This document contains questions and answers regarding a solicitation for construction services at Red River Army Depot. The solicitation seeks a broad range of minor construction projects to support real property sustainment, restoration, modernization, repair and construction of buildings, structures and other real property. Typical project trades include carpentry, road repair, roofing, excavation, electrical, HVAC, fire protection, telecommunications, plumbing, sheet metal, painting, demolition, concrete and welding. The solicitation is expected to be posted on August 3rd 2018 with an offer due date of September 2nd 2018. Questions covered include clarification on labor categories, contract minimums and maximums, statement of work requirements, and past performance documentation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RRAD_MATOC_RFP_Questions_(4th_Wave).pdf | ||
| W911RQ-18-R-0267_0002.pdf | ||
| RRAD_MATOC_RFP_Questions(2nd_Wave).pdf | ||
| RRAD_MATOC_RFP_Questions.pdf | ||
| Attachment_0002_-_Past_Performance_Questionnaire.DOC | DOC document | |
| Amendment_0001_W911RQ-18-R-0267_RRAD_MATOC_.pdf | ||
| Attachment_0001_-_Pricing_Matrix.xlsx | XLSX spreadsheet | |
| Attachment_0002_-_Past_Performance_Questionnaire.DOC | DOC document | |
| RFP_W911RQ-18-R-0267_RRAD_MATOC_.pdf | ||
| RFP_W911RQ-18-R-0267_RRAD_MATOC_.pdf | ||
| Attachment_0002_-_Past_Performance_Questionnaire.DOC | DOC document | |
| Attachment_0001_-_Pricing_Matrix.xlsx | XLSX spreadsheet |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question Number
Document Question/Comments Answer/Response Date Received
Date Posted
1 Solicitation On Attachment_001, the pricing matrix, most of the items are pretty straight forward. However, the welder is not. It makes a difference if the welder is welding pipe or structure steel. Can you please explain what is expected to be inputted as the base and fringe rate?
After review of the Davis Bacon Act (DBA), there is not a minimum wage and fringe that must be paid to welders. Because the "Welders" category represent only 1% or 1200 hours out of 120,000 hours included in the attachment, I would advise all offerors to price its proposed welders to capture a mix of potential welder positions.
8/10/2018 8/22/2018
2 Solicitation Starting on page 6 through page 14 there are various different reports called out.
Are these reports expected to be submitted with the proposal?
These reports are not to be submitted with a proposal. However, these Contract Data Requirements List (CDRL) reports shall be reviewed and submitted at the individual Task Order level.
8/10/2018 8/22/2018
3 Solicitation On pages 55‐65 there are several blanks to be filled in. Is this to be part of our proposal?
Yes, the blanks have to be filled in. 8/10/2018 8/22/2018
4 Solicitation On pages 73‐76 there is mention of a letter of credit. Are we to submit a letter of credit as part of our proposal? If not, is bid bond required in place of the letter?
The offeror may use a 52.228‐14 Irrevocable Letter of Credit (ILC), in lieu of a bid bond or to secure other types of bonds such as performance and payment bonds. The ILC is available as an alternative to a construction bond.
8/10/2018 8/22/2018
5 Solicitation Are there drawings on this project? No 8/14/2018 8/22/2018
6 Solicitation I have a job currently through the MATOC procurement at RRAD that has been completed (original scope of work). The project is not closed out due to a change order that has been held up for months in legal and admin departments. Could I use that project as a past performance even though the project has not been closed out and there is a MOD in waiting?
Please refer to Section L.4.1.1, L.4.1.2, L.4.1.3.4 of the RFP. 8/17/2018 8/22/2018
7 Solicitation We are a General Contractor in the processing of completing our renewed 5 year Contract Application. Can you please provide us with direction as to who will fill out the Past Performance Questionnaire for us?
Please refer to Section L.4.1.3.4 8/21/2018 8/22/2018
8 Solicitation To determine relevant projects can you please tell us what the $ minimum and $ maximum amount the task orders are anticipated to be?
SEE AMENDMENT 0002. The overall contract minimum ($3,000) and maximum ($96.65M) has been added to the Executive Summary in the RFP. Additionally, 52.216‐19 Order Limitations has been added to provide Task Order minimums and maximums.
8/24/2018 8/30/2018
RRAD MATOC
W911RQ‐18‐R‐0267
Question and Answer Tracker
Document Question/Comments Answer/Response Date Received
Date Posted
9 Solicitation Please confirm the total $ magnitude for the MATOC is $10M The contract minimum ($3,000) and maximum ($96.65M) are now included in the RFP.
8/24/2018 8/30/2018
10 Solicitation Are there any page limits on the 3 Volumes? If yes, what are they? No 8/24/2018 8/30/2018
11 Solicitation If we have completed CPARS, can we include them in the back of Volume I? OFFERORS ARE NOT INSTRUCTED TO INCLUDE CPARS IN THEIR
PROPOSAL SUBMITTAL
8/24/2018 8/30/2018
12 Solicitation Can you please provide me the magnitude of this MATOC for the total program ..ex NTE 30,000,000 over the life of contract ?
The contract minimum ($3,000) and maximum ($96.65M) are now included in the RFP.
8/24/2018 8/30/2018
13 Solicitation Can you please provide me the maximum task order price that will be awarded in this program?
See clause 52.216‐19, referenced in answer 8. 8/24/2018 8/30/2018
14 Solicitation Can you please provide the required staffing for a awarded task order ‐ex dedicated superintendent, qc, safety ..ect .. We don’t have any required staffing levels. If required, they would be included in each specific Task Order.
8/24/2018 8/30/2018
15 Solicitation On page 9 of 17 of the RFP, L.4.1.3 Past Performance (m) states, "Copies of the Statements of Work from each of the submitted contracts to establish the relevance of the contract to the scope of work activities listed in L.4.1.2 above." In cases were the Statements of Work were vaguely stated or incomplete, may we include relevant information from the government's project specifications and/or drawings to illustrate relevance?
SEE AMENDMENT 002. SECTION L.4.1.3 (M) HAS BEEN AMENDED TO SAY
" COPIES OF THE STATEMENTS OF WORK FROM EACH OF THE
SUBMITTED CONTRACTS TO ESTABLISH THE RELEVANCE OF THE
CONTRACT TO THE SCOPE OF WORK ACTIVITIES LISTED IN L.4.1.2 ABOVE.
IN ADDITION TO THE COMPLETE STATEMENT OF WORK, THE OFFEROR
MAY PROVIDE SUBSTANTIATING DATA (I.E. DRAWINGS) TO SUPPORT THE
STATEMENT OF WORK.
8/24/2018 8/30/2018
16 Solicitation Per Section L.4.1.3, paragraph M, offerors must provide "Copies of the Statements of Work from each of the submitted contracts to establish the relevance of the contract to the scope of work activities listed in L.4.1.2 above." As it is commonplace for Federal contracts to include sizable Statements of Work (SOW), we respectfully request that offerors be allowed to provide excerpts of SOW's as appropriate in place of entire SOW's. For example, one of our submitted contracts has an SOW of more than 1120 pages. If we are able to provide pages with relevant excerpts only, the SOW page count is reduced to just 11 pages. This will increase the ease of locating information and ease of transmission.
FOR ALL STATEMENTS OF WORK SUBMITTED, L.4.1.3 (J) STATES " IN ITS
DESCRIPTION, THE OFFEROR SHOULD SPECIFY THE LOCATION IN THE
PROPOSAL (TO INCLUDE FILENAME OR DOCUMENT REFERENCE WITH
PAGE AND PARAGRAPH OF THE PAST CONTRACT INFORMATION) THAT
SUBSTANTIATES THE RELEVANCE; "
8/27/2018 8/30/2018
17 Solicitation May we include Final CPAR evaluations to address item (l) "self‐assessment of contract performance" under L.4.1.3?
No, CPARS IS A GOVERNMENT ASSESSMENT. 8/22/2018 8/30/2018
18 Solicitation Can Final CPAR evaluations be provide in lieu of Past Performance Questionnaires?
No
8/22/2018 8/30/2018
Document Question/Comments Answer/Response Date Received
Date Posted
19 Solicitation Is there a page limit associated with the Past Performance Volume? No 8/22/2018 8/30/2018 20 Solicitation I see the requirements regarding final performance and payment bonds within 10 days if awarded, but I am not finding the bid bond requirements and Standard Form 24 or Bid Guarantee provision of the solicitation required for the proposal. Please advise if I have overlooked the bid bond requirement included in this solicitation proposal or is the bid bond a future requirement per task order if awarded a MATOC Contract?
These subject requirements are required within 10 days of Task Order award. The bid bond is a future requirement per task order if awarded a MATOC contract.
8/27/2018 8/30/2018
21 Solicitation The solicitation calls for Payment/Performance bonds within 10 days after being award the project. However, [13.B] In the solicitation form does not indicate whether or not a bid bond is required at this time and I can't find any indication within the RFP. I would just like to verify whether one is needed? And If so, at what percent of the amount?
The bid bond is a future requirement per task order if awarded a MATOC contract.
8/27/2018 8/30/2018
22 Solicitation L.1.2.1 States that the Government minimum acceptance period is 180 calendar days ‐ yet the SF 1442 says 90 days in box 13.D. Please clarify if we are to fill in 180 or 90 in box 17 on the SF 1442 Back Page
SEE AMENDMENT 0002. SECTION L TAKES PRECEDENT OVER BOX 17 OF
THE SF 1442, but BOX 17 HAS BEEN CHANGED TO 180 CALENDAR DAYS.
8/24/2018 8/30/2018
23 Solicitation Our bonding company does not feel that a bid bond is required at this stage of the solicitation. Is it possible that the bid bond and / or irrevocable letter of credit that are referenced in the specifications apply to future, individual task orders once the contract is awarded? If a bid bond is required, we would need additional information regarding assumed contract value, bid bond percentage and the proper form to use.
If a bid bond is required, (1) what contract value should be used / assumed, (2) what bid bond percentage (i.e. 5%, 20%, etc.) is required and (3) which bid bond form do we use?
Correct, the bid bond and / or irrevocable letter of credit that are referenced in the specifications apply to future, individual task orders once the contract is awarded.
8/28/2018 8/30/2018
24 Solicitation If a contractor pays its welder $20 dollars per hour with no fringes, that will be acceptable to the government?
For the Direct Labor Category "Welders", please use the lowest rates prescibed for craft performing operation to which welding is incidental, to determine the minimum Labor and Fringe rates. There are multiple "craft" types that are associated with welding, including the lowest minimum wage craft, "SHEET METAL WORKER, Excludes HVAC Duct Installation". Please use the minimums from this category. To identify the prevailing Davis Bacon Act wage determinations for this locality, go to the website https://wdol.gov/
8/22/2018 9/7/2018
Document Question/Comments Answer/Response Date Received
Date Posted
25 Solicitation In which volume is the bid bond or letter of credit to be inserted? These subject requirements are required within 10 days of Task Order award. The bid bond is a future requirement per task order if awarded a MATOC contract.
8/22/2018 9/7/2018
26 Solicitation Are there any of the other pages to be completed and returned with the three volumes? We understand that the SF1442 is to be inserted in the administrative volume.
See Section L, instruction to offerors. 8/22/2018 9/7/2018
27 Solicitation Some of the items in pages 55‐65 say to be completed by the contracting officer. Are we to leave those sections blank?
See Section L.5.1 8/22/2018 9/7/2018
28 Solicitation Are we to acknowledge all items mentioned on pages 53‐65? See Section L.5.1 8/22/2018 9/7/2018 29 Solicitation In which volume are pages 55‐65 filled in to be inserted? See Section L.5.1 8/22/2018 9/7/2018 30 Solicitation Can a CCASS Performance Review (SF1420) be submitted with the Offeror's proposal in lieu of a PPQ?
No 8/31/2018 9/7/2018
31 Solicitation Can a previously completed PPQ be submitted with the Offeror's proposal in lieu of asking our Clients to complete another PPQ?
No 8/31/2018 9/7/2018
32 Solicitation Can you please send me a list of the MATOC bidders for the Construction at Red River Army Depot (RRAD)?
No 8/31/2018 9/7/2018