This document summarizes four amendments to a solicitation for a base-wide fire alarm transmission system at Aberdeen Proving Ground. The amendments update technical exhibits, add a design after award document, provide answers to bidder questions in an Excel file, update drawings to include Building 65, extend the proposal due date to September 7, 2023, and remove a life safety plan requirement. The solicitation is for the Department of the Army Materiel Command Army Contracting Command at Aberdeen Proving Ground. Bidders are to provide a base-wide fire alarm transmission system across all buildings, including the new Building 65. Technical requirements and drawings have been updated through a question and answer process and four amendments to fully define the scope of work.

View the file

Other files

File Type Posted
QA Amendments 1-3 and 9 - combined 10-25-2023.xlsx XLSX spreadsheet
Appendix B - NSSC FACP Locations-Rev.pdf PDF
W911QY-23-R-1021 Amendment 8.pdf PDF
W911QY23R1021 - Solicitation Posting - 7-31-2023 - Amendment 6.pdf PDF
Summary of Changes for Amendment 1-5 - combined.docx DOCX document
W911QY23R1021 - Solicitation Posting - 7-31-2023 - Amendment 5.pdf PDF
QA Amendments 1 2 and 3 - combined.xlsx XLSX spreadsheet
W911QY23R1021 - Solicitation Posting - 7-31-2023 - Amendment 4.pdf PDF
Summary of Changes for Amendment 1 2 and 3 - combined.docx DOCX document
QA Amendments 1 2 and 3 - combined.xlsx XLSX spreadsheet
W911QY23R1021 - Solicitation Posting - 7-31-2023 - Amendment 2.pdf PDF
QA Amendments 1 and 2 - combined.xlsx XLSX spreadsheet
Summary of Changes for Amendment 1 and 2 - combined.docx DOCX document
Copy of Site-Visit Attendee List.pdf PDF
Attachment 11 - Bid Schedule.xlsx XLSX spreadsheet
W911QY23R1021 - Solicitation Posting - 7-31-2023 - Amendment 1.pdf PDF
Justification and Approval AES Equipment_Redacted.pdf PDF
Attachment 12 - Davis-Bacon Act WD MA20230001.pdf PDF
20230809 - FA Transmission Bidder Qs.xlsx XLSX spreadsheet
Appendix B - NSSC FACP Locations-Rev.pdf PDF
Attachment 13 - Past Performance Questionnaire.pdf PDF
Appendix A - Ground Floor Plan Bld 1.pdf PDF
W911QY23R1021 - Wireless Reporting Fire Alarm Transmission.pdf PDF
Attachment 12 - Past Performance Questionnaire.pdf PDF
Appendix D - NSSC Contractor Request For -.docx DOCX document
Appendix C - NSSC Campus Map.pdf PDF
Attachment 4 - TE -02 Submittal Register.pdf PDF
Appendix B - NSSC FACP Locations.pdf PDF
Attachment 10 - Bid Schedule.xlsx XLSX spreadsheet
Attachment 11 - Davis-Bacon Act WD MA20230001.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Summary of Changes – W911QY-23-R-1021 Amendment 1

1) TE-01 – Design Requirements Updated

a. Section 1.3.9.11 added building 65

b. Sections 1.3.6.4.15, 1.3.2.2, and 1.3.2.4 changed to reference TE-08 Design After Award

c. Table 1.3.9-1 Notes added building 65

2) TE-08 Design After Award Added

a. This document has been added to the Solicitation, and can be found under W911QY-23-R-1021, 1442 Solicitation Document.

3) Contractor Q&A Added

a. Answers from pre-Solicitation Notice and post-Site-Visit have been provided via Q&A Excel Document (see “20230809 – FA Transmission Bidder Q’s.xlsx”).

4) Appendix B, NSSC FACP Locations Drawing Updated

a. Appendix B has been updated to include building 65.

5) External attachments 10, 11, and 12 have been renamed 11, 12, and 13 to allow for inclusion of TE-08.

Summary of Changes – W911QY-23-R-1021 Amendment 2

1) The Requirement at 3.5.3 of TE-08 for “Life Safety Plans” has been removed from this requirement, and is no longer applicable.

2) Combined copy of Q&A for Amendment 1 and 2 added (see “QA Amendments 1 and 2 – combined.xlsx”).

Summary of Changes – W911QY-23-R-1021 Amendment 3

1) Combined copy of Q&A for Amendment 1, 2 and 3 added (see “QA Amendments 1 2 and 3 – combined.xlsx”).

Summary of Changes – W911QY-23-R-1021 Amendment 4

1) The proposal due-date has been extended to 7 September 2023.