W91151-19-R-0009
| Question # | Reference RFP Section/Paragraph # | Page No.(s) | Reference/Issue | Questions from Industry | Government Responses to Industry |
| 1 | Section J | 93 | Missing Attachment 1 | Will the government please provide Attachment 1 Pricing Spreadsheet? | see amendment 0001 |
| 2 | Section J | 93 | Missing Attachment 2+E4:G12 | Will the government please provide Attachment 2 Past Performance Questionnaire? | provided |
| 3 | Section L | 102 | Date for question submission | Will the government please provide the date for question submission? | All questions are due to the government by 1 July. |
| 4 | Section L, A. 2 | 102 | “All questions regarding this solicitation were required to be submitted by 4:00pm Central Standard Time on 17 December 2018” | Will the Government consider opening the Q&A period back up for questions related to the final solicitation? | All questions are due to the government by 1 July. |
| 5 | Section L, C.1, b and c | 105 | Volume numbering | The Tables showing the volume structure in Section C.1 differ from that listed in Section C.2, specifically with regard to Volume III. Should Volume III be Past Performance or Cost/Price? | Past performance is Volume III and Cost/Price is Volume IV |
| 6 | Section L, C.2.b.iii.1 | 109 | “The format of the response to the individuals TOs PWSs shall be in accordance with Section C, Part 5.9, Task Order Proposal Format, Review and Acceptance.” | In Section C, PWS, there is no Part 5.9 currently listed. Will the Government please confirm that we should format our response in accordance with PWS Part 5.7? | Formant respinses in accordance with PWS 5.8 TASK ORDER PROPOSAL FORMAT, REVIEW AND ACCEPTANCE |
| 7 | C.2.d.4.E | 112 | Attachment 2, Past Performance Questionnaire | A file for Attachment 2, Past Performance Questionnaire was not included on the FBO page, nor in the RFP document. Will the Government please provide Attachment 2? | Please see soliciation for the Past Performance Questionnaire is provided as and attachement on FBO |
| 8 | C.2.d.4.E | 112 | Attachment 2, Past Performance Questionnaire | Will the Government consider changing the due date of Volume III and Past performance questionnaires to the proposal due date as opposed to 15 calendar days from release date? This will ensure the past performance submissions will maintain consistency with any amendments that may be issued throughout the proposal period. | Past performance questionaire is due by 8 July |
| 9 | Section 5.2.1.1 |
5.2.7.1 Page 36 5.2.1.1. A brigade or battalion-sized scenario derived from a higher-level scenario to be determined by the Government and submitted to the Contractor in writing no later than 10 April 2019.
| The delivery date of 10 April 2019 is already past. Will the Government please update the time frame of deliveries post award of the contract? | Please see updated solicitation the dates have been updated | |||
| 10 | 5.3.5 | Page 39 | 5.3.5. The Contractor shall consolidate and format final staff notes based on staff note input |
provided by six Directorates on a bi-monthly (every other month) basis. Each directorate will provide staff notes by the 5th of April, June, August, October, and December 2019 and 5th of February 2020. The Contractor can expect an average of one task every other month.
| Some of these dates are already past due. Will the Government please update the dates of when staff notes will be provided? | Please see updated solicitation the dates have been updated | |
| 11 | Section M, M.d.b.4)D. |
AND
Exhibit A PRS 3rd Row of Table
AND
Section C, 5.3 bottom of Page 1
D. Specific Relevant Contracts – Identify relevant contracts in accordance Past Performance Summary Report listed as Attachment 2 and are limited to 3 pages per reference.
The Contractor shall provide support to the development of a robust CM2E/COEM analytical framework capability…
Technical Reports Office (TRO):
Issue: Section M Evaluation requires Past Performance relevance address the items in Exhibit A PRS. This includes CM2E/COEM identified as PWS 5.3. However, Section C, PWS Section 5.3 is TRO.
Question: Should we address relevancy by the PWS 5.3 or by the PRS 5.3?
Rationale: How we address all PWS sections 5.3, 5.4 and 5.5 are affected by this discrepancy. The PRS and PWS numbers are off for all of these.
| This information has been updated pkease see amendment 0002 | ||
| 12 | Section L.C.c |
Table of Volume requirements for Past Performance (third row):
AND
Section M, M.d.b.4)D.
105 5 pages per reference plus 5 for each major Subcontractor
D. Specific Relevant Contracts – Identify relevant contracts in accordance Past Performance Summary Report listed as Attachment 2 and are limited to 3 pages per reference.
Issue: In multiple places there are limits for past performance of 5 pages in some places 3 pages in some places.
Question: Would the Government please clarify whether the Past Performance reference is 5 pages or 3 Pages.
Rationale: We would like to stay within page limit guidelines.
| 5 pages | |||||
| 13 | Section J | 93 | Attachment 12 – Attachment 1 Pricing Spreadsheet | Issue: This is missing from the FBO site |
Question: Would the Government please upload this missing document.
Rationale: Needed for compliant submission.
| Please see Amendment solicitation with Pricing sheet | |||||
| 14 | Section J | 93 | Attachment 13 – Attachment 2 Past Performance questionnaire | Issue: This is missing from the FBO site |
Question: Would the Government please upload this missing document.
Rationale: Needed for compliant submission and these need to go out ASAP to our customers to meet early submission requirement of Past Performance Volume.
| please see amentment 0001 | ||||
| 15 | Section B | 4 | Phase-In Period |
FFP
30 Day Phase-In Period. IAW the PWS, See Section C.16.1, Period of Performance 1 - 31 October 2019.
FOB: Destination
PSC CD: B599
Issue: Current Bridge proposal ends 30 November 2019. A 30-day transition ending on 31 October 2019 will leave a full month on the current Bridge proposal.
Question: Would the Government consider updating these dates?
Rationale: Will assist with correct information in the proposal.
| the dates have been updated please see amendment 0001 | ||||
| 16 | Section C | 23 | 1.9.26. Transition (Phase In/Out): To minimize any decreases in productivity and to prevent possible negative impacts on additional services, the Contractor shall have personnel on board, during the thirty (30) day phase in/phase out periods. Phase In period: 1 Apr 2019 – 30 Apr 2019. Phase Out period: Last 30 days of the period of performance currently 1 Mar 2024 – 31 Mar 2024. During the Phase In period, the Contractor shall become familiar with performance |
requirements in order to commence full performance of services on the contract start date. A written transition plan shall be submitted within 10 days of notice of award.
Issue: Proposal Submission is 28 June 2019.
Question: Would the Government consider changing these dates to reflect the actual phase-in/phase out in regard to an award?
Rationale: Will assist with correct information in the proposal.
| the dates have been updated please see amendment 0001 | |||||
| 17 | Labor Category Table TE_1_-_ESTIMATED_WORKLOAD_DATA.pdf | 1 | Below are the labor categories and personnel qualifications the Government determined necessary for performance of this requirement. No additional labor categories shall be proposed. | Issue: Labor categories such as Security Specialist and Technical Writer do not have different levels, e.g. Security Specialist I, Security Specialist II, Technical Writer I, Technical Writer II, etc. |
Question: Would the Government consider expanding the Technical Writer and Security Specialist labor categories to include different labor levels?
Rationale: Labor categories such as ORSA, Combat Ops Analyst and S/W Computer Analyst have different levels, allowing appropriate skillsets to be positioned for tasks.
| Please see the amendment 0001 for changes | |||
| 18 | Is there an incumbent contractor currently providing these services? If yes, please provide us with contract details? | Yes The cutrent contract number is W91151-19-D-0003 | |
| 19 | What will be the contract value for this opportunity? | ||
| 20 | In reviewing Section J, List of Documents, Exhibits and Other Attachments, the documents listed do not match what was posted on FBO item for item, therefore, it is difficult to determine if all attachments are present. However, it does it appear that Attachment 12 (Attachment 1) Pricing Spreadsheet, and Attachment 13 (Attachment 2) Past Performance Questionnaire are both missing. Since we have been asked to submit the past performance volume early (14 June by my math), it is imperative that we receive the Past Performance Questionnaire and related information quickly. | The pricing sheet and past performance qurestionair have been uploaded to FBO | |
| 21 | Also, does the government wish to receive either Consent Letters or Client Authorization Letters with the past performance citations? They were not requested in the Section L. | At this time please only submit the documents that were requested in the solicitation. | |
| 22 | The volume numbers in Section L, Paragraph C.2 do not match what is shown in C.1.b. and C.1.c. (specifically Past Performance and Price volumes). Can we assume the volume numbers in C.1 are correct use C.1 as guidance on volume numbering? | This information has been updated please see amendment 0001 | |
| 23 | I assume that an IGE has been done and I'm curious if you can shed any light on a ballpark figure on what the government in expecting to pay on this requirement. I would just like to see if its in line with the private industry right now and if it would be worth our time to put together a proposal. | No | |
| 24 | I note that the PWS states the minimum requirements is a “Secret” level security clearance, however the DD254 states Top Secret. Could you please verify the minimum facility clearance requirements to bid this proposal? | This information has been updated please see amendment 0001 | |
| 25 | The volume numbers in Section L, Paragraph C.2 do not match what is shown in C.1.b. and C.1.c. (specifically Past Performance and Price volumes). Can we assume the volume numbers in C.1 are correct use C.1 as guidance on volume numbering? | This information has been corrected please see amendment 0001 | |
| 26 | What will be the contract value for this opportunity? | ||
| 27 | Is there an incumbent contractor currently providing these services? If yes, please provide us with contract details? |
| Yes The cutrent contract number is W91151-19-D-0003 | ||||||
| 28 | Section L, c. Volume III, b, 1 | 118 | Says “The offeror is requested to submit the Past Performance Volume fifteen (15) calendar days after RFP issuance date…”. In Section L c. Volume III, b, 4, E (Page 119) Says that past performance questionnaires are due not later than 15 calendar days before the RFP closes. However, in the Response to Questions spreadsheet, question 8 says that the Past Performance Questionnaire is due by 8 July. | Will the Government please clarify when the Past Performance Volume and the Past Performance Questionnaires are due? | past performance questionaires are due to the government by July 8th | |
| 29 | 5.1.6.11 CXXI Tracking Tool Tickets: | 37 | Issue: A minimum of 17 tickets per month does not account for the significant variability of ticket difficulty as tickets can cover everything from simple bugs to a new capability. | Would the government consider changing this minimum requirement to 8 per month while leaving the 204 annual requirement in place? Rationale: To account for the extensive variability of the difficulty of tickets. Reducing the minimum monthly tickets will allow the contractor to complete a minimum of 204 tickets and ensure that the governments needs are met. This will give the contractor the flexibility to work on tickets that are most important to the government, instead of those that help them make their monthly quota. | The PWS is being revised and will be posted by 8 July. Please check back for the revised PWS | |
| In regards to the Analytic Engineering Mission Support Service, sol # W9115119R0009, I am still confused on the due dates due to finding multipal dates in the solicitation and on the FBO website. I "think" the past performance document is Due on July 8th and the Final Proposal is due on July 22nd. Can you clear up my confusion. | The final proposal is due on the 22 of July and the past performance questionaire is due on 8 July |