This document provides summaries of changes for Amendments 1, 2 and 3 to the Solicitation for a Base-Wide Fire Alarm Transmission System. The Solicitation is issued by the Department of the Army Materiel Command Army Contracting Command Aberdeen Proving Ground. Amendment 1 updates design requirements and drawings to include an additional building, adds a new design document, provides answers to bidder questions, and renumbers external attachments. Amendment 2 removes a life safety plan requirement. Amendment 3 provides a combined set of answers to questions from Amendments 1, 2 and 3. No pricing, response dates or other contract details are included in the summaries of changes.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Summary of Changes – W911QY-23-R-1021 Amendment 1
1) TE-01 – Design Requirements Updated
a. Section 1.3.9.11 added building 65
b. Sections 1.3.6.4.15, 1.3.2.2, and 1.3.2.4 changed to reference TE-08 Design After Award
c. Table 1.3.9-1 Notes added building 65
2) TE-08 Design After Award Added
a. This document has been added to the Solicitation, and can be found under W911QY-23-R-1021, 1442 Solicitation Document.
3) Contractor Q&A Added
a. Answers from pre-Solicitation Notice and post-Site-Visit have been provided via Q&A Excel Document (see “20230809 – FA Transmission Bidder Q’s.xlsx”).
4) Appendix B, NSSC FACP Locations Drawing Updated
a. Appendix B has been updated to include building 65.
5) External attachments 10, 11, and 12 have been renamed 11, 12, and 13 to allow for inclusion of TE-08.
Summary of Changes – W911QY-23-R-1021 Amendment 2
1) The Requirement at 3.5.3 of TE-08 for “Life Safety Plans” has been removed from this requirement, and is no longer applicable.
2) Combined copy of Q&A for Amendment 1 and 2 added (see “QA Amendments 1 and 2 – combined.xlsx”).
Summary of Changes – W911QY-23-R-1021 Amendment 3
1) Combined copy of Q&A for Amendment 1, 2 and 3 added (see “QA Amendments 1 2 and 3 – combined.xlsx”).