SOL Amendment W911N226QA0080002.pdf
PDF 3 MB Posted
- Solicitation number
- W911N226QA008
About this file
This is a Standard Form 30 Amendment of Solicitation/Modification of Contract for a Lightning Protection System Pole Replacement project. The amendment, issued by the Work LAB CONTR OFF on 17 DEC 2025, modifies the original solicitation W911N226QA008 to clarify the scope of work for CLIN 0003 and related option line items. The key modification changes the description from a generic "Lightning Protection System Pole Replacement" to specifically performing replacement on "65 foot - 80 foot wooden poles" in accordance with Sections 5.2 and 5.3 of the Performance Work Statement.
The amendment also updates the list of contract documents, adding a new Q&A document (Q&A #2) dated 16 Dec 2025 and adjusting page counts for some existing documents. The Wage Determination document now shows 14 pages instead of the previous unspecified count. The contract is administered by the U.S. Army, with the issuing office located in Chambersburg, PA. No changes were made to the contract's pricing, award date, or other substantive terms beyond the clarification of the pole replacement specifications.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.
If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Continuation of Supplies or Services and Prices/Costs
The following CLIN(s) / SLIN(s) / ELIN(s) were modified:
INFORMATION FROM TO CHANGED
BY
Description
Provide all Repairs, Labor, Tools, Parts, and Equipment to perform Lightning Protection System Pole Replacement, in accordance with Sections 5.2 and 5.3 of the Performance Work Statement.
Provide all Repairs, Labor, Tools, Parts, and Equipment to perform Lightning Protection System Pole Replacement on 65 foot - 80 foot wooden poles, in accordance with Sections 5.2 and 5.3 of the Performance Work Statement.
Option Line Item 1003
INFORMATION FROM TO CHANGED
BY
Description
Provide all Repairs, Labor, Tools, Parts, and Equipment to perform Lightning Protection System Pole Replacement, in accordance with Sections 5.2 and 5.3 of the Performance Work Statement.
Provide all Repairs, Labor, Tools, Parts, and Equipment to perform Lightning Protection System Pole Replacement on 65 foot - 80 foot wooden poles, in accordance with Sections 5.2 and 5.3 of the Performance Work Statement.
Option Line Item 2003
INFORMATION FROM TO CHANGED
BY
Description
Provide all Repairs, Labor, Tools, Parts, and Equipment to perform Lightning Protection System Pole Replacement, in accordance with Sections 5.2 and 5.3 of the Performance Work Statement.
Provide all Repairs, Labor, Tools, Parts, and Equipment to perform Lightning Protection System Pole Replacement on 65 foot - 80 foot wooden poles, in accordance with Sections 5.2 and 5.3 of the Performance Work Statement.
Option Line Item 3003
INFORMATION FROM TO CHANGED
BY
Description
Provide all Repairs, Labor, Tools, Parts, and Equipment to perform Lightning Protection System Pole Replacement, in accordance with Sections 5.2 and 5.3 of the Performance Work Statement.
Provide all Repairs, Labor, Tools, Parts, and Equipment to perform Lightning Protection System Pole Replacement on 65 foot - 80 foot wooden poles, in accordance with Sections 5.2 and 5.3 of the Performance Work Statement.
Option Line Item 4003
W911N226QA0080002
INFORMATION FROM TO CHANGED
BY
Description
Provide all Repairs, Labor, Tools, Parts, and Equipment to perform Lightning Protection System Pole Replacement, in accordance with Sections 5.2 and 5.3 of the Performance Work Statement.
Provide all Repairs, Labor, Tools, Parts, and Equipment to perform Lightning Protection System Pole Replacement on 65 foot - 80 foot wooden poles, in accordance with Sections 5.2 and 5.3 of the Performance Work Statement.
List of Contract Documents, Exhibits, or Attachments
The attachments table has changed from:
Identifier Document Name Document Description Reference Identifier
Date Line Item Page Numbers
Document Type
Provided Under Separate Cover
0001 Solicitation Notes(1) Solicitation Notes 12 Dec 2025 2 Attachment No
Performance Work Statement
Performance Work Statement 13 Nov 2025 9 Attachment No
CDRL A001
Training Certificate
CDRL A001 30 Oct 2025 3 Attachment No
CDRL A002 Test Reports
CDRL A002 30 Oct 2025 3 Attachment No
CDRL A003
Warranty
CDRL A003 30 Oct 2025 3 Attachment No
0006 Disclosure of Hours Disclosure of Hours 13 Nov 2025 1 Attachment No
0007 Q&A Questions & Answers 10 Dec 2025 Attachment No
Wage Determination 2015-
Wage Determination 11 Dec 2025 Attachment No
To:
Identifier Document Name Document Description Reference Identifier
Date Line Item Page Numbers
Document Type
Provided Under Separate Cover
0001 Solicitation Notes(1) Solicitation Notes 12 Dec 2025 2 Attachment No
Performance Work Statement
Performance Work Statement 13 Nov 2025 9 Attachment No
CDRL A001
Training Certificate
CDRL A001 30 Oct 2025 3 Attachment No
CDRL A002 Test Reports
CDRL A002 30 Oct 2025 3 Attachment No
CDRL A003
Warranty
CDRL A003 30 Oct 2025 3 Attachment No
0006 Disclosure of Hours Disclosure of Hours 13 Nov 2025 1 Attachment No
0007 Q&A Questions & Answers 10 Dec 2025 1 Attachment No
Wage Determination 2015-
Wage Determination 11 Dec 2025 14 Attachment No
0009 Q&A #2 Questions & Answers 16 Dec 2025 1 Attachment No
The following contract documents were added:
Q&A #2
The following contract documents Page Counts were changed:
DOCUMENT PAGE COUNTS
DOCUMENT NAME FROM TO
Q&A #2 none 1
| IDCode: J |
| Page: 1 |
| Pages: 4 |
| AmendNo: 0002 |
| EffDate: 17 DEC 2025 |
| ReqNo: |
| ProjNo: |
| IssCode: W911N2 |
| AdmCode: |
| IssuedBy: W6QK LAD CONTR OFF |
1 OVERCASH AVE KO, BLDG 2 SOUTH
CHAMBERSBURG, PA 17201-4150
UNITED STATES
BOBIE BURKETT, EMAIL: BOBIE.J.BURKETT.CIV@ARMY.MIL TELEPHONE: 717-267-5283
AdminBy:
SCD: PAS:
| ContractorNameAdd: |
| Code: |
| FacCode: |
| SolChg: 1 |
| SolNo: W911N226QA008 |
| SolDate: 25 NOV 2025 |
| AwardChg: Off |
| AwardNo: |
| AwardDate: |
| Amended: 1 |
| OffrExt: Off |
| OffrNoEx: 1 |
| NoCopies: 1 |
| ApprData: SEE CONTINUATION |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: The purpose of this amendment is to answer questions in response to the Solicitation and revise CLIN x003 extended description. |
| ContNameTitle: |
| CoNameTitle: THOMAS C. HALL |
| ContDate: |
| CODate: 17 DEC 2025 |
File details come from the government source that posted it. Updated .