About this file

W911S0-15-R-0005 Amendment 0003

View the file

Other files

File Type Posted
W911S0-15-R-0005_Amendment_0009.pdf PDF
ATTACHMENT_3_-_Summary_Pricing_Sheets_List_of_Individual_Prices_(LIPs)_Excel_(Rev-6).xlsx XLSX spreadsheet
ATTACHMENT_2_-_Summary_Pricing_Sheets_List_of_Individual_Prices_(LIPs)_Word_(Rev-6).docx DOCX document
ATTACHMENT_1_-_Specifications_(Rev_5).docx DOCX document
W911S0-15-R-0005_Amendment_0008.pdf PDF
ATTACHMENT_3_-_Summary_Pricing_Sheets_List_of_Individual_Prices_(LIPs)_Excel_(Rev-5).xlsx XLSX spreadsheet
ATTACHMENT_1_-_Specifications_(Rev_4).docx DOCX document
W911S0-15-R-0005_Amendment_0007.pdf PDF
ATTACHMENT_2_-_Summary_Pricing_Sheets_List_of_Individual_Prices_(LIPs)_Word_(Rev-5).docx DOCX document
ATTACHMENT_2_-_Summary_Pricing_Sheets_List_of_Individual_Prices_(LIPs)_Word_(Rev-4).docx DOCX document
ATTACHMENT_1_-_Specifications_(Rev_3).docx DOCX document
ATTACHMENT_3_-_Summary_Pricing_Sheets_List_of_Individual_Prices_(LIPs)_Excel_(Rev-4).xlsx XLSX spreadsheet
W911S0-15-R-0005_Amendment_0006.pdf PDF
ATTACHMENT_2_-_Summary_Pricing_Sheets_List_of_Individual_Prices_(LIPs)_Word_(Rev-3).docx DOCX document
W911S0-15-R-0005_Amendment_0005.pdf PDF
ATTACHMENT_1_-_Specifications_(Rev_2).docx DOCX document
ATTACHMENT_3_-_Summary_Pricing_Sheets_List_of_Individual_Prices_(LIPs)_Excel_(Rev-3).xlsx XLSX spreadsheet
W911S0-15-R-0005_Amendment_0004.pdf PDF
ATTACHMENT_1_-_Summary_Pricing_Sheets_List_of_Individual_Prices_(LIPs)_Excel_(Rev-2).xlsx XLSX spreadsheet
ATTACHMENT_2_-_Summary_Pricing_Sheets_List_of_Individual_Prices_(LIPs)_Word_(Rev-2).docx DOCX document
ATTACHMENT_2_-_Summary_Pricing_Sheets_List_of_Individual_Prices_(LIPs)_Word_(Rev).docx DOCX document
ATTACHMENT_1_-_Summary_Pricing_Sheets_List_of_Individual_Prices_(LIPs)_Excel_(Rev).xlsx XLSX spreadsheet
ATTACHMENT_3_-_Specifications_(Rev).docx DOCX document
W911S0-15-R-0005_Amendment_0002.pdf PDF
ECTO_Amendment_0001.pdf PDF
ATTACHMENT_2_-_Summary_Pricing_Sheets_List_of_Individual_Prices_(LIPs)_Word.docx DOCX document
ECTO_Solicitation_10-21-15.pdf PDF
ATTACHMENT_2_-_Summary_Pricing_Sheets_List_of_Individual_Prices_(LIPs)_Excel.xlsx XLSX spreadsheet
ATTACHMENT_3_-_Specifications.docx DOCX document
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Programmed and Unprogrammed Drydocking, Cleaning, Painting, Repairs, and Modifications to U. S. Army Active and Reserve Vessels stationed on the East Coast at Fort Eustis, Virginia; Fort Belvoir, Virginia; Morehead City, North Carolina; Sunny Point, North Carolina; and Tampa, Florida

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 03-Nov-2015

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911S0-15-R-0005

X 9B. DATED (SEE ITEM 11)

21-Oct-2015

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

02-Nov-2015

CODE

MICC - FORT EUSTIS

705 WASHINGTON BLVD,

SUITE 126

FORT EUSTIS VA 23604-5327

W911S0 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W911S0-15-R-0005

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

1. The purpose of this Amendment is to provide answers to the following questions from Industry:

Question 1. There are no specifics regarding temporary services that may or may not be required for the various vessels. I understand that these services may not be exactly known but can the government provide a basic requirement regarding shore power and other known service that will be at a minimum required for bidding purposes for each vessel type.

Answer: Answer: Contractor to obtain shore power requirements from TM's and drawings, which are provided upon request as discussed in the solicitation. Contractor to provide services to the vessel that enable them to accomplish all work and comply with the General Requirements.

Question 2. Per Note 8. Liquidated Damages on page 7 of 81 of the Solicitation, are the values indicated a typo?

Answer: No. Based on Industry published day rates for equivalent equipment.

Question 3. Per Note 8, Liquidated Damages on page 7 of 81 of the Solicitation, is this cost a per day charge?

Answer: Yes. Based on Industry published day rates for equivalent equipment.

Question 4. Per Note 8, Liquidated Damages on page 7 of 81 of the Solicitation, if this is the intended value Contractor respectfully requests that Government please provide justification for the LD's increasing 489% since this task order was issued for release in 2013? Contractor also respectfully requests Government's consideration of a more reasonable cost value?

Answer: Based on Industry published day rates for equivalent equipment.

Question 5. In the Specifications document, it appears that some classes of Vessels are not included in the Table of Contents.

Answer: The SLWT class (C.500-512), MWT/CF class (C.550-562) and LCM Mod 2 class (C.750-777) have been incorporated into the Table of Contents. Table of Contents revised accordingly.

Question 6. Contractor notices that Towing is not included in the CLIN's for any of the vessels? Is this because Government intends to bid this as a Section 2 item in each issued task order?

Answer: In the event the Government does not deliver the vessel, Towing will be included as a Section 2 item.

Question 7. Contractor notices that Item C.211 Rudders is not broken down into various line items as it has been in past solicitations. For instance, if this item were broken down into the various components on rudder repairs required such as lower rudderstock bearings, upper bearing ,carrier bearings, etc. this item would be a huge cost savings to the Government since rudders often have selective repairs required. Would Government consider the breakdown of this item accordingly?

Answer: The below items are included in the Specifications. The below were inadvertently not broken out in List of Individual Prices. LIPs revised accordingly.

0211AA Removal, Examination, Repairs and Reinstallation 2 EACH 0211AB Cleaning, Inspection and Repairs 2 EACH 0211AC Lower Rudderstock Bearings Replacement 2 EACH 0211AD Upper Bearings Replacements 2 EACH

0211AE Carrier Bearings Replacements 2 EACH 0211AF Lower Spacer Bearings Replacements 2 EACH 0211AG Shoe Bushings Replacements 2 EACH 0211AH Pintles Shaft Replacements 2 EACH 0211AI Pintles Shoe Plates Replacements 2 EACH 0211AJ Rudder Shoe Plates Replacements 2 EACH

Question 8. Contractor notices that Government has not included abrasive blasting as an option to price in the tanks? Would Government please consider reinserting Abrasive Blasting into the specifications for these overhauls since sometimes these tanks need abrasive blasting since they are beyond the ability to power tool clean? Or is this going to be Section 2 item at the task order level?

Answer: Yes, this item now becomes a section 2 repair if required.

Question 9. In Attachment 3, it references C.900 BK Class Vessel but there are no Specs provided and no CLIN's?

Please advise.

Answer: There are no BK Class Vessels assigned to the East Coast. Items C.900. through C.906. should be DELETED from the Table of Contents. Table of Contents revised accordingly.

Question 10. Under C.200 Specs for the LCU, Contractor does not see a cost line item or Specification for Hull Cleaning (Main Deck and Above)? Was this inadvertently removed?

Answer: No. If required, this will be a section 2 item.

Question 11. Solicitation requests pricing for (12) Classes of U.S. Army watercraft. Several Classes have beams in excess of our current dry docking capacities. Consequently we are unable to dry dock either the LSV vessels or the Derrick Crane Barge. Will the Government consider and accept a proposal for some, but not all, Classes of U.S Army watercraft covered by this solicitation?

Answer: Note 1 on page 6 of the Solicitation states that "All items of work in the List of Individual Prices (LIPs) must be completed in their entirety for the Base Period and four (4) option periods for EACH vessel for which the Offeror wishes to be considered. Offerors are not required to complete the LIPs on the vessels for which they do not wish to be considered. "

Question 12. Review of the solicitation does not reveal a provision for delivery of the U.S. Army watercraft to the Contractor's facility, or for the redelivery back to the watercraft's base of operation.

There appears to be no provision in the Pricing Document for Delivery / Redelivery of the watercraft.

a. How does the Government propose to deliver and redeliver each watercraft to the successful Contractor's facility?

Answer: Army Tug in accordance with (IAW) General Requirements, or Towing will be priced as an item in Section 2 in the Request for Delivery Order Proposal (RDOP).

b. Does the Government intend to impose an "out of port" cost differential to specific responses to each Request for Delivery Order Proposal (RDOP)?

Answer: When Towing is included as a Section 2 item, the cost for Towing will not be evaluated in the contractor's proposal as part of their proposal price.

Question 13. Will the Government provide the current location for each of the principal watercraft (LSVs, LCU 2000s, LT-800 Tugs & ST-900 Tugs)?

Answer: Locations of Vessels are indicated in the OCM Summary Pricing Sheets (Attachment 1, pages 69-73 of the Solicitation).

SUMMARY OF CHANGES

(End of Summary of Changes)