Amendment 0006
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W5J9JEANA18064
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04 EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
D-B of Camp Pratt
1. CONTRACT ID CODE PAGE OF PAGES
J 1 18
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 13-Mar-2018
16B. UNITED STATES OF AMERICA 15C. DATE SIGNED 15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer) (Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W5J9JE18R0006
X 9B. DATED (SEE ITEM 11)
28-Feb-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTA L AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
13-Mar-2018
CODE
TRANSATLANTIC AFGHANISTAN ENGINEER - TAA
DISTRICT (TAA), US ARMY CORPS OF ENGINEERS
CETAA-CT, BAGRAM AE 09354
W5J9JE 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODE CODE
EMAIL: TEL:
W5J9JE18R0006
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The following have been added by full text:
OFFEROR QUESTIONS – 5
A. A revised Price Schedule, revised Project Facilities & Approximate SM and revised Priority Schedule of Facilities attachments are incorporated into this solicitation.
B. Questions and Answers
V. The following are Offeror questions and the Government’s response to each question:
Q24: Could you please clarify if there is page limitation for this RFP?
A24: There is no page limitation on the Phase 1 Proposal.
Q25: In response to your answer for #A21 for the performance bond and payment bond, both bonds will be total 30% of the contract, which is still a lot and Afghan companies are not able to provide such enormous bond. I am kindly requesting you to reduce the max bond to $3,000,000 for both bonds, or 15% for both bonds, which will be fair. I am sure you don’t know the bank policies in Afghanistan. In overseas, the situation is totally different.
Kindly requesting you to once again re-consider this issue and share your final decision.
A25: We do understand the banking and bonding situation in Afghanistan. We have already reduced the bonding requirement from 50% for each type bond (which would have been 100% total) to 15% for each type bond (equalling 30% of the contract value). Offerors are reminded that, per FAR Part 28 regulation, the Government must have financial protections in place to protect it against financial losses and to ensure fulfillment of the contractor’s obligations under the contract. However, after consultation with our attorney, we will reduce the bonding requirement for the Payment Bond to 5%, but the Performance Bond will remain at 15%; this equates to a total bonding requirement of 20% of the contract value. This is the final decision of the Contracting Officer for this solicitation and its resultant contract.
Q26: Upon reading the answers to the Qs #21 and #23, we believe your answers to these questions are contradictory. Please let us know if the bonding requirements are 15% of the total value of the awarded contract for Performance and Payment combined or 15% for each bonding type. For example, assuming the project awarded price is $10M, Scenario 1 – If 15% for a combined of Performance and Payment Bonds is correct, as it stated in the answer to the question #23, then the total amount for the 2 bonds will be $1.5 million. Will this be equally divided between the 2 bonds with an amount of $750,000 for Performance Bond and $750,000 for the Payment Bond? Or, Scenario 2 – Using your answer to Q #21, the requirements are $1.5M for Performance Bond and an additional $1.5M for Payment Bond, then the total value of these bonds for this project will be $3M or 30% of the total. Is this correct?
A26: The bonding requirements for this project are as follows: 15% of the contract value for the Performance Bond and 5% of the contract value for the Payment Bond. This equates to 20% of the contract value for the total bonding requirement for this project.
Q27: We have signed PPQs (NAVFAC/USACE PPQ-0 forms) which were obtained from USACE officers for our previous Afghanistan projects, and considering that we will use them for our Phase 1 Proposal. But your form is different from this previous form of ours. Can we use our previous official USACE PPQ-0 forms instead of the new one that was included in this solicitation?
A27: Yes.
The following have been modified:
1. The following Table of Contents provides the Uniform Contract Format (UCF) sections within this solicitation and their corresponding title of content information.
SECTION TITLE
A Solicitation/Contract Form
B Supplies or Services and Prices/Costs
C Description/Specifications/Statement of Work
D Packaging and Marking
E Inspection and Acceptance
F Deliveries or Performance
G Contract Administration Data
H Special Contract Requirements
I Contract Clauses
J List of Documents, Exhibits & Other Attachments
K Representations, Certifications & Other
Statements of Offerors or Respondents
L Instructions, Conditions & Notices to
Offerors or Respondents
M Evaluation Factors for Award
2. PRELIMINARY SCOPE OF WORK OF THIS SOLICITATION’S DESIGN-BUILD PROJECT
REQUIREMENT – FINAL VERSION TO BE PROVIDED IN PHASE 2
This project requires the contractor to design and build new utilities infrastructure and facilities at Camp John Pratt in Mazar-E Sharif. New utilities to be provided include electrical power, communications (e.g., telephone and Internet}, potable water, waste water, and site drainage. New facilities to be constructed include barracks, latrines, laundries, dining facilities, fitness center, medical clinic, headquarters buildings, tactical operations center, logistics building, classrooms, vehicle maintenance facility, fire station, small arms storage, storage buildings, electric power generation plant with refueling station, water supply system with well house, waste water treatment plant, entry control point and perimeter fence. All facilities, systems and structures will be delivered complete and ready for occupancy and use.
Priority 1 - Force Protection
Facility Standard Design Type Quantity
1) Perimeter Fence G05
2) Entry Control Point (ECP) FP05 x2
Priority 2 – Billeting & Site Improvements
Facility Standard Design Type Quantity
1) Officers Barracks B03 x2
2) NCO Barracks B04 x4
3) Classroom CL01 x4
4) Latrine – Medium L02 x2
5) Dining Facility (DFAC) D02 x1
6) Demolition N/A
7) Clearing and Grubbing N/A
8) Site Drainage and Grading N/A
9) Water Well #1 N/A
10) Water Storage and Distribution System* N/A
11) Power Generation and Plant U01
12) Electric Distribution* N/A
13) WWTP N/A
14) Wastewater Collection System* N/A
*At a minimum, required for Priority 2 Facilities.
Priority 3 – Remaining Work
2) NCO Barracks B04 x3
3) Classroom CL01 x1
4) Small Arms Storage S03 x3
5) Headquarters Building AD04 x3
6) Tactical Operations Center (TOC) TOC x1
7) Medical Clinic MS01 x1
8) Laundry MS02 x5
9) Fitness Center MS03 x1
10) Fire Station VM01 (Modified) x1
11) Fire Station Water Supply MS14 x2
Priority 3 - Remaining Work
12) Logistics Building VM01 x1
13) Vehicle Maintenance Facility VM02 x1
14) Fuel Storage & Refueling Point VM03 x1
15) POL Storage VM06 x1
16) Motor Pool (fenced in parking area) N/A
17) Medium Office / Barracks B25 x4
18) Storage S01 x3
19) Propane Storage Sunshade (for DFAC) U13a x1
20) Ammunition Storage Point N/A
21) Well #2 N/A
22) Electrical Distribution (for Priority 3 Facilities) N/A
23) Water Distribution (for Priority 3 Facilities) N/A
24) Wastewater Collection (for Priority 3 Facilities) N/A
25) New Roads N/A
26) Existing Road Maintenance N/A
27) Aggregate Sidewalks N/A
28) Concrete Sidewalks N/A
(Revision 13 March 2018)
Standard designs for facilities and structures that make up Priority 1, 2 and 3, will be provided in the Plans and Specifications volume of the Phase 2 Solicitation. Those items above that are designated with an ‘N/A’ will need to be designed by the contractor.
Total # of Days Period of Performance (PoP) Duration to Complete Contract: 947 Calendar Days
(a) Priority 1 completion: 125 Calendar Days from Notice to Proceed (NTP)
(b) Priority 2 completion: 348 Calendar Days from NTP
(c) Priority 3 completion: can work these facilities concurrently with Priority 1 and/or Priority 2 facilities, but must be completed 947 Calendar Days from NTP
NAICS Code: 236220
Estimated Magnitude Range of Construction Price: Between $25 Million and $100 Million
3. PROCUREMENT METHODOLOGY
(a) This is a full and open, 2-phase, design-build, tradeoff source selection procurement using FAR Parts 15 and 36 proposal evaluation procedures. The following are the evaluation factors for Phases 1 and 2 of this solicitation:
Phase 1
Factor 1 – Specialized Experience Factor 2 – Construction Management Capability
Factor 3 – Past Performance
Phase 2
Factor 4 – Design Capability Factor 5 – Project Management Approach Factor 6 – Scheduling Capability Factor 7 – Key Personnel Factor 8 - Price
(b) Proposal submittal requirements are found in Section L herein.
(c) The basis of award is in Section M herein.
(d) Pursuant to FAR 36.303-1, the Government intends to advance between 5 and 8 Phase 1 offerors to Phase 2 of the solicitation.
4. ENTRY-GATE CRITERIA – As authorized in the Army Source Selection Supplement (SSS) of 28 Nov 2017, the Government will utilize entry-gate criteria and a pass/fail rating methodology to evaluate objective requirements prior to the start of evaluating the Phase 1 proposals.
The objective requirements for this solicitation are as follows:
(a) REQUIRED REGISTRATIONS AND LICENSE
Failure of an offeror to have the following at the time of Phase 1 proposal due date, will result in the offeror’s
Phase 1 proposal not being evaluated, and, thus, removed from competition:
(1) have an active, updated and completed registration in the System for Award Management (SAM) database;
(2) be determined base access eligible in the Joint Contingency Contracting System (JCCS)**; and,
(3) possess an Afghan Investment Support Agency (AISA) License or a Ministry of Commerce and Industries (MOCI) Entrepreneurial License, **Phase 1 proposals from offerors who are being vetted at the time of Phase 1 proposal submission deadline, will be evaluated. However, if there is still no decision as to whether the offeror is base access eligible at the conclusion of Phase 1 proposal evaluation, the offeror will not be considered for advnacement to Phase 2.
An offeror who would otherwise be awarded the contract, but due to an incomplete or expired registration(s) at any time up to contract award, will be deemed ineligible for the contract. Should this occur, the Government will then consider for award the next highest rated proposal with a reasonable price, who is determined responsible pursuant to the definition of ‘responsibility’ in FAR Part 9, and who possesses updated and valid registrations and is base access eligible according to JCCS.
The responsibility of maintaining current information in the following databases and organizations rests solely on the offeror:
a. System for Award Management (SAM): http://www.sam.gov/
b. Joint Contingency Contracting System (JCCS): https://www.jccs.gov/
c. Afghan Investment Support Agency (AISA) License: http://www.aisa.org.af/ or
Ministry of Commerce and Industries (MOCI) Entrepreneurial License:
http://moci.gov.af/ http://www.sam.gov/ http://www.jccs.gov/ http://www.aisa.org.af/ http://moci.gov.af/
If an offeror is a joint venture (JV), the JV entity must have a valid registration representing the JV as one (1) business, firm or entity. This is also applicable to SAM, JCCS, AISA or MOCI License. The Government will not accept separate registrations and licenses for each separate entity representing the JV.
(b) REQUIRED BONDS
For this design-build project, the Government requires the winning contractor to provide a performance bond and a payment bond, with each bond equal to 15% of the contract price. Thus, in addition to database registrations described in Paragraph 3(a) above and the offeror’s Phase 1 proposal receiving favorable ratings, another condition in order to advance to Phase 2 is the offeror’s ability to obtain the 2 required bonds as determined by the offeror’s response to the bonding question in the ‘Questionnaire for Phase 1 Offerors’ attachment. In that Questionnaire, the offeror must respond that he would be able to obtain the required bonds within 21 days after receiving contract award; otherwise, the offeror’s proposal will not advance to Phase 2.
For Phase 2, offerors must include in their Phase 2 proposal, an Irrevocable Letter of Credit (ILC) or a similar official, written commitment from an established financial institution, that attests to the offeror’s ability to obtain the required performance and payment bonds within 21 days of receiving contract award. Without an ILC or similar document in the offeror’s Phase 2 Proposal, the offeror will not be considered for contract award. FAR clause 52.228-14 explains the ILC in detail, and it is included in this solicitation in full text.
If the contractor is unable to obtain the 2 bonds 21 days after contract award, the Notice to Proceed (NTP) will not be issued, and the contract will be terminated.
5. INSTALLATION ACCESS REQUIREMENT
In accordance with CENTCOM Clause 5152.225-5916, Mandatory Eligibility for Installation Access, the Government will remove an offeror from consideration and not evaluate or complete the evaluation of his proposal if the offeror is found to be base access ineligible in the Joint Contingency Contracting System (JCCS/JCXS). The
Government reserves the right to make this determination at any time prior to contract award, including at the time of receipt of proposals and prior to the start of evaluations. The Government also reserves the right to determine an offeror ineligible for award at any time after receipt of proposals if an offeror becomes ineligible for installation access. No debriefing will be provided for those offerors removed from consideration as a result of the ir base access ineligibility, since the determination may be made in advance of the offeror’s proposal being reviewed or in advance of the Government completing its evaluation. Offeror queries or requests for reconsideration related to installation or base access eligibility must be directed to the authority responsible for base access decisions, and NOT the Contracting Officer.
6. QUESTIONS FROM OFFERORS
All offeror questions must be emailed to nikisha.w.cook@usace.army.mil and mary.j.harding@usace.army.mil.
Responses to questions will be provided via an amendment to the solicitation.
7. PHASE 1 PROPOSAL DUE DATE
(a) The Past Performance Questionnaire attachment must be completed by each of the offeror’s customer/client POCs, and each POC must email the completed form to nikisha.w.cook@usace.army.mil and mary.j.harding@usace.army.mil no later than 1500 HRS, Local Kabul Time, on 20 March 2018.
(b) Phase 1 Proposals, excluding completed Past Performance Questionnaires, must be emailed to mailto:nikisha.w.cook2@usace.army.mil mailto:mary.j.harding@usace.army.mil mailto:nikisha.w.cook@usace.army.mil mailto:mary.j.harding@usace.army.mil the following persons no later than 1500 HRS, Local Kabul Time, on 24 March 2018:
Nikisha Cook at nikisha.w.cook@usace.army.mil
Mary Harding at mary.j.harding@usace.army.mil
OFFEROR QUESTIONS - 3
A. Submittal Requirements for Factor 3 – Past Performance is changed as follows:
From Paragraph 1: The offeror shall provide a list of three (3) customer or project owner Points of Contacts (POCs) who will provide present and/or past performance information on the offeror for design/build projects undertaken for the POCs the last ten (10) years from the issuance date of this solicitation.
From Paragraph 3: The offeror may provide completed Past Performance Questionnaires for other U.S. Government contracting offices as long as the projects undertaken for the customer/client/project owner, and which the client/customer POC was providing performance information on the offeror, were for design/build projects completed in the last ten (10) years from the issuance date of this solicitation.
B. Questions and Answers
III. The following are Offeror questions and the Government’s response to each question:
Q15: May we submit a copy of our CPARS completion ratings in lieu of a new PPQ? If yes, do we need to send this separately prior to 15 March?
A15: Yes, you can submit a CPARS completion ratings in lieu of a new PPQ, by the due date and time of the Phase 1 proposal (24 March 2018).
Q16: If the PPQ only is acceptable, may we submit a PPQ completed previously for the USACE? Or, are you requiring a new PPQ, sent directly from the original contract POC?
A16: We would prefer a new PPQ, but you can submit a previous PPQ from USACE if it was completed within the last 10 years from the issuance date of this solicitation, and submit that with the Phase 1 proposal.
Q17: Please extend the deadline for PPQ and proposal submission by at least two weeks.
A17: The deadline for PPQ submittal is now changed to 1500 HRS, Local Kabul Time, on 20 March
2018.
The Phase 1 proposal deadline remains at 1500 HRS, Local Kabul Time, on 24 March 2018. The Government cannot change the deadline date for the Phase 1 proposal because the procurement schedule is aggressive and must be adhered to in order to meet customer requirements.
Q18: In Factors 1 and 2, can we use subcontractor’s experience / past performance to satisfy requirements of this proposal?
A18: Yes, you can use your experience and past performance as a subcontractor for Factors 1 and 2. For Factor 1 / Specialized Experience, make sure to state on your list of projects that you were a subcontractor for the applicable project(s). In the Factor 1 Submittal Requirement, it states that the following information (under #4) must be included on your list: “Whether the Offeror was the Prime, Subcontractor or Part of a Joint
Venture and Percentage of Work Performed by the Offeror”.
mailto:nikisha.w.cook@usace.army.mil mailto:mary.j.harding@usace.army.mil
If you meant the question for Factor 3 / Past Performance, the answer is yes, you can use your experience and past performance as a subcontractor to address this factor.
Q19: JCCS authority notified us that our documents have been submitted for base vetting / approval. We may get final decision during proposal evaluation. Would you let our proposal be in competition until we get base access decision?
A19: Yes, we will allow the evaluation of Phase 1 proposals from offerors who are being vetted at the time that Phase 1 evaluation is taking place. However, we will not advance to Phase 2 any offeror who is not actually determined base access eligible at the conclusion of Phase 1 proposal evaluation. That is the fairest process since there will be offerors who are already base access eligible prior and during Phase 1 evaluation.
OFFEROR QUESTIONS - 4
IV. The following are Offeror questions and the Government’s response to each question:
Q20: Is there an advance payment involved? Can we at least have 5-10% advance payment after we provide performance and payment bonds to the client? We are negotiating with sureties / banks and they want to know so they can evaluate / calculate their risks.
A20: Notwithstanding the fact that it is not customary to provide advance payment on USACE construction contracts and would be difficult to obtain approval for such a financial arrangement, the Government also cannot, and will not, provide advance payment because the FAR clause at 52.232-5 Payments Under Fixed- Price Construction Contracts is included in this solicitation and will be included in the resultant contract. This clause states that “the Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer.” An advance payment would mean payment when work commensurate to the amount you are requesting will not have been accomplished yet.
Additionally, one of the conditions for an offeror to receive contract award is that the offeror must be determined “responsible”, as specified in FAR 9.104-1(a), which states “to be determined responsible, a prospective contractor must have adequate financial resources to perform the contract, or the ability to obtain them.” The Government understands that, in Afghanistan, it may be difficult to obtain performance and payment bonds, but there are substantial risks to the Government, as well, should contracted work not be completed or completed inadequately. In light of the situation, the Government is permitting the use of alternative types of security, such as those listed in FAR 28.204-1 United States Bonds or Notes; FAR 28.204-2 Certified or Cashier’s Checks, Bank Drafts, Money Orders or Currency; and, FAR 28.204-3 Irrevocable Letter of Credit (ILC). **However, please note that, for this solicitation and resultant contract, the Government cannot accept currency / cash.
Q21: Answer to Question 14 allows bidders to provide 15% bonds. It is a fair deal, and we thank you for this.
Is this 15% only for performance bond, or is it for both performance and payment bonds? Do we need to provide only one bond with a value of 15% contract value, or 2 bonds of 15% each?
A21: The winning contractor must provide a Performance Bond at 15% of contract value and a Payment Bond at 15% of contract value, or any of the types of securities mentioned in Government Response #A20 above.
Q22: Is the entry to Camp Pratt from the main / current gate? It takes a couple of hours to enter this camp based on our experience in the same camp, and life support was not allowed inside the base. Is it a different situation now, or will a separate and easier access be provided to the contractor?
A22: The contractor will use the existing main ECP gate until the required contractor-constructed perimeter fence and contractor-constructed ANA external ECP have been completed. Once the perimeter fence and new ECP are constructed, the contractor shall use this ECP for site access.
Q23: The percentage of performance and payment bond is 15%. It is two different guarantees – performance guarantee and payment guarantee. Please let us know how much is performance and how much is payment guarantee in 15%. The highest performance guarantees and other guarantees in Afghanistan and other world, do not exceed from 5%.
A23: The dollar mount of the performance and payment bond is 15% of whatever the contract award amount is if you receive contract award. For Phase 2 of your proposal, you need to submit an official, written instrument (like an ILC, letter with official stamp, etc.) from an established banking or financial institution that attests to your firm being able to obtain a performance bond and a payment bond, or something similar as stated in Government’s Response #A20 above, at the amount equal to 15% of the contract award amount.
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
The following have been added by full text:
PRIORITY SCHEDULE OF FACILITIES
Priority 1 - Force Protection
15) Perimeter Fence G05
16) Entry Control Point FP05 x2
Priority 2 – Billeting & Site Improvements
29) Officers Barracks B03 x2
30) NCO Barracks B04 x4
31) Classroom CL01 x4
32) Latrine - Medium L02 x2
33) Dining Facility (DFAC) D02 x1
34) Demolition N/A
35) Clearing and Grubbing N/A
36) Site Drainage and Grading N/A
37) Water Well #1 N/A
38) Water Storage and Distribution System* N/A
39) Power Generation and Plant U01 x1
40) Electric Distribution* N/A
41) WWTP N/A
42) Wastewater Collection System* N/A
*At a minimum, required for Priority 2 Facilities.
Priority 3 - Remaining Work
2) NCO Barracks B04 x3
3) Classroom CL01 x1
4) Small Arms Storage S03 x3
5) Headquarters Building AD04 x3
6) Tactical Operations Center TOC x1
7) Medical Clinic MS01 x1
8) Laundry MS02 x5
9) Fitness Center MS03 x1
10) Fire Station VM01(Modified) x1
11) Fire Station Water Supply MS14 x2
12) Logistics Building VM01 x1
13) Vehicle Maintenance Facility VM02 x1
14) Fuel Storage & Refueling Point VM03 x1
15) POL Storage VM06 x1
16) Motor Pool (fenced in parking area) N/A
17) Medium Office / Barracks B25 x4
18) Storage S01 x3
19) Propane Storage Sunshade (for DFAC) U13a x1
20) Ammunition Storage Point N/A
21) Well #2 N/A
22) Electrical Distribution (for Priority 3 Facilities) N/A
23) Water Distribution (for Priority 3 Facilities) N/A
24) Wastewater Collection (for Priority 3 Facilities) N/A
25) New Roads N/A
26) Existing Road Maintenance N/A
27) Aggregate Sidewalks N/A
28) Concrete Sidewalks N/A
Total # of Days Period of Performance (PoP) Duration to Complete Contract: 947 Calendar Days
(a) Priority 1 completion: 125 days from Notice to Proceed (NTP)
(b) Priority 2 completion: 348 days from NTP
(c) Priority 3 completion: can work these facilities concurrently with Priority 1 and/or Priority 2 facilities, but must be completed 947 Calendar Days from NTP
The following have been modified:
PROJECT FACILITIES & APPROXIMATE SQUARE METER AREA
STANDARD DESIGN STRUCTURE OR FACILITY AREA & BUILDING TYPE
DESIGNATOR CODE
B03 Officer Barracks 761 SM and 1-Story
B04 NCO Barracks 625 SM and 1-Story
L02 Latrine Building – Medium 180 SM and 1-Story
D02 DFAC (735 person per meal) 497 SM and 1-Story
AD04 Headquarters Building 821 SM and 1-Story
CL01 200-Student Classroom (4x50) 392 SM and 1-Story
TOC Tactical Operations Center 515 SM and 1-Story
MS01 Medical Clinic 325 SM and 1-Story
MS02 Laundry 49 SM and 1-Story
MS03 Fitness Center 621 SM and 1-Story
S01 Storage 895 SM and 1-Story
S03 Small Arms Storage (SAS) 98 SM and 1-Story
VM01 Logistics Building 231 SM and 1-Story
VM03 Fuel Storage and Vehicle Refueling Point
70 SM + 173 SM and 1-Story
VM06 POL Building 25 SM and 1-Story
FP05 Guard Shack 12 SM and 1-Story
U01 Electrical Power Generation and Distribution
630 SM and 1-Story
U03 Well House 20 SM and 1-Story
VM02 Vehicle Maintenance Facility 180 SM and 1-Story
CORPORATE CERTIFICATE / AUTHORITY TO BIND PARTNERSHIP
SOLICITATION NO. W5J9JE-18-R-0006 DESIGN/BUILD OF CAMP PRATT
A. CORPORATE CERTIFICATE
If a corporation submits a proposal in response to Solicitation Number W5J9JE-18-R006, the Corporate Certificate below must be completed and included in the offeror’s Phase 1
Proposal. If the proposal is submitted by a partnership, the Authority to Bind Partnership at Paragraph B below must be completed, and a copy of the Partnership Agreement must be included with the Phase 1 Proposal.
If the proposal is submitted by a Joint Venture, the Corporate Certificate below must be completed by each member of the Joint Venture , and a copy of the Joint Venture
Agreement must be included with the proposal.
CORPORATE CERTIFICATE
I, _____________________ (Name), certify that I am the _________________________
(Position Title) of the Corporation named as offeror/contractor herein, and that I, _____________________ (Name), who signed this proposal/contract on behalf of the offeror/contractor, is the _______________________________ (Position Title) of our corporation. I also certify that said proposal/contract is duly signed for, and on behalf of said corporation, by authority of its governing body and within the scope of its governing body and within the scope of its corporate powers.
__________________________________________ (Corporate Seal)
______________________________________ (Signature)
______________________________________ (Date of Certificate)
B. AUTHORITY TO BIND PARTNERSHIP
This is to certify that the names and signatures of all partners of the offeror submitting a proposal in response to Solicitation Number W5J9JE-18-R-0006, are listed below and that the person signing the proposal has authority to actually bind the partnership pursuant to its partnership agreement. The offeror may add additional names and signatures below, as necessary. Each of the named partners individually has full authority to enter into and execute contractual instruments on behalf of said partnership, with the United States of America, except as follows: (state “None” or describe limitations, if any).
This authority shall remain in full force and effect until such time as the revocation of authority by any cause whatsoever, has been furnished in writing to, and acknowledged by, the Contracting Officer.
(Name of Partner Representative) (Signature of Partner Representative)
(Name of Partner Representative) (Signature of Partner Representative)
__________________________________ (Date of Certificate)
QUESTIONNAIRE FOR ALL PHASE 1 OFFERORS
WRITE N/A IF IT IS NOT APPLICABLE TO YOUR FIRM.
(THIS FORM MUST BE INCLUDED IN THE OFFEROR’S
PHASE 1 PROPOSAL)
NAME OF OFFEROR___________________________________________________________
IF JOINT VENTURE, NAMES OF BOTH COMPANIES_______________________________
FULL NAME OF CONTRACT NEGOTIATOR(s) FOR YOUR FIRM
BUSINESS ADDRESS__________________________________________________________
CITY/STATE/ZIP CODE_________________________________________________________
PHONE NUMBERS_____________________________________________________________
EMAIL ADDRESSES___________________________________________________________
JCCS I.D. NUMBER____________________________________________________________
AISA CERTIFICATE OR MoCI LICENSE #_________________________________________
CAGE OR NCAGE CODE_______________________________________________________
DUNS NUMBER_______________________________________________________________
TAX I.D. NUMBER_____________________________________________________________
PRIMARY NAICS CODES_______________________________________________________
(1) IS YOUR BUSINESS PROFILE INFORMATION IN SAM.GOV UPDATED AND
CURRENT? ___________YES ___________NO
(2) NUMBER OF YEARS YOUR COMPANY HAS BEEN IN BUSINESS________________
(3) IN THE PAST FIVE YEARS, THE NUMBER OF DESIGN-BUILD CONSTRUCTION
PROJECTS YOUR COMPANY HAS COMPLETED
AS A PRIME CONTRACTOR ___________ AS A SUBCONTRACTOR___________
(4) WILL YOU BE ABLE TO INCLUDE IN YOUR PHASE 2 PROPOSAL, AN
IRREVOCABLE LETTER OF CREDIT (ILC) OR SIMILAR OFFICIAL WRITTEN
COMMITMENT BY A FINANCIAL INSTITUTION, THAT WILL ATTEST TO YOUR
ABILITY AS A BUSINESS TO OBTAIN A PERFORMANCE BOND AND A PAYMENT
BOND FOR THE RESULTANT CONTRACT? ____________YES ____________NO
(SEE FAR CLAUSE 52.228-14 FOR AN EXPLANATION OF AN ILC.)
(5) WITHIN 15 DAYS OF CONTRACT AWARD, WILL YOUR FIRM BE ABLE TO
OBTAIN A PERFORMANCE BOND AND A PAYMENT BOND THAT AMOUNTS TO 50%
OF THE CONTRACT PRICE? ____________ YES ____________ NO
PRINTED NAME, TITLE AND SIGNATURE OF COMPANY REPRESENTATIVE
COMPLETING THIS FORM
DATE THIS QUESTIONNAIRE WAS COMPLETED_________________________________
PRICE SCHEDULE
ANA-18-064 Camp John Pratt
Mazar-e-Sharif, Balkh, Afghanistan
Item DESCRIPTION Quantity Unit Unit Price Extended Amount
BASE LINE ITEMS
0001 Mobilization 1 JOB
0002 Security 1 JOB
0003 Survey 1 JOB
Architectural and Engineering Design
1 JOB
0005 As-Built Drawings 1 JOB
0006 Demolition 1 JOB
0007 Clearing and Grubbing 1 JOB
0008 Site Grading and drainage 1 JOB
0009 Existing Road Maintenance 1 JOB
0010 New Roads 1 JOB
0011 Concrete Sidewalks 1 JOB
0012 Aggregate Sidewalks 1 JOB
0013 Water Wells 2 EA
Water Storage and Distribution System
1 JOB
Wastewater Treatment Plant
(WWTP)
1 JOB
0016 WWTP Control Building 1 JOB
Wastewater Collection
System
1 JOB
0018 Power Generation and Plant 1 JOB
0019 Electrical Distribution System 1 JOB
0020 Perimeter Fence 1 JOB
0021 Entry Control Point (ECP) 2 EA
0022 B03-Officers Barracks 4 EA
0023 B04-NCO Barracks 7 EA
CL01-Student Classroom Building
5 EA
0025 L02-Latrine 2 EA
0026 MS02-Laundry Building 5 EA
0027 S03-Small Arms Storage 3 EA
0028 D02-DFAC 1 JOB
0029 MS01-Medical Clinic 1 JOB
0030 AD04-Headquarters Building 3 EA
Tactical Operations Center
(TOC)
1 JOB
0032 B25a-Barracks-Medium 4 EA
0033 MS03-Fitness Center 1 JOB
0034 S01-Storage 3 EA
0035 Motor Pool 1 JOB
VM03-Fuel Storage and Vehicle Refueling Point
1 JOB
VM02-Vehicle Maintenance Facility
1 JOB
0038 VM06-POL Storage 1 JOB
0039 VM01-Logistics Building 1 JOB
0040 Fire Station 1 JOB
MS14-Fire Station Water Supply System
1 JOB
0042 Ammo Supply Point (ASP) 1 JOB
0043 Demobilization 1 JOB
BASE ITEMS TOTAL:
OPTION LINE ITEMS
0044 Option FFE Package 1 1 JOB
0045 Option FFE Package 2 1 JOB
OPTION ITEMS TOTAL:
BASE + OPTION ITEMS TOTAL:
NOTE 1: Award will be made as a whole (meaning all line items) to only one (1) offeror.
NOTE 2: Offerors shall furnish unit prices for each item listed in the above Schedule. If the offeror fails to insert a unit price in the appropriate blank for any of the line items above, but furnishes an extended total, the Government shall deem the unit price to be the quotient obtained by dividing the extended amount for that line item by the quantity. IF AN OFFEROR OMITS
BOTH THE UNIT PRICE AND THE EXTENDED TOTAL FOR ANY ITEM, ITS OVERALL OFFER
SHALL BE DECLARED INELIGIBLE FOR AWARD.
NOTE 3: Any offer may be rejected if the Contracting Officer determines in writing that it is unreasonable as to price. Unreasonableness of price includes not only the total price of the price proposal, but also the extended price for individual line items.
NOTE 4: The Option Line Items may be exercised at time of contract award or at any time after award, but no later than 270 days from the issuance of the Notice to Proceed (NTP).
NOTE 5: The unit “JOB” as used in this Price Schedule is synonymous with the term “Lump Sum.”
NOTE 6: The offeror’s Cost/Price Breakdown Spreadsheet shall contain costs, rates and data that align with, and support, the unit and extended prices shown above in the offeror’s Price Schedule.
NOTE 7: This Price Schedule is for information purposes only during Phase 1. The final version will be provided in the Phase 2 solicitation. ** Be advised the Government may add additional line items to the final version of this Price Schedule.
LIST OF SOLICITATON ATTACHMENTS
1. Price Schedule (with Base and Option Item CLINs) - Revised 13 March 2018 – final version to be provided in Phase 2 of the solicitation
2. Questionnaire For Phase 1 Offerors
3. Past Performance Questionnaire (to be provided by the offeror to 3 different client/customers)
4. Corporate Certificate / Authority to Bind Partnership Form
5. Design-Build Project Specifications and Drawings – April 2018 (will be included in
Phase 2 of the solicitation)
6. Questionnaire For Phase 2 Offerors
7. Project Facilities and Approximate Square Meter Area - Revised 13 March 2018
8. Priority Schedule of Facilities – Revised 13 March 2018
(End of Summary of Changes)