 55 does not match the labor categories in the pricing file. The 3rd and 4th lines of the table on Page 55 show “Mid-Level Graphic Designer/” and “Mid-Level Graphic Designer/Graphics Services Specialist 3.” In the pricing worksheet, Line 19 shows the “Mid-Level Graphic Designer/Graphics Services Specialist 3” labor category. Can the Government please confirm the DOL mapping for this labor category is the Graphic Artist and that the “Mid-Level Graphic Designer/” labor category mapped to Illustrator II will not be used? | ||
| 23) The Government corrected the DOL equivalent, please see amended SF 1449 for more information. Please note that DOL equivalents in FAR 52.222-42 that the Government uses are suggestions to Contractors, who may propose alternative labor categories. | |||
| RFP Pg 55 and Attachment 3, Pricing Worksheet | 24) The 5th and 6th lines of the table on Page 55 show “Mid-Level II Print Center Specialist/” and “Mid-Level II Print Center Specialist/Graphic Services Specialist III.” In the pricing worksheet, Line 19 shows the “Mid-Level II Print Center Specialist/Graphic Services Specialist III” labor category. Can the Government please confirm the DOL mapping for this labor category is the Graphic Artist and that the “Mid-Level II Print Center Specialist/” labor category mapped to Illustrator II will not be used? | 24) The Government corrected the DOL equivalent, please see amended SF 1449 for more information. Please note that DOL equivalents in FAR 52.222-42 that the Government uses are suggestions to Contractors, who may propose alternative labor categories. | |
| RFP Pg 55 and Attachment 3, Pricing Worksheet | 25) Line 25 of the pricing file shows a labor category “Entry-level Photographic Services Specialist/Photographic Services Specialist I.” In the table on Page 55, line 9 shows a labor category of “Photographic Services Specialist I/Mid-Level” mapped to the DOL Photographer I. Can the Government please confirm if this is the correct matching of the labor categories since both have the Photographic Service Specialist I base, but on is listed as Entry-Level and the other as Mid-Level? | 25) Please refer to the updated table in FAR 52.222-42 in the amended SF 1449. | |
| RFP Pg 55 and Attachment 3, Pricing Worksheet | 26) The table on Page 55, line 7 and 8 show “Mid-Level Photographic Services Specialist/” and “Photographic Specialist 2” both mapped to the DOL Photographer II. Line 24 of the pricing file shows “Mid-Level Photographic Services Specialist/Photographic Services Specialist 2.” Can the Government please confirm this mapping between the pricing file and Page 55 table since they are both mapped to the same DOL job title? | ||
| 26) Please refer to the updated table in FAR 52.222-42 in the amended SF 1449. | |||
| RFP Pg 55 and Attachment 3, Pricing Worksheet | 27) Line 27 of the pricing file shows a labor category “Mid-Level Audio-Visual Presentation Services Specialist/AudioVisual Services Specialist 3.” The table on Page 55, line 11 shows “AudioVisual Services Specialist 3” mapped to the DOL Photographer IV. Can the Government please confirm if this is the correct matching of the labor categories? | 27) Please refer to the updated table in FAR 52.222-42 in the amended SF 1449. | |
| RFP Pg 55 and Attachment 3, Pricing Worksheet | 28) Line 29 of the pricing file shows a labor category “Mid-Level Fabrication Services Specialist/AudioVisual Services Specialist 3.” The table on Page 55, line 12 shows “Mid-Level Fabrication Services Specialist/” mapped to the DOL Exhibit Specialist II and Line 11 shows “AudioVisual Services Specialist 3” mapped to the DOL Photographer IV. Can the Government please clarify the mapping of these labor categories as there is a discrepancy between the pricing file and the table on Page 55? | 28) Please refer to the updated table in FAR 52.222-42 in the amended SF 1449. | |
| RFP Pg 55 and Attachment 3, Pricing Worksheet | 29) The table on Page 55, line 10 shows a labor category of “Sr. Audiovisual Presentation Specialist” mapped to the DOL Photographer V. There is no reference to this labor category in the pricing file. Can the Government please confirm that this labor category does not map to any of the labor categories shown in the pricing file? | 29) Please refer to the updated table in FAR 52.222-42 in the amended SF 1449. | |
| RFP page 61, b. File Packaging | 30) This section specifies that the files are to be provided on CD or DVD rather than an email or other file transfer solution. Can the Government please confirm the requirement for the CD or DVD. | 30) Please see SF 1449, Amendment 2. | |
| RFP Page 61, (i) Volume I | 31) Can the Government please confirm that in the case where a major subcontractor is proposed, the maximum page count for Volume 1 would be 15 pages (10 offeror plus 5 subcontractor) and not the maximum of 10 pages shown in the table at the top of page 61? | 31) Please refer to SF 1449, Amendment 2 regarding this question. | |
| RFP Page 61, (i) Volume I | 32) The requirements for a “major subcontractor” are not defined. Can the Government please clarify what is required for a subcontractor to be deemed a “major subcontractor?” | 32) Please see SF 1449, Amendment 2. | |
| RFP Page 61, (i) Volume I | 33) The RFP states that offerors may submit up to three contracts. Is there a maximum number of contracts that can be submitted from the major subcontractor(s)? | 33) The Government is requesting 3 total references which is a combination of Prime Contractor/subcontractor past performance references. | |
| SAM Posting | 34) The information on SAM was updated on March 4, 2024. In the description area, it references “Amendment 0001” and “Amendment 0002.” No SF30’s were included. Does the offeror need to acknowledge these amendments? If so, would a statement in Volume IV General be sufficient? | 34) Please see the answer to question 10 as this was previously answered. | |
| RFP Page 65, (6) Tab E: Supplementary Information and PWS Paragraph 1.1. | 35) The first bullet references PWS Paragraph 1.1 for a list of websites, does not list any websites. Can the Government please provide the list of websites the offeror is required to access? | 35) Please see updated PWS in Attachment 5. | |
| RFP Page 65, (6) Tab E: Supplementary Information and PWS Paragraph 5.3. | 36) The second bullet requires the offeror to discuss the ability to travel to specific sites in accordance with PWS paragraph 5.3, TV/Video Services. PWS paragraph 5.3 does not provide specific information on travel requirements. Can the Government please provide information on typical travel locations, length of trips, staff traveling, etc. when travel is required for PWS paragraph 5.3? | 36) Please see updated PWS in Attachment 5. | |
| PWS Paragraph 5.3.14 Aerial-Based Video | 37) Would the aerial video be located in Government controlled airspace? |
38) Would aerial video off a Government installation be required?
39) Does the Army require an FAA Licensed spotter in addition to the pilot/video technician to operate a UAV?
40) Can the Government provide information on the model of UAV provided for the aerial-based video requirement?
37) If aerial video were required, it could be located both inside and outside of Government controller airspace.
38) Yes
39) No
40) Any UAV the Contractor would be asked to operate will be in accordance with FAA laws/regulations.
| PWS Paragraph 5.2 Auxiliary Services | 41) Can the Government please provide information on how Auxiliary services are requested, frequency, and leadtimes. How are these services priced? | 41) The EMC receives work requests (through VIOS) from a wide range of Army and DoD customers who "pay" for all above baseline work requests by MIPRing funds to the EMC. Auxiliary services are driven by these customer requests/needs that exceed the EMC's standard capabilities. In the past, this work has included: video production, audiobook production and hiring professional actors. Please see updated PWS in Attachment 5. |
| PWS Section 7.2, Attachment B | The last item for task 5.5.2 lists SOP’s for 7 departments. |
42) What are the 7 departments?
43) Do SOP’s currently exists that would be updated?
44) Does task 5.5.2 reference PWS paragraph 5.5.2? 42) The seven departments are Graphics, Print, Fabrication, Audiovisual (AV), TV/Video, Information Management Technology (IMT), and Production Management/Administration. Please see updated PWS in Attachment 5.
43) The EMC already has SOPs which have been produced by the Government and can continue to be used and updated as needed. Please see updated PWS in Attachment 5.
44) The requirement for the Contractor to deliver SOPs within 30 days has been removed from the Deliverables Schedule. See updated PWS in Attachment 5.
| Attachment 3: Pricing Worksheet | 45) The pricing worksheet is using 2,080 hours per year for a CFTE. This does not take into account any Holiday or other leave hours. May the contractor replace this number with the hours per FTE productive year that we use in our estimating? | 45) Please refer to the updated Attachment 3 Pricing Worksheet. Yes, the contractor may replace the 2080 hours per year for a CFTE. The pricing worksheet is a guideline that the Government believes is a reasonable estimation of level of effort. |
| N/A | 46) In the PWS section 7.3, the Government provided links to sample work. Would it be acceptable to include links to samples of our work in either the Technical or Past Performance volume that would not violate page count? | 46) No, the government is not accepting links to samples of contractor work. |
| D. EVALUATION APPROACH, Technical Approach; RFP page 28 |
Proposal Submission Requirements; Volume II – Technical (Factor 2); Element 1, Section 2; RFP page 63
Relevant Language: “(i) The Offeror’s demonstrated ability to perform the primary tasks as detailed in PWS section 5.0.”
“The Offeror’s ability to perform the primary tasks as detailed in PWS section 5.0.”
| 47) Section 5.0 of the PWS does not define what “primary tasks” are. Can the Government please clarify and confirm which section #s of the PWS are required to be responded to as part of the Technical approach? | 47) Please refer to SF 1449, Amendment 2. |
| Proposal Submission Requirements; Volume I – Past Performance (Factor 1); RFP page 61-62 |
Relevant Language: “This volume shall contain past performance information regarding similar contracts. This volume shall not exceed ten (10) pages plus five (5) pages for each major subcontractor, excluding Past Performance Questionnaire Forms. The offeror shall detail the past performance references using Attachment 1 Past Performance Reference Sheet. Offerors shall submit up to three (3) Government and/or commercial contracts for the prime offeror in performance or awarded recently, which are relevant to the effort required by this solicitation.” 48) Will the Government please confirm that affiliate past performance will be considered (as prime past performance) when submitted by the Offeror, as long as Offeror is able to demonstrate how the affiliate will contribute to the performance of the contract (i.e., workforce, management, facilities or other resources, etc.) and a firm commitment of meaningful participation in the eventual contract?
49) Of the three past performance references, will the Government please confirm that at least one past performance should be presented from the prime offeror.
50) Will the Government please clarify if a total of 10 pages or 15 pages is allowed as the table says the maximum pages are 10 for the volume and narrative states differently (10 from prime and 5 from subcontractor) in text within RFP instructions? 48) Please see SF 1449, Amendment 2.
49) Please see SF 1449, Amendment 2.
50) Please see SF 1449, Amendment 2.
SF 1449 – Block 8 & SAM.Gov
| Relevant Language: Per the SF 1449 block 8 it states Offer Due Date/Local Time - 12:00 PM 29 Mar 2024, within SAM.Gov it states Mar 29, 2024, 03:00 pm EDT | 51) Will the Government please clarify what time the proposal submissions are due 12 or 3 PM EST on March 29th? | 51) Please see SF 1449, Amendment 2. |
| RFP PG 60 1. Proposal Submission Requirements & RFP PG 61 2. Proposal Files |
| Relevant Language: PG 60 - a. Each volume shall be submitted electronically via email. PG 61 - All of the proposal files shall be compressed (zipped) into one file entitled “proposal zip” using WinZip version 6.2 or later, or as separate uploads in their native format, i.e., doc, xls, ppt, etc., and provided on CDs or DVDs. | 52) Will the Government please provide the names, titles, and emails of whom we are to submit our proposals to via email and given that the requirement is for electronic submittals, will the Government please remove the requirement for CDs/DVDs submissions? | 52) Please submit proposals to the Contract Specialist - Jared Maunz, jared.b.maunz.civ@army.mil & Contracting Officer - Benjamin Cady, benjamin.m.cady.civ@army.mil. Please see SF 1449, Amendment 2. |
| DD 254 |
Relevant Language: Box 1.b of the DD254 indicates that offerors must be able to safeguard classified material up to the secret level at the offeror’s facility.
| 53) The PWS does not indicate that any of the work will be performed off-site at the offeror’s facility. Can the Government please confirm that there is no requirement to store classified information at the offeror’s site, and that Box 1.b of the DD254 should be corrected to “None”?” | 53) Please see updated DD 254. |
| PWS Deliverables table on p. 133 |
| Relevant Language: Deliverable item “SOPs for 7 departments” (the last item in the deliverables table on p. 133), the associated PWS reference is PWS 5.5.2 | 54) Will the Government clarify which PWS reference the 7 departments deliverable is applicable to, either 5.5.2 or 5.1.9? | 54) The seven departments are Graphics, Print, Fabrication, Audiovisual (AV), TV/Video, Information Management Technology (IMT), and Production Management/Administration. Please see updated PWS in Attachment 5. | |
| General | 55) Will the Government provide an extension to the proposal due date, extending the proposal due date to two weeks after the answers to questions are released by the Government? | 55) Please see SF 1449, Amendment 2. | |
| Pricing Worksheet Attachment 3 | 56) Are contractors able to modify the estimated number of hours or FTEs in the worksheet? | 56) Please refer to the updated Attachment 3 Pricing Worksheet. Yes, the contractor may replace the 2080 hours per year for a CFTE. The pricing worksheet is a guideline that the Government believes is a reasonable estimation of level of effort. | |
| Pricing Worksheet Attachment 3 | 57) Can the Government please confirm if 2000 hours per FTE is the rate being used on the incumbent contract? | 57) Levels of effort on the pricing worksheet are government estimates based on historical efforts. | |
| PROPOSAL SUBMISSION REQUIREMENTS , (i) VOLUME I – Past Performance (Factor 1), bullet (F) |
| Relevant Language: In the event a CPARS report is not available or not applicable, the offeror shall provide the Past Performance Questionnaire as Attachment 2 to the reference. | 58) Can the Government please confirm - if a CPARS report is not available or not applicable for a particular reference, and the Offeror has a PPQ completed by their customer and submitted direct to the solicitation contracting officer per the solicitation instructions, that only the Attachment 1 Past Performance Reference Sheet is required for said reference as part of this volume? | 58) Contractors are required to provide only the Past Performance Reference Sheet if a CPARS report is not available for a reference. |
| Proposal Submission Requirements, Volume IV General, Tab E- Supplementary Information | 59) The Offeror shall demonstrate its knowledge and understanding of the magnitude and complexity of this requirement and its capability to perform all tasks in the PWS. This language appears to be a copy and paste from Volume II, Element 1: Technical Approach. Can the Government clarify whether this same requirement is also applicable to Volume IV, or if the Government is seeking different information within this volume? |
60) The Offeror shall include a discussion of the offeror's ability to meet or perform the following requirements:
1. The Offeror's ability to access the required websites, as referenced in PWS Paragraph 1.1.
2. The Offeror's ability to travel to specific sites in accordance with PWS Paragraph 5.4.
PWS Paragraph 1.1 does not reference websites. Can the Government please clarify which websites we are to demonstrate our ability to access?
PWS Paragraph 5.3 does not reference sites required for travel to/from. Can the Government please clarify which sites we are to demonstrate our ability to travel to?
59) Please see SF 1449, Amendment 2.
60) Please see updated PWS in Attachment 5.
| Solicitation W911S024R0003 | 61) The issue date has been pushed. Can the Past Performance Questionnaire be sent after March 7, 2024? | |
| 61) Please see amended SF 1449. | ||
| Solicitation W911S024R0003 | 62) What is the list of documents that must be submitted? I see no info on which order they should be in. | 62) The list of documents should be submitted according to their Attachment number and the order listed in addendum to FAR 52.212-1. (VOL I - IV) |
| Solicitation W911S024R0003 | 63) We have sought a Past Performance Questionnaire (PPQ) from our Intelligence Community customer, but due to the classified nature of the work on the contract, they are unable to respond in a timely manner. In lieu of the PPQ, we request the Government allow us to provide the customer’s full contact information (name, address, phone, email) in our proposal so the Government may reach out directly to our customer for evaluation information. | 63) Yes, please refer to SF 1449, Amendment 2 (i) VOL I (g). |
| Past Performance Questionnaire | 64) Our customer completed and submitted their evaluation on the PPQ form released in Amendment 1. We request the Government confirm that they will accept this submission instead of requiring our customer to fill out the same information again and submit on the new form. | 64) The Government will accept submissions received on the older Past Perfomance Questionnaire form. |
| Solicitation W911S024R0003 | 65) Is the Past Performance Reference Sheet what needs to be turned in to qualify as a response, or are you looking for any additional information to be included as well? | 65) Please refer to the Addendum to FAR 52.212-1 in the SF 1449 Amendment 2 for instructions. |