PRIORITY OF FACILITIES
Priority 1 - Force Protection:
Facility Standard Design Type Quantity
1) Perimeter Fence G05
2) Entry Control Point FP05 x2
Priority 2 – Billeting & Site Improvements:
1) Officers Barracks B03 x2
2) NCO Barracks B04 x4
3) Classroom CL01 x4
4) Latrine - Medium L02 x2
5) Dining Facility (DFAC) D02 x1
6) Demolition N/A
7) Clearing and Grubbing N/A
8) Site Drainage and Grading N/A
9) Water Well #1 N/A
10) Water Storage and Distribution System* N/A
11) Power Generation and Plant U01 x1
12) Electric Distribution* N/A
13) WWTP N/A
14) Wastewater Collection System* N/A
*At a minimum, required for Priority 2 Facilities.
Priority 3 - Remaining Work:
1) Officers Barracks B03 x2
2) NCO Barracks B04 x3
3) Classroom CL01 x1
4) Small Arms Storage S03 x3
5) Headquarters Building AD04 x3
6) Tactical Operations Center TOC x1
7) Medical Clinic MS01 x1
8) Laundry MS02 x5
9) Fitness Center MS03 x1
10) Fire Station VM01(Modified) x1
11) Fire Station Water Supply MS14 x2
12) Logistics Building VM01 x1
13) Vehicle Maintenance Facility VM02 x1
14) Fuel Storage & Refueling Point VM03 x1
15) POL Storage VM06 x1
16) Motor Pool (fenced in parking area) N/A
17) Medium Office / Barracks B25 x4
18) Storage S01 x3
19) Propane Storage Sunshade (for DFAC) U13a x1
20) Ammunition Storage Point N/A
21) Well #2 N/A
22) Electrical Distribution (for Priority 3 Facilities) N/A
23) Water Distribution (for Priority 3 Facilities) N/A
24) Wastewater Collection (for Priority 3 Facilities) N/A
25) New Roads N/A
26) Existing Road Maintenance N/A
27) Aggregate Sidewalks N/A
28) Concrete Sidewalks N/A
Total # of Days Period of Performance (PoP) Duration to Complete Contract: 947 Calendar Days
(a) Priority 1 completion: 125 days from Notice to Proceed (NTP)
(b) Priority 2 completion: 348 days from NTP
(c) Priority 3 completion: can work these facilities concurrently with Priority 1 and/or Priority 2 facilities, but must be completed 947 Calendar Days from NTP
(Revision 13 March 2018)