MCD Industry Day Information(CT Edit).pptx

PPTX presentation 16 MB Posted

Attached to
CHL023 Moose Creek Dam Safety Modification Federal contract opportunity
Solicitation number
W911KB21R0001
Issued by
Department of the Army Corps of Engineers Engineering District Alaska

About this file

This document provides details for a sources sought announcement for the Moose Creek Dam Safety Modification project. The U.S. Army Corps of Engineers Alaska District is seeking information from firms capable of constructing a 4.5 mile mix-in-place barrier wall between 56 to 66.5 feet below the crest of Moose Creek Dam's embankment. The barrier wall must be between 18 to 30 inches wide with a minimum unconfined compressive strength of 200 psi at 28 days and approach 500 psi long term. Interested firms must submit capabilities packages by September 10, 2019 demonstrating experience on similar projects valued between $100 to $250 million completed within the last six years. Packages should include business information, bonding limits, and a completed questionnaire. Firms meeting the experience requirements will be considered for the potential procurement.

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Moose Creek Dam Safety Modification Chena river Lakes Flood Control project Alaska District - CEPOA

Industry Day

Alaska District 12 December 2019

“The views, opinions and findings contained in this report are those of the authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”

Agenda Opening Comments (PTAC)

Contracting

Small Business Introduction

Project Overview (Project Manager/Lead Engineer)

Closing

One-on-One Meetings (If signed up through PTAC)

- See schedule for appropriate time

Contracting Points of Contact Contract Specialists

John McComas (John.L.Mccomas@usace.army.mil)
Christine Dale (Christine.A.Dale@usace.army.mil)

Contracting Officer Aldone Graham (Aldone.R.Graham@usace.army.mil)

Mailing Address

U.S. Army Corps of Engineers
Alaska District
POA-CT, RM 30
PO Box 6898
JBER, AK 99506-0898

DISCLAIMERS

Questions regarding today’s industry day or any material presented shall be emailed to john.l.Mccomas@usace.army.mil no later than 20 December 2019

- Questions will not be answered today
- The Government reserves the right to not answer questions should they chose to do so
- Today’s slides, attendee list, and all questions/answers will be posted tohttps://beta.sam.gov as soon as all answers are consolidated

The information being presented today is draft/preliminary information for the Moose Creek Dam Safety Modification and is subject to change. No offers or proposals will be accepted at this time.

Once the formal solicitation is issued, the solicitation shall be reviewed in its entirety as changes may/will occur from the information presented today till the formal solicitation is released.

Any information presented today does not commit the Government to any particular Contracting means/methods as formal reviews and approvals will direct the acquisition.

Contracting

Contracting All information regarding this acquisition will be posted to https://beta.sam.gov (formally known as www.fbo.gov) once it is available for release.

Solicitation Number is W911KB21R0001 – FAR Part 15 Contracting by Negotiation

- Anticipating Best Value Tradeoff Source Selection

NAICS is 237990 Other Heavy and Civil Engineering Construction

- Small Business Size Standard $39.5 Million

Anticipated contract is FFP

Project Magnitude is between $100,000,000 and $250,000,000

Approved by SBA as Unrestricted Acquisition

- Small Business Subcontracting Plan will be required
- Factor Related to Extent of Small Business Participation Commitment is anticipated

Schedule Tentative Schedule (Calendar Year)

Second Industry Day*-2nd Quarter 2020
Solicitation-1st Quarter 2021
Award-3rd Quarter 2021
Construction Complete-3rd Quarter 2024
Contract Closeout-3rd Quarter 2025

The second industry day tentatively scheduled for 2nd Quarter 2020 (Calendar Year) and may be held at Moose Creek Dam. Information regarding this visit will be posted to https://beta.sam.gov when it becomes available.

Solicitation and all amendments must be signed/acknowledged

Contractors must have an active registration in https://beta.sam.gov and must not be debarred and/or suspended to be considered for award.

USACE-CEPOA Small Business Specialist

Kathy Kinnett
(907) 753-5557
Kathy.J.Kinnett@usace.army.mil

Procurement Center Representative (Alaska)

Randy Miller
(907)229-6939
Randall.Miller@sba.gov

System for Award Management https://beta.sam.gov/

Small Business Administration www.sba.gov

Alaska Procurement Technical Assistance Center https://ptacalaska.org/

Small Business Contacts/Helpful links

Moose Creek Dam Safety Modification Chena river Lakes Flood Control project Jenipher Cate Ph.D.

Project Manager

Coleman Chalup P.E.

Lead Engineer Dam Safety Program Manager

Robert Tedrick P.E.

Design Manager

Alaska District 12 December 2019

“The views, opinions and findings contained in this report are those of the authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”

All information is subject to change once the project is out for bid.

This information represents a 35% design

Project Location

OPERATIONAL SCHEMATIC

Population at risk Operational schematic

Reaches

Project Office Reach 1 Reach 2 Reach 3 Reach 4 Reach 5 Reach 6 Reach 7 Reach 8 Reach 9 Control Works/Chena River

FLOODWAY AND DAM

Control Works (1992 Pool of Record)

NEED TO UPDATE

Geology

Foundation is gravelly sand/sandy gravel that likely exceeds 1000 ft in thickness with a surficial blanket of silt.

The transition from sand and gravel to silt includes layers of sand and silty sand, including fine sand with Cu<3.

The sand and gravel includes gap graded and open work gravel lenses.

Sloughs from meanders and braids, as well as permafrost, complicate the near surface geology.

Chena River Tanana River

600 ft

MCD

SLOUGHS AND PERMAFROST LOCATIONS

Mapped Sloughs Mapped Permafrost

Geophysical Investigation

Capacitive-Coupled Resistivity (CCR) 50 foot depth Electrical Resistivity Tomography (ERT) 300 foot depth Ground Penetrating Radar (GPR) 50 foot depth

Thawed zone at surface

Permafrost at depth

Station 290+00 Cross-transect

Geophysical Investigation – ERT

File Name

Station 410+00 to 490+00 (North of Control Works) Station 230+00 to 390+00 (South of Control Works) Permafrost Embankment zone to ~490 feet NAVD88 High resistivity due to nature of the embankment (Brown to Red) Thawed zone to ~400 feet NAVD88 Lower resistivity due to thawed coarse grained soils (Blue to Green) Deeper frozen zone to ~200 feet NAVD88 High resistivity due to frozen soils (Brown to Red)

Geophysical Investigation – GPR

GPR

Harder to distinguish specific features Shows excavations and different phases of construction

Results Better understanding of permafrost.

Thawed zone between embankment and deeper permafrost across site.

See extent of features (Control Works, sloughs, and phases of work).

Embankment Design

Rock Fill

Geotechnical Investigation – USACE-CEPOA 53 additional borings with continuous sampling.

5,120 feet drilled.

Borings ranging from 60 to 130 feet deep.

Results Encountered permafrost.

Fine grained soil layer around 90 to 110 feet below the ground surface.

Ground truth for Geophysics performed.

Mix Design samples acquired.

Better understanding of foundation conditions.

Encountered zones with cobbles.

Centerline Boreholes

R3 R4 R5 R7 R6 R8 R9

Typical Centerline Boring

Depth of Barrier Wall at 464 feet NAVD88 Sands and Gravel Sand Water Table Type III Fill Semi-Pervious Fill Type I Fill Type II Fill Type II Fill

Typical Downstream Boring

Silt Sand Sands and Gravel Depth of Barrier Wall at 474 feet NAVD88 Water Table

Potential Failure modes

24 ft 40 to 80 ft

Silt Layer Coarse Sand and Gravel Layer

Pooling and Floodway from Chena River Stability Berm Upstream Water Stage <= 525 feet NAVD 88 Continuous Silty sand/fine sand Layer

Boils Boils Downstream – City of North Pole

Impervious silt blanket Moose Creek Dam During periods of high water stages in the Chena River, due to the silty sand and fine sand layer under the silt layer, three modes of failure can occur under the Moose Creek Dam: 1. backwards erosion and piping (horizontal exits), 2. backwards erosion and piping (vertical exits) and 3. contact erosion. These three modes of failure could act independently or together, eventually causing a failure in the dam, leading to flooding and potential risk of loss of life and damage to the cities of North Pole and Fairbanks, and other adjacent communities.

Horizontal Exit Vertical Exit Allowable Seepage Backwards erosion Potential Failure point Contact Erosion Piping

LEGEND

Potential Failure in Dam Fairbanks City of North Pole Backward Erosion and Piping with Vertical Exit Backward Erosion and Piping with Horizontal Exit Contract Erosion

PLAN (BARRIER WALL)

StationWall Depth (feet)Wall Elevation (NAVD88)
240+0021509
240+00243+002156509474
243+00284+0056474
284+00285+005662.5474468
285+00335+0062.5468
335+00336+0062.566.5468464
336+00406+0066.5464
407+00493+0062470

Centerline Boreholes with Barrier Wall Extents

R3 R4 R5 R7 R6 R8 R9

Potential Permafrost and Bedrock Area Potential Permafrost Potential Bedrock

Existing Crest

ALLOWABLE CREST HEIGHT REDUCTION

Existing Crest (ft)Allowable Crest Height Reduction (ft)
Crest Reduction05
Working Platform Width23.53451.561
Min Distance from Drain88

Low Point Drain

Barrier wall (control works tie-in)

Barrier Wall (Control Works tie-in)

Barrier wall tied into sloped concrete wall Sheet pile

Mix Design Findings To Date Bureau of Reclamation Design Standards No. 13: Embankment Design (Table 16.7.11-1)

Dam NameCement Factor
(lb/yd3)Bentonite Content
(% of cement)W/C RatioCoarse/Fine Aggregate Ratio28-day UCS (lb/in2)
Island Copper Mine239222.781.0220
Wister Dam350101.01.39598
Meeks Cabin255151.851.04151
1Based on average for the mix shown.
Golder 2018 Mix Design (with Relief Well Water)

FHWA Design Manual: Deep Mixing For Embankment and Foundation Support (Bench Scale Testing)

Binder FactorCement Factor
(lb/yd3)Bentonite Content
(% of cement)W/C RatioCoarse/Fine Aggregate Ratio28-day UCS (lb/in2)
10 (lb/ft3) (8.16)18718.02.03258
20 (lb/ft3) (13.68)3399.01.38582
25 (lb/ft3) (16.08)4057.21.23934
30 (lb/ft3) (18.27)4666.01.131199
35 (lb/ft3) (20.29)5215.11.061334

Bureau of Reclamation Used for comparison of Mix Design

FHWA

Used Bench Scale Testing to conduct Mix Design

Contractor will be required to perform their own Mix Designs after award of the contract.

Allowable Technology for Barrier Wall construction at moose creek dam Mix in place methods shall be utilized to mix the embankment and foundation materials with Bentonite and Portland Cement in order to construct a Barrier Wall through Moose Creek Dam.

Any methods that utilize a bentonite slurry trench to support the embankment while excavation of the barrier wall takes place will NOT be utilized at Moose Creek Dam. The potential loss of slurry could result in failure of the embankment into the excavation during construction due to highly pervious foundation materials.

12/4/2019

Proposed Construction Criteria/Constraints

Specification
Max Depth66.5 feet
Min Width18 inches
Max Width36 inches
Length25,300 feet (4.5 Miles)
Permeability1E-05 – 1E-06 cm/sec
Unconfined Compressive Strength200 psi @ 28 days
Measure of Acceptance
Verification CoringYes
Insitu Permeability TestingYes
Unconfined Compressive StrengthYes
Permeability on SamplesYes
Homogeneous and ContinuityYes
Connections to Existing Structures
Low Point DrainTie into Sheet Pile
Control WorksTie into Sheet Pile or have positive contact. No embedment.

Closing Comments Email questions to: John.l.Mccomas@usace.army.mil

These slides, attendee list and questions/answers will be posted to the industry day notification once all answers are consolidated.

Reminder: The Government reserves the right to not answer questions should they chose to do so.

image4.png image5.png image6.png image10.jpeg image11.jpeg image12.png image13.jpeg image14.jpeg image15.jpeg image16.jpeg image17.png image18.png image19.jpeg image20.png image21.png image22.png image23.png image24.png image25.png image26.png image27.png image28.png image29.png image30.png image31.png image32.png image33.png image34.png image35.png image36.png image37.jpeg image38.png image39.png image40.png image41.png image42.png image43.png image44.png image45.png image46.png image47.png image48.png image49.png image50.png image51.png image52.png image53.png image54.png image55.png image56.png image57.png image58.png image59.png image60.png image61.png image1.png image2.png image3.png image7.png image8.png image9.png

File details come from the government source that posted it. Updated .