Attachment 1 PWS (Rev-1).pdf
PDF 439 KB Posted
- Attached to
- Lenel OnGuard Software Magnetic Door Locking System Federal contract opportunity
- Solicitation number
- W911RX-24-Q-0047
About this file
This document is a Performance Work Statement (PWS) for a federal contract opportunity to provide the installation of a Magnetic Door Locking System (MDLS) using Lenel OnGuard software for Buildings 210 and 253 on Fort Riley. The key details are:
The contractor shall install 9 secure electronic locks with PIN pads on Building 210 and 5 secure electronic locks with PIN pads, 1 storeroom lock, and 1 lockable crash-bar on Building 253. Each building will have a separate and distinct access control system operating independently to allow facility managers to control and monitor access. The contractor shall also provide training for government personnel on using, troubleshooting, and managing the MDLS systems. The work is to be completed during normal business hours of 0730-1600 Monday through Friday. The PWS includes a Quality Assurance Surveillance Plan, deliverable schedule, and list of government-furnished property. The contract opportunity is solicitation W911RX-24-Q-0047 from the Department of the Army Materiel Command Mission and Installation Contracting Command Fort Hood.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Exhibit E Floor Plans.pdf | ||
| Solicitation Revision 1.pdf | ||
| Exhibit B (Rev-1) Pictures of Building 210.pdf | ||
| Exhibit C (Rev-1) Pictures of Building 253.pdf | ||
| Question-Answers Response 1.pdf | ||
| Attachment 1 PWS.pdf | ||
| Solicitation MDLS Bldg 210 253.pdf | ||
| Attachment 3 Wage Determination.pdf | ||
| Attachment 4 Questionnaire.pdf | ||
| Attachment 2 PRS.pdf | ||
| Exhibit A Pricing Bid Schedule.xlsx | XLSX spreadsheet | |
| Exhibit B Pictures of Building 210.pdf | ||
| Exhibit C Pictures of Building 253.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AUG 22
Revision 1 changes will be listed in “Red”
PERFORMANCE WORK STATEMENT (PWS)
Lenel OnGuard Magnetic Locking System – Building 210 and Building 253
17 JUN 2024
Part 1 General Information
1. General: This is a non-personal service(s) contract under which the personnel rendering the service(s) are not subject, either by the contract’s terms or by the manner of its administration, to the supervision and control usually prevailing in relationships between the Government and its employees.
1.1 Description of Services/Introduction: This is a non-personal service(s) contract to provide the installation of Lenel OnGuard magnetic door locking/unlocking access control systems on Building 210 and 253 on Fort Riley.
1.2 Background: The Army is designated to provide Lenel OnGuard software Magnetic Door Locking System (MDLS) on Building 210 and Building 253 with PIN pad to ensure the security of both buildings.
1.3 Scope: The Contract shall provide non- personal service(s). The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items necessary to perform services as described in the PWS and associated contract documents, except for those items specified in Part 3 Government Property and Services. The Contractor shall perform to the standards and acceptable quality levels identified in this PWS and associated contract documents.
1.4 Objectives: The objective of this contract is to provide the installation and setup of a magnetic controls systems at the access points or doorways for Buildings 210 and 253 on Fort Riley, KS. Each building will have a separate and distinct access control system operating independently that will allow the facility managers to control and monitor access of personnel, locking, unlocking of all access points that are either timed to be open/unlocked or continuously locked to be opened via a keypad code entry to those granted access. End state is an entry control system where someone authorized can type a code on a keypad to enter the facility.
1.5 General Information:
1.5.1 Quality Control Plan (QCP): The Contractor shall develop and maintain a QCP to ensure services are performed in accordance with (IAW) this PWS. The Contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The Contractor's QCP is the means by which it assures that the work provided complies with the requirements of the contract.
The Contractor’s Proposed QCP shall be submitted to the Contracting Officer (KO) through the
Revisions 1 changes will be listed in “Red”
Contracting Officer’s Representative (COR) for review within 10 days after date of contract award.
The Government will review and either notify the Contractor in writing of acceptance of the plan or return their comments to the Contractor within five (5) days. If the Government has provided comments, the Contractor shall then have five (5) days to submit a Final QCP. After receipt of the Final QCP, the Contractor may receive the Contracting Officer’s acceptance in writing. Any proposed changes to the accepted QCP are required to be resubmitted for acceptance by the Contracting Officer no later than five (5) days prior to the anticipated change and before implementation by the Contractor. The timeline noted above will apply for review and acceptance for proposed changes. At a minimum, the QCP must include and answer the following to be acceptable:
(a) A chart showing the organizational structure and lines of authority, the names, qualifications, duties, responsibilities, and classification of each member of the Contractor's Quality Control Team;
(b) How the Contractor will monitor work to ensure performance complies with all deliverables (etc. timelines, deadlines, and goals);
(c) How the Contractor will monitor work to ensure performance complies with all specifications and requirements of the contract, including the contract’s clauses;
(d) How the Contractor will monitor and ensure staff qualifications remain current and valid including Department of Defense (DoD) Contractor Personnel Office (DOCPER) processes/approvals throughout contract performance;
(e) How the Contractor will ensure all keys issued will remain controlled items
(Paragraph 1.7 Key Control);
(f) How the Contractor will inventory and track maintenance of all Government Provided
Equipment / Materials;
(g) How the Contractor will identify, investigate, and correct any non-conforming performance and prevent similar deficiencies in the future; and
(h) How the Contractor will file and save all Quality Control related documents for the life of the contract plus 5 years.
1.5.1.1 Reserved
1.5.1.2 The Contractor shall inform the COR of issues or potential issues that might affect the performance within 2 hours of identifying those issues. Verbal reports shall be followed up by written reports within 2 days.
1.5.2 Quality Assurance: The Government will evaluate the Contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government must do to ensure that the Contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the acceptable quality levels (performance thresholds).
1.5.3 Recognized Holidays: The following provides information on recognized holidays for the purpose of the PWS. If submittal of any documentation (e.g. deliverables, submittals, etc.)
deadlines fall on a holiday, the closest work day prior to the holiday will apply as the deadline for submittal.
1.5.3.1 U.S. Holidays: Work shall not be performed on U.S. federally recognized holidays occurring during the normal workweek unless otherwise directed by the Contracting Officer.
When a U.S. holiday occurs on a Saturday or a Sunday, the holiday is observed on the preceding Friday or following Monday, respectively.
New Year’s Day January 1st M. L. King Memorial Day 3rd Monday in Jan Presidents Day 3rd Monday in February Memorial Day last Monday in May Juneteenth June 19th Independence Day July 4th Labor Day 1st Monday in September Columbus Day 2nd Monday in October Veteran’s Day November 11th Thanksgiving Day 4th Thursday in November Christmas Day December 25th
1.5.3.2 Host Nation Holidays: Reserved
1.5.4 Operating Hours: The Government facility office hours, facility operating hours, and the Contractor support hour requirements often coincide, however, they may differ. Please refer to the following.
1.5.4.1 Government Facility Office Hours: The Government facility office hours are 0800 to 1700, Monday through Friday except U.S. Holidays identified in paragraph 1.5.3.1 above or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings.
1.5.4.2 Government Facility Operating Hours: The Government facility operating hours occur between the hours of 0800 to 1700, Monday through Friday. The Government facility is not open for operations during the recognized U.S. Holidays identified in paragraph 1.6.3.1 above. The Government facility may close due to local or national emergencies, administrative closings, or similar Government directed facility closings and will be communicated by the Contracting Officer to the Contractor.
1.5.4.3 Contractor Support Hours: The Contractor shall provide support between the hours of 0800 to 1700, Monday through Friday when the facility is open. The Government facility is not open for operations during the recognized U.S. Holidays identified in paragraph 1.6.3.1 above. The Contractor shall maintain an adequate workforce at all times, for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce is essential.
1.5.4.3.1 Contractor Work Plan: Reserved
1.5.5 Training Holidays: Reserved
1.5.6 Place of Performance: The work to be performed under this contract will be performed at a Government facility located on Fort Riley, Kansas.
1.6 Security Requirements: The following information is provided on security related matters.
1.6.1 Security Program: Reserved
1.6.2 Personnel Security Clearance Requirements: Reserved
1.6.3 Installation Access: Access to U.S. installations, buildings and controlled areas is limited to personnel who meet security criteria and are authorized. Failure to submit required information/data and obtain required documentation or clearances will be grounds for denying access to U.S. installations, buildings and controlled areas. The Contractor shall ensure that any subcontractors used in performance of this contract complies with these requirements and that all employees, of both the Contractor and any subcontractor utilized by the Contractor, are made aware of and comply with these requirements.
The Contractor shall be aware of and comply with the requirements associated with Installation Access Control. The Government is not liable for any costs associated with performance delays due solely to a firm’s failure to comply with Installation Access Control System (IACS) processing requirements.
The Contractor shall return installation passes to the issuing IACS office when the contract is completed or when a Contractor employee no longer requires access.
1.6.3.1 Installation Pass Log: In addition, the Contractor shall provide the Contracting Officer, via the COR, an Initial Installation Pass Log within three (3) calendar days after contract award. The log must at a minimum contain the following information: The Contractor shall provide the following information: Last, First and Middle Names, government issued personal identifier (e.g. Social Security Number, Federal Identification Number, or Tax Identification Number), date of birth, primary email address.The log shall be updated as employees are added or removed. The Updated Installation Pass Log shall be current and available at any time upon request by the Government and submitted to the COR within five
(5) days after any changes to the log.
1.6.3.2 Individual Termination or Expiration of Employment: The Contractor shall collect the installation access passes the same day employment of an individual has expired or has been terminated and shall return them to the issuing office within two (2) days.
1.6.3.3 Contract Termination or Cancellation: Upon termination or cancellation of this contract, the Contractor shall collect all outstanding installation access passes and return them to the issuing office within two (2) days.
1.6.3.4 Common Access Cards (CAC) and CAC Log: Reserved
1.6.4 Background Checks: Contractor and all associated sub- contractor’s employees shall provide all information required for background checks to meet installation access requirements.
1.6.4.1 U.S. Citizen: Contractors that work with or teach youth under the age of 18 years are subject to U.S background checks. The Requiring Activity Manager will determine the extent of background checks required. The Contractor employee may begin performance of the contract after receiving a favorable local background check. The Contractor agrees to replace the employee should results of the background check, if required, be unfavorable as determined by the Requiring Activity Manager. The Contractor’s replacement of the employee with the unfavorable background check shall be within a timeframe provided by the Requiring Activity Manager. The Contractor shall also replace employees whose background check, during their tenure of employment, renders them with an unfavorable local or stateside background check, as determined by the Requiring Activity Manager. The Contractor shall forward a copy to the Contracting Officer via the COR and the Requiring Activity Manager of each favorable background check within two (2) days of receipt by the Contractor, identifying such with the appropriate contract number. The Contractor shall forward a copy to the Contracting Officer via the COR and the Requiring Activity Manager of each unfavorable background check within two
(2) days of receipt by the Contractor, identifying such with the appropriate contract number.
When the Government awards a non-personal services contract directly to an individual, the failure of the individual to provide a favorable background check would be grounds for termination.
1.6.4.2 Local Nationals and Third Country Nationals: Reserved
1.6.5 Physical Security: The Contractor shall safeguard all Government equipment, information, and property provided for Contractor use. At the close of each work period, Government facilities, equipment, and materials shall be secured IAW the Army Physical Security Program (AR 190-13.”)
1.6.6 Operations Security (OPSEC) Requirements: Contractor personnel shall adhere to facility security policies and restrictions. The Contractor shall immediately report suspicious activities to security personnel.
1.7 Key Control: The Contractor shall establish and implement methods of making sure all keys issued to the Contractor by the Government are not lost or misplaced and are not used by unauthorized persons. NOTE: All references to keys include key cards. No keys issued to the Contractor by the Government shall be duplicated. The Contractor shall develop procedures covering key control that shall be included in the Contractor’s Security Plan and the Quality Control Plan. Such procedures shall include turn-in of any issued keys by personnel who no longer require access to locked areas. The Contractor shall immediately report any incidents of lost or duplicate keys to the Contracting Officer. In the event keys, other than master keys, are lost or duplicated, the Contractor shall, upon direction of the Contracting Officer, re-key or replace the affected lock or locks; however, the Government, at its option, may replace the affected lock or locks or perform re-keying. When the replacement of locks or re-keying is performed by the Government, the total cost of re-keying or the replacement of the lock or locks shall be deducted from payment due to the Contractor. In the event a master key is lost or duplicated, all locks and keys for that system shall be replaced by the Government and the total cost deducted from the payment due to the Contractor. The Contractor shall prohibit the use of Government issued keys by any persons other than the Contractor’s employees. The Contractor shall prohibit the opening of locked areas by Contractor employees to permit entrance of persons other than Contractor employees engaged in the performance of assigned work in those areas, or personnel authorized entrance by the Contracting Officer.
The Contractor shall establish and implement methods of ensuring that all lock combinations are not revealed to unauthorized persons. The Contractor shall ensure that lock combinations are changed when personnel having access to the combinations no longer have a need to know such combinations. These procedures shall be included in the Quality Control Plan.
1.8 Post Award Conference/Periodic Progress Meetings: The Contractor shall attend any post award conference convened by the contracting activity or contract administration office in accordance with FAR Subpart 42.5. The Contracting Officer, COR, and other Government personnel, as appropriate, may meet periodically with the Contractor to review the Contractor's performance. At these meetings the Contracting Officer will apprise the Contractor of how the Government views the Contractor's performance and the Contractor shall apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the Government.
1.8.1 The Contractor shall attend, participate in, and furnish input to scheduled and unscheduled meetings, conferences, and briefings that relate to the functions and services herein as required by the Government to provide effective communication and impart necessary information. The Contract Manager or designated representative shall attend meetings as requested by the Government. Meeting attendees shall at times include Contractor managerial, supervisory, and other personnel knowledgeable of the subject matter.
Meetings may start or end outside of regular duty hours.
1.9 Contracting Officer’s Representative (COR): Refer to Part 2 of this PWS for the definition of a COR. As determined by the Contracting Officer, a COR will be appointed and identified by letter of designation, a copy of which will be provided to the Contractor by the Contracting Officer. The designation letter states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates, or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order. The COR monitors all technical aspects of the contract and assists in contract administration. The COR is not authorized to obligate the Government. If the work is not written in the contract, the COR is not authorized to request new work. The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract, perform inspections necessary in connection with contract performance, maintain written and oral communications with the Contractor concerning technical aspects of the contract, issue written interpretations of technical requirements, including Government drawings, designs, specifications, monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies, coordinate availability of Government property, and coordinate site entry of Contractor personnel.
1.10 Key Personnel: The following personnel are considered key personnel by the Government: The Contractor shall provide a Program/Contract Manager who shall be responsible for the performance of the work. The name of this person and an Alternate Program/Contract Manager, who shall act for the Contractor when the Program/Contract Manager is absent, along with a Curriculum Vitae (CV) for each of these individuals, shall be provided in writing to the Contracting Officer no later than no later than five (5) days after contract award. (Acceptance of the CV by the Contracting Officer is required before these individuals are permitted to perform any task on this contract.) The Contract Manager and Alternate Contract Manager shall have full authority to act for the Contractor on all contract matters relating to daily operation of this contract. The Contract Manager or Alternate Contract Manager shall be available between 0800-1600, Monday through Friday except during Federal Holidays during the installation work period(s) for each building Those requirements are also identified in paragraph 1.6.4. Qualifications for all key personnel are listed below:
a. Contract Manager and Alternate Contract Manager: The Contractor shall provide a contract manager who shall be responsible for the performance of the work. A primary and alternate contract manager shall be appointed in writing. The alternate contract manager may act on behalf of the Contractor/Company. The contract manager or alternate shall have full authority to act for the Contractor on all contract matters relating to daily operations of this contract. The contract manager or alternate shall be available between 0730 AM to 1600 PM Local Central Mountain Time., Monday-Friday except Federal Holidays or when the Government facility is closed for administrative reasons. They are to be certified or licensed representatives to coordinate and oversee the installation of Lenel OnGuard software Magnetic Door Locking System (MDLS) and then train Government employees how to use, troubleshoot and manage the daily operations of the MDLS to its full potential. Basic understanding of carpentry and resolving installation challenges, such as selecting pin pad locations, mounting and traffic are needed.
b. Quality Control Manager: Is a certified or licensed representative with 5 years of experience or has performed similar MDLS work done on government buildings. Quality Control Manager should also have basic MDLS installation, carpentry and troubleshooting skills of the installation of Lenel OnGuard software (MDLS). Quality Control Manager must also be able to assure training for Government employees on how to use, troubleshoot and manage the daily operations of the MDLS to its full potential. Basic understanding of carpentry and resolving installation challenges, such as selecting pin pad locations, mounting and traffic are needed.
c. Systems Administrator: Is a certified or licensed representative with 5 years of experience or has performed similar MDLS work done for access control of government buildings.
Systems Administrator must assure the system(s) installed work in accordance with industry and MDLS standards and assist in training Government employees on how to use, troubleshoot and manage the daily operations of the MDLS to its full potential. Basic computing skills in a Microsoft Office setting with a laptop is required.
d. Special Qualifications: All are certified or licensed representatives with MDLS that can install, operate and troubleshoot the product(s) and possess the capability to train Government employees on the use, how to troubleshoot and manage a MDLS to the industry standard and/or full potential. Basic understanding of carpentry and resolving installation challenges, such as selecting pin pad locations, mounting and traffic are needed.
1.11 Identification of Contractor Employees: All Contractor personnel attending meetings, answering Government telephones, and working in other situations where their Contractor status is not obvious to third parties must identify themselves, to include proper marking of signature blocks in correspondence, to avoid creating an impression in the minds of members of the public that they are Government officials. The Contractor shall ensure that all documents or reports, produced by Contractors are suitably marked as Contractor products or that Contractor participation is appropriately disclosed.
1.12.1 Reserved
1.12.2 Contractor Identification Badges: Contractor personnel shall be easily identifiable through the display of badges IAW Contractor Identification (AE Reg. 27-715). The Contractor (to include subcontractors) shall provide each of their employees an easily readable identification badge. The badge must include the employee’s name, the contractor’s company name, the functional area of assignment, and a recent color photograph of the employee.
Companies with U.S. Government contracts will require their employees to wear these badges visibly when performing work at Government workplaces unless this would be impractical because of mission or safety considerations. The Contractor shall collect all ID Badges upon completion of the contract or termination of employee. A listing of issued ID cards shall be furnished to the Contracting Officer prior to the contract performance date and updated as needed to reflect Contractor personnel changes.
1.13 Contractor Travel: Reserved
1.14 Other Direct Costs (ODCs): Reserved
1.15 Data Rights: The Government has unlimited rights to all documents and materials produced under this contract. All documents and materials, to include the source codes of software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership and copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the Contractor without written permission from the Contracting Officer. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.
1.16 Non-Disclosure Requirements: Reserved
1.17 Protection of Government and Contract Information: Per Public Use Notice of Limitations stated by Defense imagery Management operations Center and contained at www.dimoc.mil/resources/limitations/ , the Contractor shall not cite any information (e.g., contract information, pictures, locations, etc.) obtained through this contract on any hard copy or digital marketing tools to include its company website.
1.18 Non-Disclosure Statements: Reserved
1.19 Organizational Conflict of Interest (OCI): Contractor and subcontractor personnel performing work under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent OCI as defined in FAR Subpart 9.5. The Contractor shall notify the Contracting Officer immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the Contracting Officer to avoid or mitigate any such OCI.The Contractor’s OCI Mitigation Plan will be determined to be acceptable solely at the discretion of the Contracting Officer. In the event the Contracting Officer unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the Contracting Officer may affect other remedies as he or she deems necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.
1.20 Phase In /Phase Out Period: Reserved
1.21 Safety: The following provides information pertaining to Safety and Accident Prevention:
1.21.1 Safety Laws and Regulations: The Contractor shall comply with FAR 52.236-13, Accident Prevention (November 1991), the references contained therein (e.g. U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1))
The requirements under FAR 52.236-13 and specifically of the EM 385-1-1 include, but are not limited to the following:
(a) Before initiation of work at the job site, an Accident Prevention Plan, written by the Contractor for the specific work and hazards of the contract and implementing in detail the pertinent requirements of EM 385-1-1; will be reviewed for acceptance by designated Government personnel. Specific requirements for development of the Accident Prevention Plan are found in 01.A and Appendix A of EM 385-1-1. EM 385-1-1 is available online at www.usace.army.mil.
(b) Before beginning each activity involving a type of work presenting hazards not experienced in previous project operations or where a new work crew or subcontractor is to perform work, activity hazard analysis (AHA) shall be prepared by the Contractor performing the work activity (See paragraph 01.a.09 of EM 385-1-1);
http://www.dimoc.mil/resources/limitations/ http://www.usace.army.mil/
(c) The Contractor shall require subcontractors to submit their plan of operations showing methods they propose to use in accomplishing major phases of work;
(d) The Contractor shall discuss the plans in conferences convened by the Contracting
Officer prior to starting work on each major phase of operation. Plans shall include all pertinent information such as layout of haul roads, access roads, storage areas, electrical distribution lines, methods of providing minimum exposure to overhead loads, and methods of access to work areas. The plan for accomplishing the initial work phase shall be submitted within fifteen
(15) calendar days after award of the contract. Plans for subsequent major phases of work shall be submitted no later than fifteen (15) calendar days prior to initiation of work on each major phase; and
(e) In all areas where construction, demolition, alteration, building, or similar related activities take place, the Contractor shall have the following minimum personal protective clothing and equipment requirements in place for any person working on or visiting the site:
(i) Short sleeve shirt;
(ii) Long trousers;
(iii) Steel-toed safety boots; and
(iv) Hard hat.
1.21.1.1 In addition to other requirements for accident prevention specified in this contract, the Contractor shall comply with all Federal and State requirements governing safety and health protection on construction sites and other applicable occupational safety codes.
The Contractor shall indicate its plan for compliance considering conditions of the work described by the design, technical proposal, operational activities of the Government or others in the area of the work, identification of the coordinator, and implementation of all other accident prevention provisions of this contract.
1.21.1.2 The Contractor shall complete and provide safety notifications required and will provide documented proof to the Contracting Officer via the COR, no later than five (5) days that such notifications were made.
1.22 Environmental Compliance: The following provides information on Environmental Compliance.
1.22.1 Environmental Compliance Plan and Program: Contractors are required to keep the work areas free of hazards, clean up debris and properly dispose of any chemicals according industry standards.
1.23 Required Training: The following provides information on training requirements.
1.23.1 Anti-Terrorism (AT) Level I Training: All Contractor employees, including subcontractor employees, who are employed under the contract, shall complete AT Level I Training within thirty (30) days after contract start date or effective date of incorporation of this requirement into the contract, whichever applies, or ten (10) days after employment of new personnel. Contractor personnel travelling overseas shall complete area of responsibility (AOR) specific AT awareness training for U.S. based Contractor employees and associated subcontractor employees. The Contractor shall submit certificates of completion for each affected Contractor employee and subcontractor employee to the COR (or to the Contracting Officer, if a COR is not assigned) within five (5) days after completion of this training by all employees and subcontractor personnel. AT Level I awareness training is available at https://jkodirect.jten.mil. Contractor personnel shall complete refresher training every twelve
(12) months except AOR specific AT Level I training which shall be completed as required by local AT policies
If training cannot be conducted on the website, the Contractor shall coordinate with the COR who will contact the local AT Officer at their assigned location for classroom training.
Contractor personnel completing training in the classroom will receive a certificate or the training attendance roster signed by the AT Officer. Verification of the training shall be provided to the COR within five (5) days after completion of the training.
1.23.2 OPSEC Training: All Contractor employees, including subcontractors, shall complete Level I OPSEC training within thirty (30) calendar days of employment under this contract.
Verification of the training shall be provided to the COR within five (5) days after completion of the training. OPSEC Level I training is available at http://www.cdse.edu/catalog/elearning/GS130.html. Contractor personnel must complete refresher training every 12 months. Verification of the training shall be provided to the COR within five (5) days after completion of the training.
If training cannot be conducted on the website, the Contractor shall coordinate with the COR, who will contact the local OPSEC Officer at their assigned location for classroom training.
Contractor personnel completing training in the classroom will receive a certificate or the training attendance roster signed by the OPSEC Officer. Verification of the training shall be provided to the COR within five (5) days after completion of the training
1.23.3 iWATCH Training: The Contractor and all associated subcontractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within thirty (30) days after the contract is awarded and within ten (10) days after new employees commence contract performance, with the results reported to the COR within thirty-five (35) days after the contract is awarded and within fifteen (15) days after new employees commence contract performance, Verification of the training shall be provided to the COR within five (5) days after completion of the training. Training slides can be found on the Army OneSource we site:
http://www.myarmyonesource.com/familyprogramsandservices/iwatchprogram/default.aspx https://jkodirect.jten.mil/ http://www.cdse.edu/catalog/elearning/GS130.html http://www.myarmyonesource.com/familyprogramsandservices/iwatchprogram/default.aspx
1.23.4 Information Assurance (IA) Training
1.23.4.1 All Contractor employees, including subcontractors, requiring access to Government information systems shall complete the DoD IA Cyber Awareness Training within thirty (30) days after contract start date or effective date of incorporation of this requirement into the contract, whichever applies, or ten (10) days after employment of new personnel. Verification of the training shall be provided to the COR within five (5) days after completion of the training.
1.23.4.2 All Contractor employees, including subcontractors, working information technology (IT)/IA functions shall comply with DoD and Army training requirements per Information Assurance Training Certification and Workforce Management DoD Directive (DoDD) 8570.01, Information Assurance Workforce Improvement Program DoD 8570.01-M, and Information Assurance AR 25-2 within thirty (30) calendar days of employment. Training is available at https://ia.signal.army.mil/DoDIAA/default.asp .
1.23.5 Personally Identifiable Information (PII): Reserved
1.24 Reserved
1.25 Notice to Proceed: The notice to proceed will be provided as indicated below.
☒The effective date of contract will constitute the date of notice to proceed ☐A notice to proceed letter will be issued ☐The date of the letter transmitting the contract will constitute the date of the notice to proceed
1.26 Electromagnetic Compatibility Directive: Reserved
1.27 Government Property and Services: Refer to Part 3 of this PWS for Government property (GP) for this contract. For all issued GP for this contract, the Contractor shall submit a Property Management Plan to the Contracting Officer and the Property Administrator via the COR within ten (10) days after date of contract award.
1.28 Conventional Forces Europe (CFE) Treaty Verification Inspection: Reserved https://ia.signal.army.mil/DoDIAA/default.asp
PART 2
DEFINITIONS & ACRONYMS
2. Definitions and Acronyms
2.1 Definitions: Although not inclusive of every term used within this PWS, the following provides a list of definitions used throughout this PWS and commonly used in the acquisition field.
Contracting Officer – means a person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings on behalf of the Government. Note: The only individual who can legally bind the Government.
Contracting Officer's Representative (COR) – As defined in DFARS 202.101, means an individual designated and authorized in writing by the Contracting Officer to perform specific technical or administrative functions. DoD Instruction (DoDI) 5000.72, Part II Definitions states the following when defining a COR: “Defined in subpart 202.101 of Reference (f). Any individual delegated responsibilities pursuant to subpart 1.602-2 of Reference (e), regardless of local terminology, must be certified in accordance with this instruction. For example, local terminology can be COR, Contracting Officer’s technical representative, technical point of contact, technical representative, alternate COR, administrative COR, assistant COR, line item manager, task order manager, quality assurance personnel, quality assurance evaluator, or COR management.” In addition, Army Regulation 70-13, Chapter 2, paragraph 2-2g, states, in part, the following when providing other surveillance support personnel to assist the COR when needed, “…These other surveillance support personnel may serve as on-site representatives of the COR in performance of actual contract surveillance if they meet all COR requirements and have been appointed by the Contracting Officer as alternate CORs.”
Contractor – means a supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.
Contractor-acquired Property - means property acquired, fabricated, or otherwise provided by the Contractor for performing a contract and to which the Government has title.
Day – means, unless otherwise specified, a calendar day.
Defective Service – means a service output that does not meet the standard of performance associated with the Performance Work Statement.
Deliverable – means anything that can be physically delivered but may include non-manufactured things such as meeting minutes or reports.
Government-furnished Property – As reflected in FAR 52.245-1, Government-furnished Property “means property in the possession of, or directly acquired by, the Government and subsequently furnished to the Contractor for performance of a contract. Government-furnished property includes, but is not limited to, spares and property furnished for repair, maintenance, overhaul, or modification. Government-furnished property also includes contractor-acquired property if the contractor-acquired property is a deliverable under a cost contract when accepted by the Government for continued use under the contract
Government Property - means all property owned or leased by the Government. Government property includes both Government-furnished and Contractor-acquired property. Government property includes material, equipment, special tooling, special test equipment, and real property. Government property does not include intellectual property and software.
Property Administrator - means an authorized representative of the Contracting Officer appointed in accordance with agency procedures, responsible for administering the contract requirements and obligations relating to Government property in the possession of a Contractor.
High Level Objective (HLO) – means a key overarching result-based objective for a project necessary to achieve the project’s vision. HLOs are similar to Level 2 in a Work Breakdown Structure. Each HLO may contain several statements to flesh out the areas necessary to meet the objective.
Physical Security – means that part of security concerned with physical measures designed to safeguard personnel; to prevent unauthorized access to equipment, installations, material, and documents; and to safeguard against espionage, sabotage, damage, and theft.
Quality Assurance – (or Government contract quality assurance) means the various functions, including, inspection, performed by the Government to determine whether a Contractor has fulfilled the contract obligations pertaining to quality and quantity.
Quality Assurance Surveillance Plan (QASP) – means the key Government-developed surveillance process document, and is applied to Performance-Based Service Contracting (PBSC). The QASP is used for managing Contractor performance assessment by ensuring that systematic quality assurance methods validate that Contractor quality control efforts are timely, effective, and are delivering the results specified in the contract or task order. The QASP directly corresponds to the performance objectives and standards (i.e., quality, quantity, timeliness) specified in the Performance Work Statement (PWS). It provides specific details on how the Government will survey, observe, test, sample, evaluate, and document Contractor performance results to determine if the Contractor has met the required standards for each objective in the PWS. The QASP, with very few if any exceptions, is an internal to Government document.
Quality Control – means all necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.
Statement – means the specific results-based activities required to satisfy HLOs. A statement contains a result, the context of the statement, and the required action(s). Statements focus on “what” is to be accomplished; however they are not prescriptive in describing “how” the outcome is to be achieved. Each HLO may have several statements to flesh out the areas necessary to meet the objective. Statements are similar to Level 3 in a Work Breakdown Structure.
Subcontractor – means one that enters into a contract with a prime Contractor. The Government does not have privity of contract with the subcontractor.
Work Day - The number of hours per day the Contractor provides services in accordance with the contract.
Work Week - Monday through Friday, unless otherwise specified.
2.2 Acronyms: Although not inclusive of every term used within this PWS, or that may be included in an acquisition, the following provides a list of acronyms commonly used in the acquisition field.
ACOR Alternate Contracting Officer's Representative AE Army in Europe AFARS Army Federal Acquisition Regulation Supplement AHA Activity Hazard Analysis AOR Area of Responsibility AR Army Regulation AT Anti-terrorism ATCTS Army Training Certification Tracking System CAC Common Access Card CCE Contracting Center of Excellence CFE Conventional Forces Europe CFR Code of Federal Regulations CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer’s Representative COTS Commercial-Off-the-Shelf DA Department of the Army DD250 Department of Defense Form 250 (Receiving Report) DD254 Department of Defense Contract Security Requirement List DFARS Defense Federal Acquisition Regulation Supplement DMDC Defense Manpower Data Center DoD Department of Defense FAR Federal Acquisition Regulation FRG Federal Republic of Germany GFP Government Furnished Property HLO High Level Objective HIPAA Health Insurance Portability and Accountability Act of 1996 IA Information Awareness IAC Installation Access Control IACO Installation Access Control Office ID Identification
IGCE Independent Government Cost Estimate IT Information Technology JTR Joint Travel Regulation JPAS Joint Personnel Adjudication System KO Contracting Officer OCI Organizational Conflict of Interest OCONUS Outside Continental United States (includes Alaska and Hawaii) ODC Other Direct Costs OPSEC Operations Security PA Property Administrator PII Personally Identifiable Information PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Program QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program RA Requiring Activity RCO Regional Contracting Office SIGE Safety and Health Protection Plan TE Technical Exhibit USAG United States Army Garrison USAREUR United States Army Europe UOM Unit of Measure
PART 3
GOVERNMENT PROPERTY (GP) AND SERVICES
3. Government Property and Services
3.1 Services: Reserved
3.2 Facilities: The Government will provide necessary workspace for the Contractor to support the work outlined in the PWS, IAW FAR 52.237-2.
3.3 Utilities: The Government will provide all utilities in the facility will be available for the Contractor’s use in performance of the tasks outlined in the PWS, etc.The Contractor shall instruct employees in utilities conservation practices. The Contractor shall operate under conditions that preclude the waste of utilities, which include turning off the water faucets or valves, light switches, etc. after using the required amount to accomplish tasks requiring the use of the utilities.
3.4 Equipment: The Government will provide: existing closed network wiring with router switch, standard keyboard, government provided computer / CPU, and Computer Monitor.
3.5 Special Tooling and Test Equipment: Reserved
3.6 Materials: Reserved
3.7 Training: Reserved
3.8 Common Access Cards (CAC): Reserved
PART 4
CONTRACTOR FURNISHED ITEMS AND SERVICES
4. Contractor Furnished Property and Services
4.1 General: The Contractor shall furnish all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items necessary to perform services as described in the PWS and associated contract documents, except for those items specified in Part 3 Government Property and Services.
4.2 Secret Facility Clearance: Reserved
4.3 Materials: The Contractor shall provide the following:
• Software and Licensing – to be deployed on a computer provided by the Government o Lenel OnGuard Software: required PC software will be listed on the bid.
Contractor may substitute materials listed below (no used or refurbished equipment allowed)
• (3) Board enclosure and power supply
• (3) Lenel FIPS Compliant 2 door network controller
• (5) Lenel Dual Reader module
• (6) 12V 7AH Backup Battery
• (13) HID SIGNO Keypad PIV class Reader
• (8) Wbox Request to Exit Motion Sensor
• (16) Honeywell Door Position Switch
• (9) HES 9400 Electric Strike
• (1475) Composite Access Control Cable
• (2) MS Sedco Time Delay Module
• (1) Best Storeroom Knob Lock SFIC Core (keying by DPW)
• (2) Von Duprin Electrified Rim Exit Devise
4.4 Vehicles and Equipment: The Contractor shall provide all necessary vehicles and equipment to perform the work described in this PWS. Contractor's vehicles and equipment used in the performance of this contract shall meet all local traffic, safety, and environmental requirements. Vehicles and equipment found to be unsafe shall be removed from the installation and replaced. The Contractor shall not use any Government-owned tools, materials, or parts to maintain Contractor vehicles and equipment without prior written approval of the Contracting Officer. The COR may inspect the Contractor’s vehicles and equipment at any time.
4.5 Background Checks): The Contractor shall provide Background Checks in accordance with this PWS and as determined by the Government.
PART 5
SPECIFIC TASKS
5.1 Basic Services:
The Contractor shall provide the installation of a Magnetic Door Locking System
(MDLS) using Lenel OnGuard software on Building 210 and Building 253 for security purposes. The MDLS will need to have an active PIN pad and will need to have an embedded Common Access Card (CAC) reader that are Federal Information Processing Standards (FIPS) complaint that can be activated with a software update. In accordance with these assignments, the contractor provides a Lenel certified Value Added Reseller for the installation. Furthermore, the MDLS will require door hardware / mechanical hardware installation as well as the software integration.
The contractor shall install and setup magnetic control systems at the access points or doorways on Building 210 and 253.The contractor shall install nine (9) ten (10) secure electronic locks on Building 210 with an active PIN pad. The contractor shall install five (5) secure electronic locks on Building 253 with active PIN pad, one (1) lockable crash-bar, and 1 storeroom locking door. The installation, setup, and cable infrastructure are to be provided by the contractor.
Each building will have a separate and distinct access control system operating independently that will allow the facility managers to control and monitor access of personnel, locking, unlocking of all access points that are either timed to be open / unlocked or continuously locked to be opened via a keypad code entry to those granted access. End state is an entry control system where an authorized user can enter a code on the keypad to enter the facility.
5.2 Tasks: Tasks consist of the following:
5.2.1 The contractor shall install nine (9) ten (10) secure electronic locks on Building 210 with an active PIN pad that has a separate and distinct access control system operating independently that will allow the facility managers to control and monitor access of personnel, locking, unlocking of all access points that are either timed to be open / unlocked or continuously locked to be opened via a keypad code entry to those with authorized access.
The contractor shall install five (5) secure electronic locks on Building 253 with an active PIN pad that has a separate and distinct access control system operating independently that will allow the facility managers to control and monitor access of personnel, locking, unlocking of all access points that are either timed to be open / unlocked or continuously locked to be opened via a keypad code entry to those with authorized access. Building 253 also requires one (1) storeroom lock and one (1) lockable crash-bar.
5.2.2 The contractor shall install hardware to exterior doors, with magnetic door locks that must respond to system commands as directed from the stand-alone computer. This includes doors locking and unlocking as “timed.” Individual card swipes or pin/keypad must be able to activate magnetic lock upon a valid input method.
5.2.3 The contractor shall provide a system in which users and CORs must be capable of manipulating exteriors doors/magnetic locks at will and with all systems commands reacting with 100% accuracy. System users must be capable of performing periodic access audits and denial reports without prior notice. Contractor shall ensure access system can grant or deny access, by individual or group, without prior notice to users or CORs.
5.2.4 The contractor shall input magnetic door lock commands via government furnished desktop computer.
5.2.5 The contractor shall…