ATTACHMENT_05_Prototypical_Proposal_Form_revised.pdf

PDF 16 KB Posted

Attached to
Multiple Award Task Order Contract (MATOC) for Construction Projects and Repairs Federal contract opportunity
Solicitation number
W911QY-16-R-0023
Issued by
Department of the Army Materiel Command Army Contracting Command Aberdeen Proving Ground

About this file

Attachment 05 Prototypical Project Proposal Form

View the file

Other files for this federal contract opportunity

Other files attached to Multiple Award Task Order Contract (MATOC) for Construction Projects and Repairs, newest first.
File Type Posted
Amedment_0004.pdf PDF
Amedment_0003.pdf PDF
Amedment_0002.pdf PDF
WD_MA160001_04-08-2016__MA1_Mod_5.docx DOCX document
Amedment_0001.pdf PDF
ATTACHMENT_0004_of_SOW_Drawings _Hudson_Conversion_Unit_16_(2016)_11x17.pdf PDF
ATTACHMENT_01_Statement_of_Work_(SOW).pdf PDF
W911QY-16-R-0023.pdf PDF
ATTACHMENT_03_Past_Performance.pdf PDF
ATTACHMENT_02_Project_Information_Worksheet.pdf PDF
ATTACHMENT_04_Self_Performing.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W911QY-16-R-0023

ATTACHMENT 05

PROTOTYPICAL PROJECT

PROPOSAL FORM

Date: 21 March 2016

PROJECT TITLE: Conversion of duplex housing Unit 16A & 16B into a single housing unit

PROJECT DESCRIPTION: Project consists of all work required for the conversion of two (2) bedroom duplex housing units into a three (3) bedroom single unit. Demolition of party walls, kitchen, closet, stairs.

Renovation, construction of stairs, flooring, painting, kitchen area, dining area, electrical and mechanical as indicated in the contract documents (SOW, drawings, etc.). All work is to be performed for the conversion of duplex housing Unit 16A & 16B into a single housing unit for the US Army Natick Soldier Systems Center (NSSC) Housing area located in Hudson, MA 01749.

MAGNITUDE OF PROJECT: $100,000 - $250,000

PERFORMANCE PERIOD: 90 Days, after receipt of Notice to Proceed

SITE VISIT: A site visit will take place on 21 April 2016 at 10:00AM. Interested vendors that plan on attending the site visit shall fill out the requested information on NSSC Contractor Access Request Form (Attachment 3 of the Statement of Work), and e-mail the completed form to michael.w.vincent.civ@mail.mil by 2:00PM on 18 April 2016. The meeting location will be provided to Vendors who submit a completed NSSC Contractor Access Request Form.

PERFORMANCE & PAYMENT BONDS: In accordance with FAR 28.102-1 and Contract Clause 52.228-15, Contractors are reminded that any amount awarded over $30,000 shall require Payment Bonds, and awards exceeding $100,000 shall require both Payment and Performance Bonds. All bonds are due no later than 10 days after award.

LIQUIDATED DAMAGES: ( ) YES or (X) NO- reference Contract Clause 52.211-12.

CONSTRUCTION: (X) YES or ( ) NO- reference Contract Clause 52.246-21, Warranty of Construction, is applicable to this task order.

WAGE DETERMINATION: Currently, General Decision Number MA160001 dated 02/19/2016 is applicable to this task order. http://www.wdol.gov/dba.aspx

PROPOSAL DUE DATE: All offers are due with proposal for MATOC basic contract. Failure to provide a price will make offer noncompliant, eliminated from the competition and offeror ineligible for a basic contract award. Basis for award is in the RFP.

Item Number Description Total Project Cost

0001 Conversion of duplex housing Unit 16A & 16B $________________

SIGNATURE: COMPANY NAME

Name and title of person authorized to sign Offer Date: ________________

The following breakdown cost for the Total Project Cost shall all be provided for the Prototypical Project Conversion of duplex housing Unit 16A & 16B:

Division Material Labor Total

W911QY-16-R-0023

Division 2 - Existing Conditions / Demolition ________ ________ ________

Division 6 - Carpentry ________ ________ ________

Division 7 - Thermal Protection ________ ________ ________

Division 9 - Finishes ________ ________ ________

Division 22 - Plumbing ________ ________ ________

Division 23 - HVAC ________ ________ ________

Division 32 - Electrical ________ ________ ________ Sub-Total ________ ________ ________

Overhead (___%) ________ ________ ________ Sub-Total ________ ________ ________

Profit (___%) ________ ________ ________ Sub-Total ________ ________ ________

Bond (___%) ________ ________ ________ Total Project ________ ________ ________