PRIORITY OF FACILITIES

Priority 1 - Force Protection:

Facility Standard Design Type Quantity

1) Perimeter Fence G05

2) Entry Control Point FP05 x2

Priority 2 – Billeting & Site Improvements:

1) Officers Barracks B03 x2

2) NCO Barracks B04 x4

3) Classroom CL01 x4

4) Latrine - Medium L02 x2

5) Dining Facility (DFAC) D02 x1

6) Demolition N/A

7) Clearing and Grubbing N/A

8) Site Drainage and Grading N/A

9) Water Well #1 N/A

10) Water Storage and Distribution System* N/A

11) Power Generation and Plant U01 x1

12) Electric Distribution* N/A

13) WWTP N/A

14) Wastewater Collection System* N/A

*At a minimum, required for Priority 2 Facilities.

Priority 3 - Remaining Work:

1) Officers Barracks B03 x2

2) NCO Barracks B04 x3

3) Classroom CL01 x1

4) Small Arms Storage S03 x3

5) Headquarters Building AD04 x3

6) Tactical Operations Center TOC x1

7) Medical Clinic MS01 x1

8) Laundry MS02 x5

9) Fitness Center MS03 x1

10) Fire Station VM01(Modified) x1

11) Fire Station Water Supply MS14 x2

12) Logistics Building VM01 x1

13) Vehicle Maintenance Facility VM02 x1

14) Fuel Storage & Refueling Point VM03 x1

15) POL Storage VM06 x1

16) Motor Pool (fenced in parking area) N/A

17) Medium Office / Barracks B25 x4

18) Storage S01 x3

19) Propane Storage Sunshade (for DFAC) U13a x1

20) Ammunition Storage Point N/A

21) Well #2 N/A

22) Electrical Distribution (for Priority 3 Facilities) N/A

23) Water Distribution (for Priority 3 Facilities) N/A

24) Wastewater Collection (for Priority 3 Facilities) N/A

25) New Roads N/A

26) Existing Road Maintenance N/A

27) Aggregate Sidewalks N/A

28) Concrete Sidewalks N/A

Total # of Days Period of Performance (PoP) Duration to Complete Contract: 947 Calendar Days

(a) Priority 1 completion: 125 days from Notice to Proceed (NTP)

(b) Priority 2 completion: 348 days from NTP

(c) Priority 3 completion: can work these facilities concurrently with Priority 1 and/or Priority 2 facilities, but must be completed 947 Calendar Days from NTP

(Revision 13 March 2018)