Exhibits.pdf
PDF 252 KB Posted
- Attached to
- FMS Huey II Flight Training Device
- Solicitation number
- W900KK-18-R-0047
About this file
Solicitation Exhibits - CDRLS
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Final_Question_and_Answer.pdf | ||
| Attachment_2_-_Technical_Evaluation_Checklist_-_Rev_1.xlsx | XLSX spreadsheet | |
| Attachment_1_-_SOW_Rev_2.pdf | ||
| Solicitation_W900KK-18-R-0047_-_Amend_2.docx.pdf | ||
| Attachment_1_-_SOW_Rev_2.pdf | ||
| Attachment_1_-_SOW_Revised.pdf | ||
| Solicitation_W900KK-18-R-0047_Amendment_1.docx | DOCX document | |
| Additional_Question_and_Answer.pdf | ||
| HUEY_II_FTD__Industry_Q_and_A_to_Solicitation_W900KK-18-R-0047.pdf | ||
| Attachment_2_-_Technical_Evaluation_Checklist_-_final.xlsx | XLSX spreadsheet | |
| Solicitation_W900KK-18-R-0047.docx | DOCX document | |
| RFP.pdf | ||
| Attachment_1_-_SOW.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SFAE-STRI-TRADE-FMS
6. REQUIRING OFFICE
See Block 16
5. CONTRACT REFERENCE
DI-MGMT-80227
4. AUTHORITY (Data Acquisition Document No.)
3. SUBTITLE
CPSMRSee Block 16
2. TITLE OF THE DATA ITEM
A001
1. DATA ITEM NO.
F. CONTRACTOR
2018-015
E. CONTRACT/PR NO.
Huey II FTD
D. SYSTEM/ITEM
TDP
C. CATEGORY
TM OTHER MGMT
B. EXHIBITA. CONTRACT LINE ITEM NO.
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.
Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
Form Approved OMB No. 0704-0188
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
N/A
8. APP CODE
LT
7. DD 250 REQ
D
9. DIST STATEMENT
REQUIRED
13.DATE OF SUBSEQUENT
SUBMISSION
See Block 16
11. AS OF DATE
N/A
See Block 16
12.DATE OF FIRST
SUBMISSION
ASREQ
10. FREQUENCY
ReproReg
Final
Draft
b. COPIES
a. ADDRESSEE
14. DISTRIBUTION
09-MAY-2018
J. DATE
Meister, Jeffery
I. APPROVED BY
04-APR-2018
H. DATEG. PREPARED BY
Andrade, Richard
Block 2: Contractors Progress, Status and Management Report
Block 5: SOW Paragraph 3.2.1 Logistics Support and 3.6 Program Management
Block 2: Contractors Progress, Status and Management Report
1. BLOCK 9: THE FOLLOWING DISTRIBUTION STATEMENT SHALL BE PLACED
ON DOCUMENT TITLE PAGE AND DISC LABEL (WHERE APPLICABLE):
"DISTRIBUTION STATEMENT D. DISTRIBUTION AUTHORIZED TO THE
DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY FOR REASONS
OF CRITICAL TECHNOLOGY, DETERMINED 30 JAN 2018. OTHER REQUESTS
FOR THIS DOCUMENT SHALL BE REFERRED TO THE PROGRAM EXECUTIVE
OFFICE FOR SIMULATION, TRAINING AND INSTRUMENTATION (PEO STRI)
12211 SCIENCE DRIVE, ORLANDO, FL 32826-3224.
EXPORT CONTROL WARNING. ALL PRINTED AND ELECTRONIC TECHNICAL DATA, INCLUDING
DIGITAL TECHNICAL DOCUMENTS THAT ARE DETERMINED TO CONTAIN EXPORT-CONTROLLED
TECHNICAL DATA SHALL BE MARKED AS SHOWN BELOW.
WARNING - THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY
THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C., SEC 2751, ET SEQ.) OR THE
EXPORT ADMINISTRATION ACT OF 1979, AS AMENDED, TITLE 50, U.S.C., APP. 2401 ET
SEQ. VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE
CRIMINAL PENALTIES.
DISSEMINATE IN ACCORDANCE WITH PROVISIONS OF DOD DIRECTIVE 5230.25.
DESTRUCTION NOTICE FOR CLASSIFIED DOCUMENTS, FOLLOW THE PROCEDURES IN DOD
5220.22-M, INDUSTRIAL SECURITY MANUAL, SECTION 11 -19 OR DOD 5200.01, DOD
INFORMATION SECURITY PROGRAM. FOR UNCLASSIFIED, LIMITED DOCUMENTS, DESTROY BY
ANY METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS OR RECONSTRUCTION OF THE
DOCUMENT.
2. BLOCK 12: SHALL BE DUE 30 CALENDAR DAYS AFTER CONTRACT AWARD.
3. BLOCK 13: SHALL BE DUE MONTHLY THROUGH THE LIFE OF THE CONTRACT.
4. THE GOVERNMENT WILL HAVE 10 CALENDAR DAYS FOR REVIEW AND
ACCEPTANCE OR REJECTION.
5. THE CONTRACTOR SHALL HAVE 5 CALENDAR DAYS TO INCORPORATE
GOVERNMENT COMMENTS.
6. SUBMISSIONS SHALL CONCLUDE 60 CALENDAR DAYS AFTER READY FOR
TRAINING (RFT) OF THE FINAL TRAINING DEVICE.
7. BLOCK 14 : DELIVERABLES SHALL BE DELIVERED VIA ELECTRONIC MAIL
OR OPTIC DISK (CD OR DVD) BASED ON DOCUMENTATION SIZE. ALL
DOCUMENTS FOR GOVERNMENT REVIEW SHALL BE DELIVERED IN XML OR
PLJ, AND NATIVE FORMAT. AFTER GOVERNMENT ACCEPTANCE, ALL
DOCUMENTATION SHALL BE DELIVERED IN BOTH SEARCHABLE PDF AND
NATIVE EDITABLE FORMAT. NATIVE FORMAT IS DEFINED AS BEING
PRODUCED BY COTS SOFTWARE (I.E.MICROSOFT OFFICE, OPENOFFICE,
AUTOCAD, VECTORWORKS, OR OTHERS). ONE COPY OF EACH REPRODUCIBLE
SHALL BE DELIVERED TO THE ATTENTION OF THE ASSISTANT PROJECT
MANAGER AND THE FMS CONTRACT SPECIALIST. DELIVERY SHALL BE MADE
TO THE FOLLOWING ADDRESS: PEO STRI, ATTN: SFAE-STRI-TRADE-FMS,
ATTN: FMS ASSISTANT PROJECT MANAGER AND FMS CONTRACT SPECIALIST,
16. REMARKS 020See Block 16
020 15. TOTALSee continuation sheet...
18.ESTIMATED
TOTAL PRICE
17. PRICE GROUP
Page 1 of 2 PagesPREVIOUS EDITION MAY BE USED.DD FORM 1423-1, FEB 2001
16. REMARKS (Continued)
12211 SCIENCE DRIVE, ORLANDO, FL 32826-3224.
8. DELIVERED FILE TYPE SHALL BE SEARCHABLE PDFs.
9. CONTRACTOR TEMPLATE IS ACCEPTABLE.
10. CONTENT IS DEFINED BY DID; CONTENT TAILORED OUT AS NECESSARY AND IDENTIFIED BELOW:
a) 10.3 (f)
b) 10.3 (g)
c) 10.3 (h)
d) 10.3 (i)
F. CONTRACTOR
2018-015
E. CONTRACT/PR NO.
Huey II FTD
D. SYSTEM/ITEM
TDP
C. CATEGORY
TM OTHER MGMT
B. EXHIBITA. CONTRACT LINE ITEM NO.
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Page 2 of 2 PagesDD FORM 1423-1, FEB 2001
See Block 16
5. CONTRACT REFERENCE
DI-MGMT-81861A
4. AUTHORITY (Data Acquisition Document No.)
3. SUBTITLE
IPMRIntegrated Program Management Report (IPMR)
2. TITLE OF THE DATA ITEM
A002
1. DATA ITEM NO.
F. CONTRACTOR
2018-015
E. CONTRACT/PR NO.
Huey II FTD
D. SYSTEM/ITEM
TDP
C. CATEGORY
TM OTHER MGMTA
B. EXHIBITA. CONTRACT LINE ITEM NO.
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.
Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
Form Approved OMB No. 0704-0188
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
N/A
8. APP CODE
LT
7. DD 250 REQ
D
9. DIST STATEMENT
REQUIRED
13.DATE OF SUBSEQUENT
SUBMISSION
See Block 16
11. AS OF DATE
N/A
See Block 16
12.DATE OF FIRST
SUBMISSION
MNTHLY
10. FREQUENCY
ReproReg
Final
Draft
b. COPIES
a. ADDRESSEE
14. DISTRIBUTION
09-MAY-2018
J. DATE
Meister, Jeffery
I. APPROVED BY
04-APR-2018
H. DATEG. PREPARED BY
Andrade, Richard
Block 5: SOW Paragraph 3.6.1 Integrated Master Schedule (IMS)
1. BLOCK 9: THE FOLLOWING DISTRIBUTION STATEMENT SHALL BE PLACED
ON DOCUMENT TITLE PAGE AND DISC LABEL (WHERE APPLICABLE):
"DISTRIBUTION STATEMENT D. DISTRIBUTION AUTHORIZED TO THE
DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY FOR REASONS
OF CRITICAL TECHNOLOGY, DETERMINED 30 JAN 2018. OTHER REQUESTS
FOR THIS DOCUMENT SHALL BE REFERRED TO THE PROGRAM EXECUTIVE
OFFICE FOR SIMULATION, TRAINING AND INSTRUMENTATION (PEO STRI)
12211 SCIENCE DRIVE, ORLANDO, FL 32826-3224.
EXPORT CONTROL WARNING. ALL PRINTED AND ELECTRONIC TECHNICAL DATA, INCLUDING
DIGITAL TECHNICAL DOCUMENTS THAT ARE DETERMINED TO CONTAIN EXPORT-CONTROLLED
TECHNICAL DATA SHALL BE MARKED AS SHOWN BELOW.
WARNING - THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY
THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C., SEC 2751, ET SEQ.) OR THE
EXPORT ADMINISTRATION ACT OF 1979, AS AMENDED, TITLE 50, U.S.C., APP. 2401 ET
SEQ. VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE
CRIMINAL PENALTIES.
DISSEMINATE IN ACCORDANCE WITH PROVISIONS OF DOD DIRECTIVE 5230.25.
DESTRUCTION NOTICE FOR CLASSIFIED DOCUMENTS, FOLLOW THE PROCEDURES IN DOD
5220.22-M, INDUSTRIAL SECURITY MANUAL, SECTION 11 -19 OR DOD 5200.01, DOD
INFORMATION SECURITY PROGRAM. FOR UNCLASSIFIED, LIMITED DOCUMENTS, DESTROY BY
ANY METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS OR RECONSTRUCTION OF THE
DOCUMENT.
2. BLOCK 12: SHALL BE DUE 30 CALENDAR DAYS AFTER CONTRACT AWARD.
3. BLOCK 13: SHALL BE DUE MONTHLY THROUGH THE LIFE OF THE CONTRACT.
4. THE GOVERNMENT WILL HAVE 10 CALENDAR DAYS FOR REVIEW AND
ACCEPTANCE OR REJECTION.
5. THE CONTRACTOR SHALL HAVE 5 CALENDAR DAYS TO INCORPORATE
GOVERNMENT COMMENTS.
6. BLOCK 14*: DELIVERABLES SHALL BE DELIVERED VIA ELECTRONIC MAIL
OR OPTIC DISK (CD OR DVD) BASED ON DOCUMENTATION SIZE. ALL
DOCUMENTS FOR GOVERNMENT REVIEW SHALL BE DELIVERED IN XML OR
PLJ, AND NATIVE FORMAT. AFTER GOVERNMENT ACCEPTANCE, ALL
DOCUMENTATION SHALL BE DELIVERED IN BOTH SEARCHABLE PDF AND
NATIVE EDITABLE FORMAT. NATIVE FORMAT IS DEFINED AS BEING
PRODUCED BY COTS SOFTWARE (I.E.MICROSOFT OFFICE, OPENOFFICE,
AUTOCAD, VECTORWORKS, OR OTHERS). ONE COPY EACH OF THE
REPRODUCIBLE SHALL BE DELIVERED TO THE ATTENTION OF THE
ASSISTANT PROJECT MANAGER AND THE FMS CONTRACT SPECIALIST.
DELIVERY SHALL BE MADE TO THE FOLLOWING ADDRESS: PEO STRI, ATTN:
SFAE-STRI-TRADE-FMS, ATTN: FMS ASSISTANT PROJECT MANAGERAND FMS
CONTRACT SPECIALIST, 12211 SCIENCE DRIVE, ORLANDO, FL 32826-3224.
7. DELIVERED FILE TYPE SHALL BE SEARCHABLE PDFs AND MIRCOSOFT
PROJECT COMPATIBLE FILES.
8. CONTRACTOR TEMPLATE IS ACCEPTABLE
9. CONTENT IS DEFINED BY DID; CONTENT TAILORED OUT AS NECESSARY
16. REMARKS 020See Block 16*
020 15. TOTALSee continuation sheet...
18.ESTIMATED
TOTAL PRICE
AND IDENTIFIED BELOW:
a) USE FORMAT 6 ONLY
F. CONTRACTOR
2018-015
E. CONTRACT/PR NO.
Huey II FTD
D. SYSTEM/ITEM
TDP
C. CATEGORY
TM OTHER MGMTA
B. EXHIBITA. CONTRACT LINE ITEM NO.
CONTRACT DATA REQUIREMENTS LIST
See Block 16
5. CONTRACT REFERENCE
DI-ADMN-81250B
4. AUTHORITY (Data Acquisition Document No.)
3. SUBTITLE
CMConference Minutes
2. TITLE OF THE DATA ITEM
A003
1. DATA ITEM NO.
F. CONTRACTOR
2018-015
E. CONTRACT/PR NO.
Huey II FTD
D. SYSTEM/ITEM
TDP
C. CATEGORY
TM OTHER ADMNA
B. EXHIBITA. CONTRACT LINE ITEM NO.
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.
Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
Form Approved OMB No. 0704-0188
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
N/A
8. APP CODE
LT
7. DD 250 REQ
D
9. DIST STATEMENT
REQUIRED
13.DATE OF SUBSEQUENT
SUBMISSION
See Block 16
11. AS OF DATE
N/A
See Block 16
12.DATE OF FIRST
SUBMISSION
ASREQ
10. FREQUENCY
ReproReg
Final
Draft
b. COPIES
a. ADDRESSEE
14. DISTRIBUTION
09-MAY-2018
J. DATE
Meister, Jeffery
I. APPROVED BY
04-APR-2018
H. DATEG. PREPARED BY
Andrade, Richard
Block 5: SOW Paragraphs 3.6.2 Program Reviews and Conferences and 3.6.3 Program and Technical Reviews
1. BLOCK 9: THE FOLLOWING DISTRIBUTION STATEMENT SHALL BE PLACED
ON DOCUMENT TITLE PAGE AND DISC LABEL (WHERE APPLICABLE):
"DISTRIBUTION STATEMENT D. DISTRIBUTION AUTHORIZED TO THE
DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY FOR REASONS
OF CRITICAL TECHNOLOGY, DETERMINED 30 JAN 2018. OTHER REQUESTS
FOR THIS DOCUMENT SHALL BE REFERRED TO THE PROGRAM EXECUTIVE
OFFICE FOR SIMULATION, TRAINING AND INSTRUMENTATION (PEO STRI)
12211 SCIENCE DRIVE, ORLANDO, FL 32826-3224.
EXPORT CONTROL WARNING. ALL PRINTED AND ELECTRONIC TECHNICAL DATA, INCLUDING
DIGITAL TECHNICAL DOCUMENTS THAT ARE DETERMINED TO CONTAIN EXPORT-CONTROLLED
TECHNICAL DATA SHALL BE MARKED AS SHOWN BELOW.
WARNING - THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY
THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C., SEC 2751, ET SEQ.) OR THE
EXPORT ADMINISTRATION ACT OF 1979, AS AMENDED, TITLE 50, U.S.C., APP. 2401 ET
SEQ. VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE
CRIMINAL PENALTIES. DISSEMINATE IN ACCORDANCE WITH PROVISIONS
OF DOD DIRECTIVE 5230.25.
DESTRUCTION NOTICE FOR CLASSIFIED DOCUMENTS, FOLLOW THE PROCEDURES IN DOD
5220.22-M, INDUSTRIAL SECURITY MANUAL, SECTION 11 -19 OR DOD 5200.01, DOD
INFORMATION SECURITY PROGRAM. FOR UNCLASSIFIED, LIMITED DOCUMENTS, DESTROY BY
ANY METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS OR RECONSTRUCTION OF THE
DOCUMENT.
2. BLOCK 12: SHALL BE DUE 10 DAYS AFTER EACH MEETING, CONFERENCE,
OR REVIEW (EXCEPT INTEGRATED PRODUCT TEAM (IPT) MEETINGS).
3. BLOCK 13: SHALL CONTINUE THROUGHOUT THE LIFE OF THE CONTRACT.
4. THE GOVERNMENT WILL HAVE 10 CALENDAR DAYS FOR REVIEW AND
ACCEPTANCE OR REJECTION.
5. THE CONTRACTOR SHALL HAVE 5 CALENDAR DAYS TO INCORPORATE
GOVERNMENT COMMENTS.
6. BLOCK 14*: DELIVERABLES SHALL BE DELIVERED VIA ELECTRONIC MAIL
OR OPTIC DISK (CD OR DVD) BASED ON DOCUMENTATION SIZE. ALL
DOCUMENTS FOR GOVERNMENT REVIEW SHALL BE DELIVERED IN XML OR
PLJ, AND NATIVE FORMAT. AFTER GOVERNMENT ACCEPTANCE, ALL
DOCUMENTATION SHALL BE DELIVERED IN BOTH SEARCHABLE PDF AND
NATIVE EDITABLE FORMAT. NATIVE FORMAT IS DEFINED AS BEING
PRODUCED BY COTS SOFTWARE (I.E.MICROSOFT OFFICE, OPENOFFICE,
AUTOCAD, VECTORWORKS, OR OTHERS). ONE COPY EACH OF THE
REPRODUCIBLES SHALL BE DELIVERED TO THE ATTENTION OF THE
ASSISTANT PROJECT MANAGER AND THE FMS CONTRACT SPECIALIST.
DELIVERY SHALL BE MADE TO THE FOLLOWING ADDRESS: PEO STRI, ATTN:
SFAE-STRI-TRADE-FMS, ATTN: FMS ASSISTANT PROJECT MANAGER AND FMS
CONTRACT SPECIALIST, 12211 SCIENCE DRIVE, ORLANDO, FL 32826-3224.
7. DELIVERED FILE TYPE SHALL BE SEARCHABLE PDFs.
8. CONTRACTOR TEMPLATE IS ACCEPTABLE
16. REMARKS 020See Block 16*
020 15. TOTALSee continuation sheet...
18.ESTIMATED
TOTAL PRICE
9. CONTENT IS DEFINED BY DID; CONTENT TAILORED OUT AS NECESSARY AND IDENTIFIED BELOW:
a) 10.2.A.3
F. CONTRACTOR
2018-015
E. CONTRACT/PR NO.
Huey II FTD
D. SYSTEM/ITEM
TDP
C. CATEGORY
TM OTHER ADMNA
B. EXHIBITA. CONTRACT LINE ITEM NO.
CONTRACT DATA REQUIREMENTS LIST
See Block 16
5. CONTRACT REFERENCE
DI-NDTI-80603A
4. AUTHORITY (Data Acquisition Document No.)
3. SUBTITLE
TPTest Procedure
2. TITLE OF THE DATA ITEM
B001
1. DATA ITEM NO.
F. CONTRACTOR
2018-015
E. CONTRACT/PR NO.
Huey II FTD
D. SYSTEM/ITEM
TDP
C. CATEGORY
TM OTHER NDTIB
B. EXHIBITA. CONTRACT LINE ITEM NO.
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.
Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
Form Approved OMB No. 0704-0188
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
N/A
8. APP CODE
LT
7. DD 250 REQ
D
9. DIST STATEMENT
REQUIRED
13.DATE OF SUBSEQUENT
SUBMISSION
See Block 16
11. AS OF DATE
N/A
See Block 16
12.DATE OF FIRST
SUBMISSION
ONE/R
10. FREQUENCY
ReproReg
Final
Draft
b. COPIES
a. ADDRESSEE
14. DISTRIBUTION
09-MAY-2018
J. DATE
Meister, Jeffery
I. APPROVED BY
04-APR-2018
H. DATEG. PREPARED BY
Andrade, Richard
Block 5: SOW Paragraph 3.7 Integrated Testing and Inspections
1. BLOCK 9: THE FOLLOWING DISTRIBUTION STATEMENT SHALL BE PLACED
ON DOCUMENT TITLE PAGE AND DISC LABEL (WHERE APPLICABLE):
"DISTRIBUTION STATEMENT D. DISTRIBUTION AUTHORIZED TO THE
DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY FOR REASONS
OF CRITICAL TECHNOLOGY, DETERMINED 30 JAN 2018. OTHER REQUESTS
FOR THIS DOCUMENT SHALL BE REFERRED TO THE PROGRAM EXECUTIVE
OFFICE FOR SIMULATION, TRAINING AND INSTRUMENTATION (PEO STRI)
12211 SCIENCE DRIVE, ORLANDO, FL 32826-3224
EXPORT CONTROL WARNING. ALL PRINTED AND ELECTRONIC TECHNICAL DATA, INCLUDING
DIGITAL TECHNICAL DOCUMENTS THAT ARE DETERMINED TO CONTAIN EXPORT-CONTROLLED
TECHNICAL DATA SHALL BE MARKED AS SHOWN BELOW.
WARNING - THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY
THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C., SEC 2751, ET SEQ.) OR THE
EXPORT ADMINISTRATION ACT OF 1979, AS AMENDED, TITLE 50, U.S.C., APP. 2401 ET
SEQ. VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE
CRIMINAL PENALTIES. DISSEMINATE IN ACCORDANCE WITH PROVISIONS
OF DOD DIRECTIVE 5230.25.
DESTRUCTION NOTICE FOR CLASSIFIED DOCUMENTS, FOLLOW THE PROCEDURES IN DOD
5220.22-M, INDUSTRIAL SECURITY MANUAL, SECTION 11 -19 OR DOD 5200.01, DOD
INFORMATION SECURITY PROGRAM. FOR UNCLASSIFIED, LIMITED DOCUMENTS, DESTROY BY
ANY METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS OR RECONSTRUCTION OF THE
DOCUMENT.
2. BLOCK 12. THE CONTRACTOR SHALL DELIVER ONE SET OF TEST
PROCEDURES EACH FOR THE FTD, CPT, SCHEMATIC, BMC AND
ILLUSTRATION. DELIVERY IS REQUIRED 45 CALENDAR DAYS PRIOR TO EACH TEST.
3. BLOCK 13. REVISIONS DUE AS REQUIRED.
4. THE GOVERNMENT WILL HAVE 10 CALENDAR DAYS FOR REVIEW AND
ACCEPTANCE OR REJECTION OF EACH SUBMISSION.
5. THE CONTRACTOR SHALL HAVE 5 CALENDAR DAYS TO INCORPORATE
GOVERNMENT COMMENTS.
6. BLOCK 14: DELIVERABLES SHALL BE DELIVERED VIA ELECTRONIC MAIL
OR OPTIC DISK (CD OR DVD) BASED ON DOCUMENTATION SIZE. ALL
DOCUMENTS FOR GOVERNMENT REVIEW SHALL BE DELIVERED IN XML OR
PLJ, AND NATIVE FORMAT. AFTER GOVERNMENT ACCEPTANCE, ALL
DOCUMENTATION SHALL BE DELIVERED IN BOTH SEARCHABLE PDF AND
NATIVE EDITABLE FORMAT. NATIVE FORMAT IS DEFINED AS BEING
PRODUCED BY COTS SOFTWARE (I.E.MICROSOFT OFFICE, OPENOFFICE,
AUTOCAD, VECTORWORKS, OR OTHERS). ONE COPY OF EACH REPRODUCIBLE
SHALL BE DELIVERED TO THE ATTENTION OF THE ASSISTANT PROJECT
MANAGER AND THE PROJECT ENGINEER. DELIVERY SHALL BE MADE TO THE
FOLLOWING ADDRESS: PEO STRI, ATTN: SFAE-STRI-TRADE-FMS, ATTN:
FMS ASSISTANT PROJECT MANAGER AND FMS PROJECT ENGINEER, 12211
SCIENCE DRIVE, ORLANDO, FL 32826-3224.
7. DELIVERED FILE TYPE SHALL BE SEARCHABLE PDFs. FOR TESTING
PURPOSES; PAPER COPIES WILL BE PROVIDED.
8. CONTRACTOR TEMPLATE IS ACCEPTABLE
16. REMARKS 020See Block 16
020 15. TOTALSee continuation sheet...
18.ESTIMATED
TOTAL PRICE
9. CONTENT IS DEFINED BY DID.
F. CONTRACTOR
2018-015
E. CONTRACT/PR NO.
Huey II FTD
D. SYSTEM/ITEM
TDP
C. CATEGORY
TM OTHER NDTIB
B. EXHIBITA. CONTRACT LINE ITEM NO.
CONTRACT DATA REQUIREMENTS LIST
See Block 16
5. CONTRACT REFERENCE
DI-NDTI-80809B
4. AUTHORITY (Data Acquisition Document No.)
3. SUBTITLE
TIRTest/Inspection Report
2. TITLE OF THE DATA ITEM
B002
1. DATA ITEM NO.
F. CONTRACTOR
2018-015
E. CONTRACT/PR NO.
Huey II FTD
D. SYSTEM/ITEM
TDP
C. CATEGORY
TM OTHER NDTIB
B. EXHIBITA. CONTRACT LINE ITEM NO.
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.
Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
Form Approved OMB No. 0704-0188
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
N/A
8. APP CODE
LT
7. DD 250 REQ
D
9. DIST STATEMENT
REQUIRED
13.DATE OF SUBSEQUENT
SUBMISSION
See Block 16
11. AS OF DATE
N/A
See Block 16
12.DATE OF FIRST
SUBMISSION
ONE/R
10. FREQUENCY
ReproReg
Final
Draft
b. COPIES
a. ADDRESSEE
14. DISTRIBUTION
09-MAY-2018
J. DATE
Meister, Jeffery
I. APPROVED BY
04-APR-2018
H. DATEG. PREPARED BY
Andrade, Richard
Block 5: SOW Paragraphs 3.7.3 Factory Acceptance Test and 3.7.4 Site Acceptance Test
1. BLOCK 9: THE FOLLOWING DISTRIBUTION STATEMENT SHALL BE PLACED
ON DOCUMENT TITLE PAGE AND DISC LABEL (WHERE APPLICABLE):
"DISTRIBUTION STATEMENT D. DISTRIBUTION AUTHORIZED TO THE
DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY FOR REASONS
OF CRITICAL TECHNOLOGY, DETERMINED 30 JAN 2018. OTHER REQUESTS
FOR THIS DOCUMENT SHALL BE REFERRED TO THE PROGRAM EXECUTIVE
OFFICE FOR SIMULATION, TRAINING AND INSTRUMENTATION (PEO STRI)
12211 SCIENCE DRIVE, ORLANDO, FL 32826-3224
EXPORT CONTROL WARNING. ALL PRINTED AND ELECTRONIC TECHNICAL DATA, INCLUDING
DIGITAL TECHNICAL DOCUMENTS THAT ARE DETERMINED TO CONTAIN EXPORT-CONTROLLED
TECHNICAL DATA SHALL BE MARKED AS SHOWN BELOW.
WARNING - THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY
THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C., SEC 2751, ET SEQ.) OR THE
EXPORT ADMINISTRATION ACT OF 1979, AS AMENDED, TITLE 50, U.S.C., APP. 2401 ET
SEQ. VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE
CRIMINAL PENALTIES.
DISSEMINATE IN ACCORDANCE WITH PROVISIONS OF DOD DIRECTIVE 5230.25.
DESTRUCTION NOTICE FOR CLASSIFIED DOCUMENTS, FOLLOW THE PROCEDURES IN DOD
5220.22-M, INDUSTRIAL SECURITY MANUAL, SECTION 11 -19 OR DOD 5200.01, DOD
INFORMATION SECURITY PROGRAM. FOR UNCLASSIFIED, LIMITED DOCUMENTS, DESTROY BY
ANY METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS OR RECONSTRUCTION OF THE
DOCUMENT.
2. BLOCKS 12 AND 13: A TEST/INSPECTION REPORT SHALL BE SUBMITTED
FOR EACH USG TEST EVENT. EACH SUBMISSION SHALL BE DUE 30
CALENDAR DAYS AFTER COMPLETION OF EACH USG TEST. 3. BLOCK 13:
REVISIONS AS REQUIRED.
4. THE GOVERNMENT WILL HAVE 30 CALENDAR DAYS FOR REVIEW AND
ACCEPTANCE OR REJECTION.
5. THE CONTRACTOR SHALL HAVE 5 CALENDAR DAYS TO INCORPORATE
GOVERNMENT COMMENTS.
6. BLOCK 14: DELIVERABLES SHALL BE DELIVERED VIA ELECTRONIC MAIL
OR OPTIC DISK (CD OR DVD) BASED ON DOCUMENTATION SIZE. ALL
DOCUMENTS FOR GOVERNMENT REVIEW SHALL BE DELIVERED IN XML OR
PLJ, AND NATIVE FORMAT. AFTER GOVERNMENT ACCEPTANCE, ALL
DOCUMENTATION SHALL BE DELIVERED IN BOTH SEARCHABLE PDF AND
NATIVE EDITABLE FORMAT. NATIVE FORMAT IS DEFINED AS BEING
PRODUCED BY COTS SOFTWARE (I.E.MICROSOFT OFFICE, OPENOFFICE,
AUTOCAD, VECTORWORKS, OR OTHERS). ONE COPY OF EACH REPRODUCIBLE
SHALL BE DELIVERED TO THE ATTENTION OF THE ASSISTANT PROJECT
MANAGER AND THE PROJECT ENGINEER. DELIVERY SHALL BE MADE TO THE
FOLLOWING ADDRESS: PEO STRI, ATTN: SFAE-STRI-TRADE-FMS, ATTN:
FMS ASSISTANT PROJECT MANAGER AND FMS PROJECT ENGINEER, 12211
SCIENCE DRIVE, ORLANDO, FL 32826-3224.
7. DELIVERED FILE TYPE SHALL BE SEARCHABLE PDFs.
8. CONTRACTOR TEMPLATE IS ACCEPTABLE.
16. REMARKS 020See Block 16*
020 15. TOTALSee continuation sheet...
18.ESTIMATED
TOTAL PRICE
9. CONTENT IS DEFINED BY DID.
F. CONTRACTOR
2018-015
E. CONTRACT/PR NO.
Huey II FTD
D. SYSTEM/ITEM
TDP
C. CATEGORY
TM OTHER NDTIB
B. EXHIBITA. CONTRACT LINE ITEM NO.
CONTRACT DATA REQUIREMENTS LIST
SOW paragraph 3.9 Site Requirements
5. CONTRACT REFERENCE
DI-FACR-80966
4. AUTHORITY (Data Acquisition Document No.)
3. SUBTITLE
TFRTrainer Facilities Report (TFR)
2. TITLE OF THE DATA ITEM
B003
1. DATA ITEM NO.
F. CONTRACTOR
2018-015
E. CONTRACT/PR NO.
Huey II FTD
D. SYSTEM/ITEM
TDP
C. CATEGORY
TM OTHER FACRB
B. EXHIBITA. CONTRACT LINE ITEM NO.
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.
Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
Form Approved OMB No. 0704-0188
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
N/A
8. APP CODE
LT
7. DD 250 REQ
D
9. DIST STATEMENT
REQUIRED
13.DATE OF SUBSEQUENT
SUBMISSION
SEE BLOCK 16
11. AS OF DATE
n/a
SEE BLOCK 16
12.DATE OF FIRST
SUBMISSION
ONE/R
10. FREQUENCY
ReproReg
Final
Draft
b. COPIES
a. ADDRESSEE
14. DISTRIBUTION
09-MAY-2018
J. DATE
Meister, Jeffery
I. APPROVED BY
09-MAY-2018
H. DATEG. PREPARED BY
Meister, Jeffery
1. BLOCK 9: THE FOLLOWING DISTRIBUTION STATEMENT SHALL BE PLACED
ON DOCUMENT TITLE PAGE AND DISC LABEL (WHERE APPLICABLE):
"DISTRIBUTION STATEMENT D. DISTRIBUTION AUTHORIZED TO THE
DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY FOR REASONS
OF CRITICAL TECHNOLOGY, DETERMINED 30 JAN 2018. OTHER REQUESTS
FOR THIS DOCUMENT SHALL BE REFERRED TO THE PROGRAM EXECUTIVE
OFFICE FOR SIMULATION, TRAINING AND INSTRUMENTATION (PEO STRI)
12211 SCIENCE DRIVE, ORLANDO, FL 32826-3224.
EXPORT CONTROL WARNING. ALL PRINTED AND ELECTRONIC TECHNICAL DATA, INCLUDING
DIGITAL TECHNICAL DOCUMENTS THAT ARE DETERMINED TO CONTAIN EXPORT-CONTROLLED
TECHNICAL DATA SHALL BE MARKED AS SHOWN BELOW.
WARNING - THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY
THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C., SEC 2751, ET SEQ.) OR THE
EXPORT ADMINISTRATION ACT OF 1979, AS AMENDED, TITLE 50, U.S.C., APP. 2401 ET
SEQ. VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE
CRIMINAL PENALTIES.
DISSEMINATE IN ACCORDANCE WITH PROVISIONS OF DOD DIRECTIVE 5230.25.
DESTRUCTION NOTICE FOR CLASSIFIED DOCUMENTS, FOLLOW THE PROCEDURES IN DOD
5220.22-M, INDUSTRIAL SECURITY MANUAL, SECTION 11 -19 OR DOD 5200.01, DOD
INFORMATION SECURITY PROGRAM. FOR UNCLASSIFIED, LIMITED DOCUMENTS, DESTROY BY
ANY METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS OR RECONSTRUCTION OF THE
DOCUMENT.
2. BLOCKS 12 AND 13: A TFR SHALL BE SUBMITTED FOR EACH DEVICE AND
ITS LOCATION. THE TFR SHALL BE DUE 30 CALENDAR DAYS AFTER
COMPLETION OF EACH SITE VISIT.
3. BLOCK 13: REVISIONS AS REQUIRED THROUGH THE LIFE OF THE CONTRACT.
4. THE GOVERNMENT WILL HAVE 20 CALENDAR DAYS FOR REVIEW AND
ACCEPTANCE OR REJECTION OF EACH SUBMISSION.
5. THE CONTRACTOR SHALL HAVE 5 CALENDAR DAYS TO INCORPORATE
GOVERNMENT COMMENTS.
6. BLOCK 14: DELIVERABLES SHALL BE DELIVERED VIA ELECTRONIC MAIL
OR OPTIC DISK (CD OR DVD) BASED ON DOCUMENTATION SIZE. ALL
DOCUMENTS FOR GOVERNMENT REVIEW SHALL BE DELIVERED IN XML OR
PLJ, AND NATIVE FORMAT. AFTER GOVERNMENT ACCEPTANCE, ALL
DOCUMENTATION SHALL BE DELIVERED IN BOTH SEARCHABLE PDF AND
NATIVE EDITABLE FORMAT. NATIVE FORMAT IS DEFINED AS BEING
PRODUCED BY COTS SOFTWARE (I.E.MICROSOFT OFFICE, OPENOFFICE,
AUTOCAD, VECTORWORKS, OR OTHERS). ONE COPY EACH OF THE
REPRODUCIBLE SHALL BE DELIVERED TO THE ATTENTION OF THE PROJECT
LEADER AND THE PROJECT ENGINEER. DELIVERY SHALL BE MADE TO THE
FOLLOWING ADDRESS: PEO STRI, ATTN: SFAE-STRI-TRADE-FMS, ATTN:
FMS PROJECT LEADER AND FMS PROJECT ENGINEER, 12211 SCIENCE DRIVE,
ORLANDO, FL 32826-3224.
7. DELIVERED FILE TYPE SHALL BE SEARCHABLE PDFs.
8. CONTRACTOR TEMPLATE IS ACCEPTABLE
9. CONTENT IS DEFINED BY DID.
16. REMARKS 020SEE BLOCK 16
020 15. TOTAL
18.ESTIMATED
TOTAL PRICE
Page 1 of 1 PagesPREVIOUS EDITION MAY BE USED.DD FORM 1423-1, FEB 2001
SFAE-STRI-PMTRADE
SOW paragraph 3.2.3 Spares
5. CONTRACT REFERENCE
DI-SESS-81758A
4. AUTHORITY (Data Acquisition Document No.)
3. SUBTITLE
Logistics Product DataLOGISTICS PRODUCT DATA
2. TITLE OF THE DATA ITEM
C001
1. DATA ITEM NO.
F. CONTRACTOR
2018-015
E. CONTRACT/PR NO.
Huey II FTD
D. SYSTEM/ITEM
TDP
C. CATEGORY
TM OTHER SESS
B. EXHIBITA. CONTRACT LINE ITEM NO.
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.
Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
Form Approved OMB No. 0704-0188
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
A
8. APP CODE
DD
7. DD 250 REQ
D
9. DIST STATEMENT
REQUIRED
13.DATE OF SUBSEQUENT
SUBMISSION
See Block 16
11. AS OF DATE
N/A
See Block 16
12.DATE OF FIRST
SUBMISSION
2TIME
10. FREQUENCY
ReproReg
Final
Draft
b. COPIES
a. ADDRESSEE
14. DISTRIBUTION
08-MAY-2018
J. DATE
Capote, Robert
I. APPROVED BY
08-MAY-2018
H. DATEG. PREPARED BY
Cooper, Joseph
1. Block 8: Government Approval will be required prior signing DD250.
2. Block 9: Distribution Statement D. Distribution authorized to the Governments of Uganda & Kenya, Department of Defense (DoD) and U.S. DoD contractors only as of 30 Jan 2018. Other requests for this document shall be referred to the Program Executive Office for Simulation, Training and Instrumentation (PEO STRI) 12211 Science Dr. Orlando, FL 32826-3276.
EXPORT CONTROL WARNING. All printed and electronic, including digital technical documents that are determined to contain export-controlled technical data shall be marked as shown below.
WARNING - This document contains technical data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C., Sec 2751, et seq.) or the Export Administration Act of 1979 (Title 50, U.S.C., App. 2401 et seq.)
, as amended. Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25.
3. Deliverables under this contract delivery order will be as follows:
3a. Materiel Component List for all systems (MCL) 3b. Indentured Provisioning Parts List (PPL) 3c. Initial Spare Parts List 3d. Special Tools and Test Equipment List (ST&TE) 3e. Consumables List 3f. Equipment Inventory Report (EIR) 3f1. Deliverables under this contract delivery order will be separated and tabbed as follows:
3f1a. Main Operational System 3f1b. Initial Spare Parts List 3f1c. Special Tools and Test Equipment (ST&TE) List 3f1d. Consumables/Common and Bulk items List 3f1e. Report of Discrepancy (ROD) 3f1f. Soft copy Compact Disk (CD) of EIR 3f2. The following data elements are required:
3f2a. Nomenclature (complete item description) (Column -1) 3f2b. Make and model number (Column-2) 3f2c. Unique item identification number (Column-3) 3f2d. Original part number issued by manufacturer (Column-4) (If Applicable) 3f2e. Original serial number assigned to item (Column-5) (If Applicable) 3f2f. Unit of issue (Column-6) 3f2g. Unit cost (Column-7) 3f2h. Name of manufacturer(Column-8) 3f2i. Manufacturer Cage Code (Column-9) 3f2j. Manufacturer contact information, telephone # or email address (Column 10) 3f2k. Warranty number (Column-11) (If Applicable) 3f2l. Warranty expiration date, year, month and day(Column-12) (If Applicable) 3f2m. Associated Drawing Number (Column 13 - Sortable) (If Applicable) 3f3. EIR will be bound on legal size 8.5 x 14 paper in landscape orientation. Some columns may be hidden when printed. Hidden columns will be determined based on the needs of the customer.
4. Block 12: First submittal shall be due 60 calendar days prior to Factory Acceptance Test. The Government shall have 20 calendar days for review and acceptance or rejection and provide comments. The contractor shall have 20 calendar days to incorporate Government comments.
16. REMARKS 020See Block 16
020 15. TOTALSee continuation sheet...
18.ESTIMATED
TOTAL PRICE
5. Block 13 Final submittal shall be due 20 calendar days after Factory Acceptance Test. The Government shall have 15 calendar days for review and acceptance or rejection and provide comments. The contractor shall have 15 calendar days to incorporate Government comments.
6. Block 14: Deliverables shall be delivered via electronic mail or optic disk (CD or DVD) based on documentation size. All documents for Government review shall be delivered in XML or PLJ, and native format. This includes vector and raster based documents. After Government Acceptance, all documentation shall be delivered in both PDF and native editable format. Native format is defined as being produced by COTS software (i.e. Microsoft Office, OpenOffice, AutoCAD, Vectorworks, or others). Reproducible shall be delivered to PEO STRI, ATTN: SFAE-STRI-TRADE-FMS ATTN: FMS Assistant Project Manager and FMS Logistician, 12211
SCIENCE DRIVE, ORLANDO, FL 32826-3224.
A hard copy of the EIR shall be over-packed with the equipment for inventory purposes upon delivery. The hard copy will be bound on legal size 8.5 x 14 paper in landscape orientation. The Compact Disk (CD) shall contain the Equipment Inventory List in a PDF format. Some columns may be hidden when printed. Hidden columns will be determined based on the needs of the customer. The below Equipment Inventory List shall be comprehensive and distinctly separated for the purpose of a 100% inventory of delivered hardware, spares, repair parts, TTE, and CBL. The hard copy will be separated and tabbed as follows:
a. Equipment Inventory List
b. Report of Discrepancy (ROD)
c. CD in a sleeve on the back cover IAW with this deliverable
F. CONTRACTOR
2018-015
E. CONTRACT/PR NO.
Huey II FTD
D. SYSTEM/ITEM
TDP
C. CATEGORY
TM OTHER SESS
B. EXHIBITA. CONTRACT LINE ITEM NO.
CONTRACT DATA REQUIREMENTS LIST
See Block 16
5. CONTRACT REFERENCE
DI-TMSS-81816
4. AUTHORITY (Data Acquisition Document No.)
3. SUBTITLE
COTS ManualsSee Block 16
2. TITLE OF THE DATA ITEM
C002
1. DATA ITEM NO.
F. CONTRACTOR
2018-015
E. CONTRACT/PR NO.
Huey II FTD
D. SYSTEM/ITEM
TDP
C. CATEGORY
TM OTHER TMSS
B. EXHIBITA. CONTRACT LINE ITEM NO.
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.
Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
Form Approved OMB No. 0704-0188
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
A
8. APP CODE
DD
7. DD 250 REQ
D
9. DIST STATEMENT
REQUIRED
13.DATE OF SUBSEQUENT
SUBMISSION
See Block 16
11. AS OF DATE
N/A
See Block 16
12.DATE OF FIRST
SUBMISSION
1TIME
10. FREQUENCY
ReproReg
Final
Draft
b. COPIES
a. ADDRESSEE
14. DISTRIBUTION
08-MAY-2018
J. DATE
Capote, Robert
I. APPROVED BY
08-MAY-2018
H. DATEG. PREPARED BY
Cooper, Joseph
Block 2: Commercial Off-The-Shelf (COTS) Manual Supplemental Data
Block 5: SOW Paragraph 3.4 Technical Publications and 3.4.1 Commercial Manuals
1. Block 2: Commercial Off-The-Shelf (COTS) Manual Supplemental Data
2. Block 8: Government acceptance is required prior to NET.
3. Block 9: Distribution Statement D. Distribution authorized to the Governments of Uganda & Kenya, Department of Defense (DoD) and U.S. DoD contractors only as of 30 Jan 2018. Other requests for this document shall be referred to the Program Executive Office for Simulation, Training and Instrumentation (PEO STRI) 12211 Science Dr. Orlando, FL 32826-3276.
EXPORT CONTROL WARNING. All printed and electronic, including digital, technical documents that are determined to contain export-controlled technical data shall be marked as shown below.
WARNING - This document contains technical data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C., Sec 2751, et seq.) or the Export Administration Act of 1979 (Title 50, U.S.C., App. 2401 et seq.)
, as amended. Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25.
4. Block 12: Submission of COTS publications shall occur 60 calendar days prior to Factory Acceptance Test. The Government shall have 20 days to review the deliverable and accept or reject. The contractor shall have 20 days to address Government comments.
5. All COTS documentation shall be indexed, tabbed, and placed in a binder with a table of contents.
6. Block 14 : Reproducibles of the Final Government approved submission shall be delivered via electronic mail or optical disk (CD or DVD) to PEO STRI, ATTN: SFAE-STRI-TRADE-FMS ATTN: FMS Assistant Program Manager and FMS Logistician, 12211 SCIENCE DRIVE, ORLANDO, FL 32826-3224.
Format will be compatible with current version of Microsoft Office and Adobe PDF. After Government acceptance, documentation shall be delivered in Adobe searchable PDF on CD or DVD. A hard copy, placed in a binder, shall be delivered to the fielded site.
16. REMARKS 120See Block 16
120 15. TOTAL
18.ESTIMATED
TOTAL PRICE
See Block 16
5. CONTRACT REFERENCE
DI-MGMT-81804A
4. AUTHORITY (Data Acquisition Document No.)
3. SUBTITLE
IUID ReportSee Block 16
2. TITLE OF THE DATA ITEM
C003
1. DATA ITEM NO.
F. CONTRACTOR
2018-015
E. CONTRACT/PR NO.
Huey II FTD
D. SYSTEM/ITEM
TDP
C. CATEGORY
TM OTHER MGMT
B. EXHIBITA. CONTRACT LINE ITEM NO.
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.
Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
Form Approved OMB No. 0704-0188
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
A
8. APP CODE
DD
7. DD 250 REQ
D
9. DIST STATEMENT
REQUIRED
13.DATE OF SUBSEQUENT
SUBMISSION
See Block 16
11. AS OF DATE
N/A
See Block 16
12.DATE OF FIRST
SUBMISSION
1TIME
10. FREQUENCY
ReproReg
Final
Draft
b. COPIES
a. ADDRESSEE
14. DISTRIBUTION
08-MAY-2018
J. DATE
Capote, Robert
I. APPROVED BY
08-MAY-2018
H. DATEG. PREPARED BY
Cooper, Joseph
Block 2: Item Unique Identification (IUID) Marking Activity, Validation and Verification Report
Block 5: SOW Paragraph 3.4.2 Item Unique Identification (IUID)
1. Block 2: Item Unique Identification (IUID) Marking Activity, Validation and Verification Report. IUID Report is required to identify mandated IUID requirements in accordance with MIL-STD-130N w/change 1 and DID: DI-MGMT 81804A.
2. Block 9: Block 9: Distribution Statement D. Distribution authorized to the Department of Defense (DoD) and U.S. DoD contractors only as of 30 Jan 2018. Other requests for this document shall be referred to the Program Executive Office for Simulation, Training and Instrumentation (PEO STRI) 12211 Science Dr. Orlando, FL 32826-3276.
EXPORT CONTROL WARNING. All printed and electronic, including digital technical documents that are determined to contain export-controlled technical data shall be marked as shown below.
WARNING - This document contains technical data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C., Sec 2751, et seq.) or the Export Administration Act of 1979 (Title 50, U.S.C., App. 2401 et seq.)
, as amended. Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25.
3. Block 12: Submission shall be due 20 calendar days after Factory Acceptance Test. The Government will have 15 working days to accept or reject and provide comments. The Contractor shall have 10 working days to incorporate changes. Along with the CDRL submission, the contractor must electronically submit the DD250, Material Inspection and Receiving Report (MIRR), via Wide Area Workflow (WAWF).
4. Block 14: Reproducible documents (text, drawings, tables, graphic packages used to create figures, and other type documents) shall be delivered in an editable and PDF format via electronic mail to the entire U.S. Government
FMS IPT. CONTRACTOR FORMAT IS NOT ACCEPTABLE.
16. REMARKS 010See Block 16
010 15. TOTAL
18.ESTIMATED
TOTAL PRICE
See Block 16
5. CONTRACT REFERENCE
DI-ILSS-80872
4. AUTHORITY (Data Acquisition Document No.)
3. SUBTITLE
TRAINING COURSETraining Materials
2. TITLE OF THE DATA ITEM
C004
1. DATA ITEM NO.
F. CONTRACTOR
2018-015
E. CONTRACT/PR NO.
Huey II FTD
D. SYSTEM/ITEM
TDP
C. CATEGORY
TM OTHER ILSS
B. EXHIBITA. CONTRACT LINE ITEM NO.
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.
Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
Form Approved OMB No. 0704-0188
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
A
8. APP CODE
DD
7. DD 250 REQ
D
9. DIST STATEMENT
REQUIRED
13.DATE OF SUBSEQUENT
SUBMISSION
See Block 16
11. AS OF DATE
N/A
See Block 16
12.DATE OF FIRST
SUBMISSION
2TIME
10. FREQUENCY
ReproReg
Final
Draft
b. COPIES
a. ADDRESSEE
14. DISTRIBUTION
08-MAY-2018
J. DATE
Capote, Robert
I. APPROVED BY
08-MAY-2018
H. DATEG. PREPARED BY
Cooper, Joseph
Block 5: SOW Paragraphs 3.8.1 Pilot Training, 3.8.2 Operator Training, and
3.8.3 Maintainer Training
1. Block 4: Submittal shall include separate training materials for each type of equipment being delivered. Contractor shall provide one reproducible copy (Compact Disk) of all New Equipment Training (NET). Training materials shall be provided for each student attending the NET class along with both operations and maintenance manuals. Expect 6 students per class.
2. Block 8: Government approval of training materials will be required prior to NET.
3. Block 9: Distribution Statement D. Distribution authorized to the Governments of Kenya & Uganda, the U.S. Department of Defense (DoD) and U.S. DoD contractors only as of 30 Jan 2018. Other requests for this document shall be referred to the Program Executive Office for Simulation, Training and Instrumentation (PEO STRI) 12211 Science Dr. Orlando, FL 32826-3276.
EXPORT CONTROL WARNING. All printed and electronic, including digital, technical documents that are determined to contain export-controlled technical data shall be marked as shown below.
WARNING - This document contains technical data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C., Sec 2751, et seq.) or the Export Administration Act of 1979 (Title 50, U.S.C., App. 2401 et seq.)
, as amended. Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25.
4. Block 12: Initial submission shall be due 30 days prior to Factory Acceptance Test (FAT). The Government will have 20 days to accept/reject and provide comments. The contractor shall have 10 days to incorporate changes.
5. Block 13: Final submission shall be due 45 days prior to scheduled NET event. The Government will have 20 days to accept/reject and provide comments. The contractor shall have 10 days to incorporate changes.
6. Block 14: The training products shall be delivered via electronic mail or optic disk (CD or DVD) based on documentation size. All documents for Government review shall be delivered in PDF format. If the file size is too large to deliver via e-mail, an optic disk shall be delivered to PEO STRI, ATTN: SFAE-STRI-TRADE-FMS, 12211 Science Dr. Orlando, FL 32826-3276.
16. REMARKS 171See Block 16
171 15. TOTAL
18.ESTIMATED
TOTAL PRICE
File details come from the government source that posted it.