Attachment 6
Deliverables
1. Where to Submit: The Contractor submit submittals to the Contracting Officer, Mission and Installation
Contracting Command, Directorate of Contracting, 1792 12th Street, Fort Riley, Kansas 66442, unless otherwise indicated in the schedule below.
2. When to Submit: Submit submittals when required in the schedule below. The first delivery order will not be issued until the required submittals have been approved by the Government. The approved Quality Control Plan, Accident Prevention Plan, and Management Plan shall be implemented not later than the contract start date. The
Contractor shall resubmit the plans within 5 working days prior to any proposed changes in the plans.
3. What to Submit: All submittals shall be accompanied by properly filled out ENG Form 4025 (Mar 2012), Transmittal of Shop Drawings, Equipment Data, Material Samples, or Manufacturer’s Certificates of Compliance, unless otherwise indicated in the schedule below. This ENG Form in Adobe .pdf fillable form format is available without cost at http://www.usace.army.mil/publications/. Submittals shall be grouped together by paragraph in the
PWS and submitted on one ENG 4025 form for each paragraph. Submit one copy of all submittals for review in
Adobe .pdf format by email or on a CD-RW or DVD+RW disc along with one item of any required physical material samples. The Government will review the submittals, enter the appropriate Submittal Action Code in column i on ENG Forms 4025 and return the submittals to the Contractor by email or on the CD-RW or DVD+RW along with any physical material samples. The preceding requirements also apply to any necessary resubmissions.
Item Description, Reference When Due, Submit To
ENG Form
4025 Required
Contract Manager, PWS 2.1.11.1 Post Award Conference, KO Yes
Employee List, PWS 2.1.11.5 30 calendar days after Contract Award date /
3 calendar days after any change, KO
Yes
Employee Training, PWS 2.1.11.6 30 calendar days after Contract Award date, KO
Yes
AT Level I and OPSEC Awareness Training
Completion Certificates, iWatch Program
Information Briefing Report, and Annual
Training Plan, PWS 2.2.1.3.1, 3, 4, & 6
30 calendar days after Contract Award date, KO
Yes
Special OPSEC Requirements, PWS
2.2.1.4.1 & 2
30 calendar days after Contract Award date, KO
Yes
Key Control Procedures, PWS 2.2.1.5 Post Award Conference, KO Yes
Accident Prevention Plan, PWS 2.2.2.2 Post Award Conference and within 5 calendar days of any change, KO
Yes
Technical Report of U.S. Army Ground
Accident, PWS 2.2.2.2.4
Within 5 calendar days of each accident occurrence
No
Contract Manager and Alternate
Qualifications, PWS 2.2.3.1
30 calendar days after Contract Award date, KO
Yes
Site Supervisor and Alternate Qualifications, PWS 2.2.3.2
30 calendar days after Contract Award date, KO
Yes
Proof of Training, PWS 2.2.3.3 30 calendar days after Contract Award date, KO
Yes
Redlined As-Built LPS Drawings, PWS
3.2.7.1
Within 30 calendar days of the completion of repairs, inspections, and certification testing of the LPS systems, KO
Yes
Updated LPS Visual Inspection and
Certification Testing Report, PWS 3.2.7.2
Within 30 calendar days of the completion of inspections and certification testing of the
LPS systems, KO
Yes
LPS Project Summary, PWS 3.2.7.3 Within 30 calendar days of the completion of repairs, inspections, and certification testing
Yes http://www.usace.army.mil/publications/ or the LPS systems or completion of project work, KO
Contractor Manpower Equivalent (CME)
Report, PWS 3.4
NLT 31 October each contract period, http://www.ecmra.mil
No
Management Plan, PWS 3.6.1 Post Award Conference, KO Yes
Master Work Schedule, PWS 3.6.2 30 calendar days after Contract Award date, KO
Yes
Quality Control Plan, PWS 4.2 Post Award Conference and within 5 calendar days of any change, KO
Yes
Quality Control Letter of Designation, PWS
4.2.1
Post Award Conference, KO Yes
Quality Control Inspection Schedules, PWS
4.2.2
5 workdays prior to start of schedule, COR No
Daily Quality Control Reports, PWS 4.2.3 9:00 a.m. the following workday, COR No
Insurance, Section H Post Award Conference, KO Yes