DEPARTMENT OF THE ARMY
UNITED STATES ARMY GARRISON ITALY - DARBY MILITARY COMMUNITY
PUBLIC WORKS OFFICE
APO AE 09613
Project
CD1 00197-8P
Replace kitchen hood
BLDG 726
Camp Darby AREA
TECHNICAL SPECIFICATIONS
Consisting of 80 pages
Prepared by: ________________________________ _________________
GIANLUCA LUCETTI, P.E.
Chief, Engineering Services
Date
Approved by: ________________________________ _________________
JACK P. SMITHBACK
Public Works Manager
Date
W58D2M-21-Q-0001 Attachment 2
INDEX
SECTION Ia - GENERAL PROVISIONS
SECTION IIa - DESCRIPTION OF WORK
SECTION IIIa - DEMOLITION AND REMOVAL
SECTION IIIb - EXCAVATION AND BACKFILLING
SECTION IIId - EXTERIOR DRAINAGE SYSTEM
SECTION VIId - WALLS PAINTING
SECTION VIIe - EXTERIOR INSULATION AND PLASTIC LINING
SECTION VIIIa - REPAIR OF THE ROOF MEMBRANE
SECTION VIIIc - ROOF MEMBRANE MATERIALS
SECTION Xb - FALSE CEILING
SECTION XIIa - GENERAL REQUIREMENTS MECHANICAL SYSTEMS
SECTION XIIb - MECHANICAL SYSTEMS REMOVALS
SECTION XIIc - PLUMBING SYSTEMS
SECTION XIId - DRAINAGE SYSTEM AND SANITARY VENTILATION
SECTION XIIg - AIR CONDITIONING SYSTEM
SECTION XIIh - THERMAL INSULATION FOR MECHANICAL SYSTEMS
SECTION XIIi- FIRE-EXTINGUISHING SYSTEM OF THE HOOD
SECTION XIIIa - ELECTRICAL SYSTEMS
SECTION XIIIc - FIRE DETECTION AND ALARM SYSTEMS
SECTION Ia - GENERAL PROVISIONS
1a-01 WORK PHASING.
a. Work Schedule.
Whenever the nature of the contract and the work location are such that the work is to be performed in an area assigned to activities and services that cannot be interrupted, work shall be scheduled with concurrence of COR in such a manner as to cause the least possible inconvenience to the normal operations of mentioned activities and services. Contractor shall submit his proposed work schedule to the COR at the time of the pre-construction conference. Work start shall be contingent upon schedule approval.
b. Utilities Cut-Offs.
As a rule, cut-off of power and other utilities (water, sewage, heating system, etc.) is not allowed.
All temporary connections necessary to insure continuous power distribution shall be provided. If cut-offs are necessary, they shall not exceed the period of time strictly needed to make the temporary connections. Cut-off shall be scheduled with the COR not less than 15 days ahead of time.
c. Alarm, Telephone and Televisions Systems.
Deenergizing of alarm, telephone and television systems is strictly prohibited. Should these systems, which may not appear on the drawing interfere with the contract work, they shall be temporarily diverted and fed by means of temporary connections to be adequately protected.
Written approval must be obtained from COR prior to doing any temporary work.
d. System Reactivating.
At the completion of the work, all existing systems, including water, electrical and heating systems, shall be reactivated and placed in their original locations.
e. Temporary Protections.
Floors, carpets, and equipment that cannot be removed shall be adequately protected by temporary tarpaulins to be furnished and installed at no cost to the US Government. In addition, temporary protections shall be furnished and installed in some particular areas so as to allow performance of activities that cannot be interrupted or transferred. Also, the Contractor shall be responsible for removing, protecting, and reinstalling all furniture, shelves and furnishings that may interfere with the work course. A wrong or no evaluation of all requirements specified above does not constitute grounds for a request for additional compensation.
1a-02 JOBSITE CLEAN UP AND DUST CONTROL.
The contractor shall have sufficient trash/waste bins on site, and shall clean the worksite so that all discarded materials, debris and trash are placed in these bins at the end of each workday, and not left or allowed to accumulate anywhere else on the jobsite. These waste bins shall not be allowed to overflow with debris, and shall be emptied as soon as they become full. Haul roads shall be watered sufficiently to prevent excessive dust. The work area shall be swept regularly to prevent accumulation of debris. Equipment, construction materials and excavated soil shall be stored in a safe and orderly manner on the jobsite, in accordance with the contractor's approved area use plan.
1a-03 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT.
The contractor is considered the waste generator of all salvage, re-usable, re-cyclable and disposable materials derived from the demolition and removal works included in this contract and shall handle these materials as hereinafter indicated.
a. Salvage Material.
All salvage end items that the COR will have considered in good operating conditions shall be disassembled without damage, cleared of all dirt and scaling and then transported to the DPW Warehouse, Building 5156, Depot, where they shall be handled over undamaged.
b. Re-usable Material.
End items removed during contract accomplishment which cannot be re-utilized in future construction but which still have a commercial value shall be delivered to the DRMO, through DD Form 1348-1a. This material includes, but it is not limited to, canvas, textile consisting of scrap clothing, scrap aluminum including doors, windows and frames, copper, brass, bronze, and stainless steel, cables, electric motors, light and heavy metals in different sizes and thicknesses that the DRMO contractor can handle (3-4 m long), electrical and electronic equipment, and kitchen appliances. All the above material must be free of hazardous property and need to be segregated. The scraps generated in the Supply & Maintenance Area shall be transported to the DRMO yard only on Monday and Tuesday from 08:00 am to 15:00 pm by appointment through the COR. The scraps generated from other installations must be kept in place. DRMO will arrange the removal. However, the contractor shall request a pre-inspection of the material by DRMO through the COR.
c. Recyclable Material.
All construction and demolition recyclable waste material shall be delivered to authorized treatment facilities by the contractor.
d. Special Waste.
All special waste, either hazardous or not hazardous, shall be delivered by the contractor to authorized disposal facilities.
e. Waste Storage.
Construction and demolition waste shall be stored in waste specific containers provided by the contractor. Containers will be in good conditions, free from severe rusting, bulging, or structural defects. Containers shall be placed in area identified by COR. Containers shall be removed once full or on COR’s decision.
f. Certificates and Authorizations.
Recyclable Materials.
As regards to recyclable materials, the Contractor shall submit copy of the authorization of the treatment facility which they are delivered to and will certify that waste have been removed in compliance with applicable law requirements.
Disposable Materials.
As regards to material delivery to disposal facilities, the contractor will provide the COR and DPW Environmental Office with copies of the following documents:
Authorization to transport construction and demolition waste;
Authorization of the landfill;
4th copy of Formulario di Identificazione del Rifiuto.
Waste Manifest.
All transported waste will be accompanied by the Formulario di Identificazione del Rifiuto (waste manifest) to ensure a complete audit trail from point of origin to ultimate disposal. The waste manifest must be completed in quadruplet, all dated and signed by the waste generator and countersigned by the transporter. The first copy of the manifest will remain with the waste generator; of the remaining three copies, (countersigned and dated by the receiver), the second copy will remain with the transporter, the third copy will remain with the receiver, and the fourth copy must be returned by the transporter to the waste generator within 3 months of delivery of the waste to the disposal/treatment facility.
g. Costs.
All operations included in this paragraph shall be carried out by the contractor with no additional cost to the US Government.
1a-04 AUTHORIZATION FOR INSTALLATION OF MATERIAL AND EQUIPMENT.
Before installing any material or equipment mentioned in the specifications, approval shall be obtained from the COR. Contractor shall submit material samples, shop drawings, manufacturer's literature, etc., to the COR 10 days prior to installation and shall proceed with installation only after receiving written approval from the COR. All material installed without COR's approval shall be removed.
1a-05 ISPESL AND CEI STANDARDS.
All work described in these specifications shall be accomplished in strict compliance with the ISPESL (Superior Institute of Prevention and Assurance of Work) and CEI (Italian Electrotechnical Committee) standards. In particular, if the work under contract, such as roof repairs, building painting, etc., may cause Contractor's personnel or other individuals to come in contact with non insulated electric lines, these shall be temporarily protected by use of appropriate spiral plastic tubes available on the market.
1a-06 CONTRACTING OFFICER'S REPRESENTATIVE TITLE ABBREVIATION.
The terms COR and "Direzione dei Lavori" used in the Italian version of these specifications are equivalent to the American term "Contracting Officer's Representative," which in the English version is indicated by the letters COR.
1a-07 DIGGING PERMIT.
The Contractor shall obtain a digging permit for all work areas affected by this contract (to insure that all the as-built information for underground services is received). This permit and related drawings must be received by the Contractor prior to starting any work. After receipt of the digging permit, the Contractor shall immediately notify, in writing the Contracting Officer of the permit receipt. The Contractor will be held responsible for any damages caused to existing services, as indicated on the digging permit and related drawings, and will repair such damages at his own expense. In any case before excavating, Contractor shall always perform a survey with an Underground Cable and Pipe Locator.
1a-08 ASBESTOS.
No handling of asbestos containing material is included in this project. Use of asbestos containing materials is forbidden.
1a-09 PARTICULAR REQUIREMENT FOR WORK IN HEATING PLANTS.
When the contract requires the work to be performed inside heating plants, the contractor shall provide a new cylinder in the door lock and shall deliver two keys of the new cylinder and the removed cylinder to the personnel in charge of the maintenance. At the work end the contractor shall restore the lock to the original conditions and the temporary cylinder will remain his own property.
1a-10 ANTI-TERRORISM TRAINING.
The Contractor shall comply with the following security requirements:
a. AT Level I Training.
All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR within 10 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website: httQ://jko.jten.mil.
b. OPSEC Training.
According to AR 530-1, new contractor employees must complete Level I OPSEC training within 30 calendar days after they report for duty. All contractor employees must complete annual OPSEC awareness training.
c. Access and general protection/security policy and procedures.
Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
d. iWATCH Training.
The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO).This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 40 calendar days after contract award.
1a-11 ENVIRONMENTAL POLICY.
Contractors and their personnel are required to be aware of, and comply with, the USAG Italy Environmental policy and legal and other requirements when performing work at an installation.
The Department of Defense (DoD) is committed to an Integrated Solid Waste Management (ISWM) approach that effectively manages solid waste generation, reduction, diversion, and disposal while maintaining compliance with Federal and DoD requirements.
The contractor will provide the following information semi-annually to be used by the Government to address environmental performance according to the USAG Italy goals. Please note that the amounts reported are those used/generated by the contractor regardless of source (private purchase or government furnished). Reports for January – June will be submitted by 15 July and reports for July-December will be submitted by 15 January each year.
Media Report Element #1 Report Element #2
Non-Hazardous Solid Waste
Total Waste Generated (Kg)
Amount of Waste Diverted from Landfill (Kg)
Construction Debris/Demolition Materials
Total Waste Generated (Kg)
Amount of Waste Diverted from Landfill (Kg)
Compostable/Organic Material
Total Waste Generated (Kg)
Amount of Waste Diverted from Landfill (Kg)
Hazardous Materials Total Used (Kg) Hazardous Waste Total Generated (Kg) Total Recycled (Kg) Energy Consumption – Electricity
Total Energy Consumed (MBtu)
Energy Consumption – Fuel
Total Fuel Consumed (L)
Renewable/Alternative Energy
Total Consumed
(MW)
Facility Construction/Renovation
Number of Buildings LEED Certified Silver or Higher
SqFt of buildings LEED Certified
SECTION IIa - DESCRIPTION OF WORK
2a-01 STATEMENT OF WORK. Contractor shall furnish all plants, labor, equipment, material and transportation necessary for the accomplishment of the work described in these specifications and shown on drawings , both of which are an integral and binding part of the contract.
2a-02 DESCRIPTION OF THE WORK.
Work included in this project will consist of replace the kitchen hood and its fire extinguishing system and upgrade the make-up air system
2a-03 SAFETY DURING CONSTRUCTION.
The project is performed assuming the possible presence of more than one firm, also not at the same time, on the work place, as per paragraphs 3 and 4 of art. 90 of Legislative Decree 81/2008. A preliminary “Piano di Sicurezza e Coordinamento” (safety and coordination plan) is included in the contract documentation. The final “Piano di Sicurezza e Coordinamento” (safety and coordination plan) shall be prepared by the “Coordinatore per la Sicurezza in Fase di Progettazione” (safety coordinator during design) after the approval of the final project. The Contractor shall provide his/her own “Piano Operativo di Sicurezza” (operational safety plan) and comply with the mentioned Law in all applicable parts.
2a-04 EMERGENCY SITUATIONS. Contractor will maintain the following documentation available and usable at the work site, to be provided by the COR:
- A copy of the Camp Darby Emergency Plan, to which contractor will refer in case of the emergency conditions indicated in the plan itself.
- Base Grid Coordinates layout, with the work site highlighted.
- List of emergency telephone numbers.
2a-05 SUBMISSION OF FINAL DESIGN.
The final design of the entire project shall be a contractor’s responsibility; he/she shall avail himself/herself of registered professional engineers/architects/technicians, as required by Italian regulations. No construction work shall begin until the final design is approved. Design shall be carried out in conformity of both Italian and US Codes requirements. When there is a discrepancy between the two, the designer shall follow the most stringent directives. The design shall be complete with drawings, calculations, layouts, graphics, final report, and everything else for compliance with requirements of applicable laws. In particular for electrical systems, Decree n. 37 of 22 January 2008, “Regolamento concernente l’attuazione dell’articolo 11(regulation for the implementation of art. 11) quaterdecies, para. 13, letter a) of law n. 248 of 2 December 2005, pertaining to the reorganization of the norms on the installation of systems inside buildings, and norms CEI 0-2 shall apply. The design shall be performed in accordance with the directions provided in these specifications and on the contract preliminary drawings; these are to be considered as indicative, but all requirements contained in them shall be incorporated in the design. Included in the design are all additions, modifications, and supplements to contract drawings as necessary for a complete and correct installation of all the required items. The design shall consist of the provision of drawings in standard format ISO 216 A1 and of the necessary reports and calculations, all signed and stamped by enrolled professional engineers. Once completed, all documents shall be reviewed by the Engineering Services Branch of the DPW. This office will notify the acceptance of the project or will provide the list of the necessary integrations/modifications through the Contracting Officer. The final version of the drawings shall be provided, in addition to the signed copy on reproducible material (polyester), also on computer disks by program AutoCAD 14 or by subsequent or compatible versions, and shall be complete with a signed certification of compliance to the Italian law.
2a-06 FIRE PREVENTION CONTROL.
Deliberate omissing.
2a-07 PROJECT IDENTIFICATION SIGN.
The contractor shall supply and install a sign identifying the project. The sign shall be of high-resistant plywood for outdoor installation, white painted. The dimensions shall be 1200x2400x12
mm. The letters of the wording shall be uppercase, black color, 5 cm high, except the letters of the project title which shall be 10 cm.
The sign shall be fixed to a structure made of any lasting material in compliance with all safety requirements. The sign shall be well visible, with the lower side at 1.2 m from ground level.
SECTION IIIa - DEMOLITION AND REMOVAL
3a-01 GENERAL.
Breakups of predetermined dimensions and partial or total demolition of masonry and concrete surfaces, floor, etc., must be performed in a workmanlike manner, by taking the necessary precautions or by shoring the surfaces in order to avoid damages to the structures to be left in place, accidents, inconveniences or interference. Waste material shall not be thrown down, but rather, it shall be conveyed or guided downward, after wetting it to prevent raising dust. During demolition or removal work, the Contractor shall adopt every measure suitable to avoid deterioration of the items which may be reinstalled, or which, in the opinion of the COR, may be used at a later date.
These items shall be cleaned, guarded, hauled and set neatly in the storage areas indicated by the COR. The demolition work shall be limited to the work, or to its parts, and to the dimensions specified. Reconstruction of structures demolished over and above the quantities indicated, as well as rehabilitation of work damaged as a result of lack or omission of precautions or shoring, shall be performed by the Contractor. All waste material resulting from demolition and removal shall be handled by the contractor in accordance with para. 1a-02 of these specifications.
SECTION IIIb - EXCAVATION AND BACKFILLING
3b-01 EXCAVATION.
a. General.
During excavation, material suitable for backfilling shall be piled at a sufficient distance from the banks of the excavation to avoid backslides. All earthy material in excess or unsuitable for backfilling shall be delivered to the location indicated by the COR and within 10 km from work site.
This does not apply to debris and rubble of all types, from which excavation material shall be rid of;
these shall be disposed of at a dump, as prescribed at paragraph 1a-02. In case excavation is performed in presence of water and water level is below 20 cm height, the contractor shall remove water at his expense using the means he deems suitable. If water reaches higher levels, removal shall still be at contractor's expense only if the possible presence of groundwater is indicated on the drawings or in these specifications, and only to the extent indicated. In addition, the contractor shall prevent the access of water deriving from outside to the excavation site: in case water accumulates in excavated area, removal will be at contractor's expense. Struts and shoring shall be placed as necessary for the protection of the work and for the safety of personnel. Adequate precautions shall be taken for the protection of existing underground pipelines or electrical cables. Before any excavation is started, plans showing the approximate location of underground utility lines shall be furnished to the Contractor, upon his request. The area of excavation shall be delimited by trestles, gangplanks, and warning signs visible during night and day, to prevent injuries to persons, as prescribed by the ISPESL standards.
b. Trenches.
Trenches shall be of the necessary width for the proper laying of the pipes and electric cables, and the banks shall be as nearly vertical as practicable. The bottom shall be accurately graded so as to provide bearing for the pipe on firm soil. The clear space between the pipe and the trenches wall shall not exceed 8" (20 cm.) on either side of the pipe. Further excavation will be required for housing and sealing of pipe joints. In proximity of buildings, existing underground utility lines, and wherever specifically requested in other sections of these specifications or on drawing notes, trenches shall be excavated manually.
c. Excavation for Foundation and Appurtenances.
Excavation for manholes and similar structures shall be of sufficient dimensions as to leave a 12 inches (30 cm.) free space between their outer surfaces and the embankment or timber which may be used to hold the banks.
3b-02 BACKFILLING.
Trenches shall not be backfilled until foundation, pipes or cables have been inspected and approved.
Where, in the opinion of the COR, damage is likely to result from withdrawing of shoring, the latter shall be left in place. Trenches shall be backfilled with the excavated materials, if deemed suitable, free from large clods of earth, stones, and roots. Backfilling material shall be deposited in 15 cm.
(6") layers, thoroughly rammed until the trench is completely covered, and watered as necessary. Any material rejected by COR shall be replaced with material acceptable to the COR, coming from borrow pits located outside the US military base.
3b-03 REPAIRS.
All crossings of existing paved or asphalt coated surfaces shall be cut neatly vertical and horizontal.
At the completion of the work, pavement and sidewalks shall be restored to the original conditions.
Damaged lawns shall be sown again and damaged plants shall be replaced with others of the same kinds. Any damage caused during the work progress shall be repaired by and at the expense of the Contractor. The Contractor shall be responsible also for injuries caused to persons as a result of non-compliance with prescribed ISPESL norms.
3b-04 ADDITIONAL REQUIREMENTS.
In addition to above requirements, before starting the excavation, the Contractor must investigate with a metal detector furnished by himself the location of existing underground utility lines, e.g.
electrical, communications, water, TV lines, or any other utility which may not be shown on the existing condition drawings, in order to prevent damaging or interrupting any existing utility.
Investigation shall be done in the presence of the COR. Trial runs shall be done with the metal detector in the presence of the COR or his representative prior to the investigation. Investigation shall be done following COR approval of metal detector. The Contractor shall mark-up on a copy of the existing conditions the exact field location of the existing utility lines which are found during excavation. This copy shall then be submitted to the COR. Excavation work performed close to existing utility lines shall be done by hand within a 3 meter radius.
SECTION IIId - EXTERIOR DRAINAGE SYSTEM
3d-01 RELATED REQUIREMENTS AND DESCRIPTION OF WORK.
The work includes provision of new drainage system and related work. Provide the system complete and ready for operation.
3d-02 PIPES.
Shall be PVC solid wall pipes type SN4-U, conforming to UNI EN 1401-1. Fittings and flanges shall conform to UNI 7449. The joints shall be of the ball and spigot type with elastomeric seal.
3d-03 FRAMES AND COVERS.
Frames and covers shall be made of ductile iron, Class ISO 1083, in accordance with standard UNI ISO EN 124, Class D400, with round cover, ventilated, 60 cm diameter, opening on rotula.
3d-04 MORTAR.
Mortar for connections to other drainage structures shall be composed of one part by volume of Portland cement and two parts of sand. The quantity of water in the mixture shall be sufficient to produce a stiff workable mortar. Water shall be clean and free of harmful acids, alkalis, and organic impurities. Include with shrinkage additive in accordance with product manufacturer’s recommendations. The mortar shall be used within 30 minutes from the time the ingredients are mixed with water. The inside of the joint shall be wiped clean and finished smooth.
3d-05 BURIED UTILITY WARNING AND IDENTIFICATION TAPE.
Provide detectable aluminum foil plastic-backed tape or detectable magnetic plastic tape manufactured specifically for warning and identification of buried piping. Tape shall be detectable by an electronic detection instrument. Provide tape in rolls, 7,5 cm minimum width, green-colored for the utility involved. Use permanent coloring unaffected by moisture and other substances contained in trench backfill material. Bury tape at a depth of 30 cm below the top surface of earth or the top surface of the subgrade under pavements.
3d-06 DRAINAGE STRUCTURES.
Construct of reinforced concrete as shown on drawings. However, prefabricated concrete pits are acceptable upon submittal and approval of catalogs and shop drawings and upon meeting the wall thickness and reinforcing criteria indicated on drawings.
3d-07 INSTALLATION OF PIPE.
Each pipe shall be carefully examined before being laid, and defective or damaged pipe shall not be used. Pipelines shall be laid to the grades and alignment indicated. Proper facilities shall be provided for lowering sections of pipe into trenches. Under no circumstances shall pipe be laid in water, and no pipe shall be laid when trench conditions or weather are unsuitable for such work.
All pipes in place shall have been approved before backfilling. Laying of pipes shall proceed upgrade with the spigot ends of bell-and-spigot pipe, and the tongue ends of tongue-and-groove pipe pointing in the direction of the flow.
3d-08 PIPELINE TESTING.
Each straight run of pipeline shall be checked for gross deficiencies by holding a light in a manhole; it shall show a practically full circle of light through the pipeline when viewed from the adjoining end of the line.
3d-09 WATERPROOFING OF CONCRETE SURFACE.
Shall consist of one coat of asphalt primer and one coat of oxidized asphalt.
a. Asphalt Primer. Shall consist of bituminous material of commercial type, conforming to UNI 4157, brush-applied on concrete surface which is free of dust, dry and smooth.
b. Oxidized Asphalt. Shall be based on bitumen from selected oils, processed to controlled oxidation.
SECTION IIIf - EXTERIOR SANITARY SEWER SYSTEM
3f-01 RELATED REQUIREMENTS AND DESCRIPTION OF WORK.
The work includes provision of new sanitary system and related work. Provide the system complete and ready for operation.
3f-02 PIPES.
Shall be PVC solid wall pipes type SN4-U, conforming to UNI EN 1401-1. Fittings and flanges shall conform to UNI 7449. The joints shall be of the ball and spigot type with elastomeric seal.
3f-03 FRAMES AND COVERS.
Frames and covers shall be made of ductile iron, Class ISO 1083, in accordance with standard UNI ISO EN 124, Class D400, with round cover, not ventilated, 60 cm diameter, opening on rotula.
3f-04 MORTAR.
Mortar for connections to other structures shall be composed of one part by volume of Portland cement and two parts of sand. The quantity of water in the mixture shall be sufficient to produce a stiff workable mortar. Water shall be clean and free of harmful acids, alkalis, and organic impurities. Include anti-shrinking additive in accordance with product manufacturer’s recommendations. The mortar shall be used within 30 minutes from the time the ingredients are mixed with water. The inside of the joint shall be wiped clean and finished smooth.
3f-05 BURIED UTILITY WARNING AND IDENTIFICATION TAPE.
Provide detectable aluminum foil plastic-backed tape or detectable magnetic plastic tape manufactured specifically for warning and identification of buried piping. Tape shall be detectable by an electronic detection instrument. Provide tape in rolls, 7,5 cm minimum width, red-colored for the utility involved. Use permanent coloring unaffected by moisture and other substances contained in trench backfill material. Bury tape at a depth of 30 cm below the top surface of earth or the top surface of the subgrade under pavements.
3f-06 SEWER STRUCTURES.
Prefabricated concrete pits are acceptable upon submittal and approval of catalogs and shop drawings and upon meeting the wall thickness and reinforcing criteria indicated on drawings.
3f-07 INSTALLATION OF PIPE.
Each pipe shall be carefully examined before being laid, and defective or damaged pipe shall not be used. Pipelines shall be laid to the grades and alignment indicated. Proper facilities shall be provided for lowering sections of pipe into trenches. Under no circumstances shall pipe be laid in water, and no pipe shall be laid when trench conditions or weather are unsuitable for such work.
All pipes in place shall have been approved before backfilling. Laying of pipes shall proceed upgrade with the spigot ends of bell-and-spigot pipe, and the tongue ends of tongue-and-groove pipe pointing in the direction of the flow.
3f-08 PIPELINE TESTING.
Each straight run of pipeline shall be checked for gross deficiencies by holding a light in a manhole; it shall show a practically full circle of light through the pipeline when viewed from the adjoining end of the line.
3f-09 WATERPROOFING OF CONCRETE SURFACE.
Shall consist of one coat of asphalt primer and one coat of oxidized asphalt.
a. Asphalt Primer. Shall consist of bituminous material of commercial type, conforming to UNI 4157, brush-applied on concrete surface which is free of dust, dry and smooth.
b. Oxidized Asphalt. Shall be based on bitumen from selected oils, processed to controlled oxidation.
SECTION VIId - WALLS PAINTING
7d-01 GENERAL.
All surfaces to be painted shall be carefully and adequately prepared by scraping, stripping, edge patching (if required) and whatever else may be required to make the surface smooth and even. All stains, grease, etc., shall be eliminated by suitable solvents. In particular cases the COR may request the application of an insulating coat. When repaired, the wall surfaces shall be made perfectly smooth by sandpapering and subsequently primed. All paints, enamels, special products, etc., shall be delivered to the site in original unbroken containers with intact labels and tags and used either pure or with the thinners indicated by the manufacturer. Color selection is a prerogative of the COR, who will become the owner of the specimen submitted by the Contractor. The paint coats applied over the primer shall be of different shades so that at any time it may be possible to check the number of applied coats. Prior to starting the paint work, samples of the various finish work shall be prepared at the locations indicated and with methods specified. These samples are necessary for selection of colors and workmanship. If necessary, samples shall be prepared a second time with the modifications requested, until approval of the COR is obtained. All precautions and methods suitable to avoid paint splashes or stains on the finished surfaces will be adopted by the Contractor.
All damages caused by the Contractor shall be repaired at no cost to the US Government.
7d-02 MATERIAL.
The following materials shall be used:
a. Interior Masonry Surface.
- Primer, copolymer base in water emulsion.
- Water paint for interior surfaces, resin base.
b. Exterior Masonry Surfaces.
- Primer, pliolite resin base with thinner.
- Wall paint, quartz and resins powders base, rough finish.
SECTION VIIe - EXTERIOR INSULATION AND PLASTIC LINING
7e-01 GENERAL.
The surfaces required to receive exterior plaster insulation shall be cleaned and ridded of dirt, dust, oily matters, and bumps.
7e-02 INSTALLATION OF INSULATING PANELS.
With a trowel apply a heavy strip of adhesive on the perimeter of each panel and on six spots equally distributed on the panel surface. Then firmly press the surface of the panel to the wall, as recommended by the manufacturer. The longer side of panes shall be placed horizontally; vertical joints shall be staggered; all joints shall be tightly butted against each other. Anchorage of panels to the walls shall be ensured by mechanical fastening with nails. Nails shall be provided in the quantity of no less than eight nails per square meter.
7e-03 INSTALLATION OF SCRATCH COAT AND OF REINFORCING GLASS FIVER
MESH.
The scratch coat and the glass fiber reinforcing mesh shall be installed at the same time to obtain a monolithic layer within which the mesh is embedded. The scratch coat shall be applied at the rate of 5 kg/sq.m., including cement, by means of a notch trowel. The reinforcing fiber glass mesh shall be applied on the initial scratch coat. By troweling with sufficient pressure, the mesh shall be embedded into the scratch coat. The longer side of mesh shall be installed horizontally while overlappings shall be realized both horizontally and vertically. Overlappings will not be less than 7 cm.
7e-04 APPLICATION OF PAINT COAT SUPPORT AND FINISH COAT.
The paint coat support shall be applied with a brush or roll at a rate of no less than 0.20 kg/sq.m.
and shall be of the same color of the finish coat. The finish coat shall be applied with a special trowel after having mixed the product. The application shall be made by hand by spreading the mixed material in a single layer on the prepared surface and passing over it with the same tool horizontally and vertically to flatten the coat as much as possible. Finish coat shall not be applied before 24 hours from the application of paint coat support. Application shall be continuous and at a rate of no less than 3.5 kg. per square meter for a thickness of about 2.5 mm.
7e-05 CAULKING.
Where there are different aterials all joints in the system shall be caulked as required by the representative of the material manufacturer.
7e-06 DRYING AND CURING.
No special care shall be taken for curing. For drying it is recommended to use care for the first two hours after application. The ideal temperature during this time shall not be above 26 degrees C (80 degrees F).
7e-07 ACCEPTANCE AND REPAINTING.
Work with cracks, blisters, pits, checks, or discoloration will not be accepted. Work shall be clean and sound and in accordance with the requirements of these specifications. After all other related work has been completed, finishing around trims and openings and repairing of damaged portions shall be performed to the satisfaction of the Contracting Officer. Repairs shall match existing work in texture and color.
7e-08 MATERIALS.
a. Insulating Panels. Insulating panels shall be expanded polystyrene panels of the size 100x50 cm., 20 kg/cm. density, conforming to the UNI standard 7819 F.A. 92, type PSE 20 A E, self©extinguishing. The thickness of polystyrene, if not differently noted on drawings, shall be 4 cm.
b. Adhesive. Adhesive shall be a paste, composed of synthetic resins in water solution, mixed on the field with portland cement 325/425, at rate of approximately 40%.
c. Nails for Mechanical Fastening. Nails for mechanical fastening shall consist of a plastic expansion anchor, 90 mm. long, with flat and large head and a hole of 6 mm. in diameter to receive the pin.
d. Accessories. Accessories such as corner beads, base profiles, profiles, joint profiles, and all other accessories, if not otherwise indicated, shall be made of anodized aluminum alloy and painted with a protective anti-alkali paint.
e. Scratch and Base Coats. Scratch and base coats shall be of the same composition as the adhesive but with ta cement rate of 30©35%.
f. Reinforcing Mesh.œ Reinforcing mesh shall be fiber glass wire mesh with 0.370 kg/sq.m. strength, 5x5 mm. mesh.
g. Paint Coat Support. Paint coat support shall consist of one coat of acrylic paint (unsaponifiable) in order to obtain a perfect anchorage of the finish coat.
h. Finish Coat. The finish coat shall be composed of a mixture of quartz, marble granulate, and colored pigments constituted of fine oxides, and shall be bonded together by acrylic resins (unsaponifiable). Finish appearance shall be "scratched" type; color shall be as requested by COR.
NOTE: Unless otherwise indicated on the drawings, the contractor shall remove everything installed on the wall concerned by the work (indication signs, electrical, telephone, and lighting systems, etc.). At work completion, removed equipment shall be reinstalled above the plastic lining.
SECTION VIIIa - REPAIR OF THE ROOF MEMBRANE
8a-01 REPAIR AND PREPARATION OF THE EXISTING MEMBRANES.
If the existing membrane is adhering well to the support, it shall be cleaned and dusted accurately and any grown up vegetation shall be removed. Afterwards a coat of bituminous primer in a solvent base, ready for use, shall be applied at the rate of about 200 g/sq m. The detached areas shall be glued by a propane gas torch. In case of crevices, first the treatment with the primer shall be applied, and subsequently a waterproofing membrane of elasto-plastomeric material reinforced with non-woven polyester fabric (4 mm thick) shall be applied. The strip of membrane shall be glued only along all the perimeter and shall extend on each side by 15 cm minimum over the area with the crevice. Any bobble shall be cut cross-wisely; after the contained humidity has gone, the cut edges shall be glued by a propane gas torch; a patch of membrane shall be applied to adhere totally to the restored area. The patch shall extend over the cut area by 15 cm as a minimum, along the total perimeter. In the connection areas, in the corners, and where there are strain and fissures, adequate reinforcing stripes of membrane shall be glued after smoothing the edges with adequate profiles. Where the concrete supports have been removed, an insulation similar to the existing one and having the same thickness shall be installed after coating the support with a bituminous primer and closing the bitumious membrane by gluing it with a propane gas torch.
8a-02 WATERPROOFING.
The waterproofing shall consist of a new membrane to be applied after the surface has been repaired (as required at the preceding paragraph). An accurate cleaning of the existing membrane with methods deemed as most suitable by the contractor shall be performed; the selected methods shall, however, ensure a surface preparation adequate to receive the primer application. The primers to be used for the priming shall be of two different types: one for cement containing supports to be used on the existing bituminous membranes, and the other for non-porous supports such as metallic surfaces of the flashings. The primer quantity shall be 150/200 gr/sq m. At the completion of all preliminary operations, the plasto-elastomeric membrane reinforced with uninterrupted polyester thread, 4 mm thick, protected with gray color slate chips shall be applied for a total adherence, using a propone gas torch. The connections between sheets shall be obtained by overlapping adjacent edges: 8-10 cm at the sides and 12-15 cm transversally.
8a-03 GENERAL RULES.
The membrane application shall not take place in case of humidity or rain, with excessive strong wind, or when the ambient temperature is below 4 degree C. The materials shall be kept inside a closed storage and shall never be exposed to damp of any kind before, during, or after the requested repair. Wet materials shall not be used. The materials shall be kept at a temperature above 10 degree C during the 24 hours immediately before their application.
SECTION VIIIc - ROOF MEMBRANE MATERIALS
8c-01 MATERIALS.
The materials to be used in this contract shall correspond to the technical requirements listed below:
a. Bituminous primer for cement supports:
The primer shall be solvent type, single-component, ready to use:
Composition: bitumen base with surface-active additives in solvents Specific gravity (volumetric mass): 980 (+ 30) g/cu dm Color: black Minimum consumption (on cement surfaces): 200 g/sq m (0.210 l/sq m)
Drying (U.R.. 65% + 20 degree C): about 3 hour.
b. Bituminous primer for non-porous supports:
The primer shall be modified bitumens in solvents base, single-component, ready to use:
Composition: on a base of oxided bitumens plastifying and auxiliary, in solvents Specific gravity (volumetric mass): g/cu dm 980 (+ 30) Color: black Minimum consumption: on steel: 80 g/sq m (0.085 l/sq m), on concrete, wood: 150 g/sq m (0.160 l/sq m) depending on the porosity.
Drying (U.R. 65% + 20 degree C): about 2 hours
c. Waterproofing membranes:
The membranes shall have polymer bitumen elastomeric base, reinforced with non-woven polyester fabric having uninterrupted thread:
Thickness: mm 4.0 (+ 0.2) Color: black Area mass: 3.9 (+ 0.2) kg/sq m
Dimension stability: + 10 mm Reaction to stretch: Longitudinal resistance: 700 N/5 cm Transversal resistance: 565 N/5 cm Longitudinal extension: 45% Transversal extension: 45% Flexibility at low temperature: -10 degree C Shape stability at hot temperature: >120 degree C Waterproofing: >60 Kpa Resistance to transversal and longitudinal tearing: 130 N
d. Waterproofing membranes, self-protected with slate chips:
The membrane shall consisting of metal-cenic resins in a bituminous base, reinforced with non-fabric material of uninterrupted polyester thread.
Color: natural gray Area mass: 4.8 (+ 0.2) kg/sq m
Compound volumetric mass: 0.96 (+ 0.02) kg/cu dm Thickness: mm 4.0 (+ 0.2), slate excluded.
Dimension stability: + 10 mm Reaction to stretch: Longitudinal resistance: 750 N/5 cm
Transversal resistance: 650 N/5cm Longitudinal extension: 50% Transversal extension: 50% Flexibility at ambient temperature: -20 degree C
Shape stability at hot temperature: >140 degree C Sliding at hot temperature (+90 degree C): <1 mm Waterproofing: >60 Kpa Permeability to water vapor: >80,000 micron
Resistance to static punching on a rigid and non-rigid support: PS4 Resistance to dynamic punching on a rigid and non-rigid support: PD4 Resistance to longitudinal tearing: 160 N Resistance to transversal tearing: 180 N Dimension stability at a thermal action: <0.5%
e. Vapor Barrier:
The barrier shall consist of a prefabricated waterproofing membrane on a bitumen-polymer vapor-poof base and of a reinforcement made of an aluminum sheet and of “velo-vetro”.
The barrier shall have the following characteristics:
Thickness: 2 mm;
Waterproofing: Kpa >60;
Water vapor-proofing: absolute;
Flexibility at low temperature: -10 degree C Shape stability at hot temperature: 120 degree C.
f. Insulating Panels.
Panels shall have a base of expanded pearlite, cellulose and glass fibers, dimensions 1200x600 mm, total layer thickness 60 mm. The panels shall have the following characteristics:
Density: 150 kg/cu m;
Thermal conductivity: 0.040 Kcal/m h C;
Resistance to compression: > 300 Kpa Breaking load at bending: > 500 Kpa
Fire reaction: Class 1.
g. Certifications and Tests:
The membrane described at subparagraphs d. above shall be complete with a certification of adequacy issued by the ICITE (Istituto Centrale Industrializzazione e Tecnologia Edilizia) to be provided by the contractor with the material submission and before the work start. The waterproofing membranes shall be installed in compliance with the requirements contained in the adequacy certification issued by the ICITE.
For each type of membrane installed under this contract, samples of materials shall be taken by the contractor to be analyzed at his/her expense by the ICITE laboratories, to determine the characteristics specified below:
Flexibility at ambient temperature;
Dimensions stability.
The taken samples shall have dimensions sufficient to perform the tests. These shall be performed in the quantities specified below:
one series of tests per quantities over 500 sq m of membrane installed;
one additional series of tests over the 1,500, 2,500, 3,500, (etc.)of membrane installed.
The samples shall be taken at the presence of and in conjunction with the COR.
SECTION Xb - FALSE CEILING
10b-01 GENERAL.
Prior to starting works, surfaces remaining above false ceiling shall be inspected to determine conditions that will prevent a satisfactory installation. Such conditions shall be corrected prior to work starting.
10b-02 INSTALLATION OF LAY-IN PANEL SUSPENSION SYSTEM.
Installation of the suspension system for the suspended acoustical ceiling shall be in accordance with the requirements specified herein. Acoustical work shall be provided complete with all necessary fastenings, clips, and other accessories required for a complete installation. Mechanical fastenings shall not be exposed in the finished work. Hangers shall be laid out for each individual room.
Hangers shall be placed to support framing around beams, ducts, columns, grilles, and other penetration through ceilings. Main runners shall be kept clear of abutting walls and partitions. At least two main runners shall be provided for each ceiling span. Unless otherwise shown, the ceiling grid shall be symmetrically about the center lines of the space. Partial modules, when necessary due to non-modular spaces, shall occur at the perimeter and shall be arranged so that modules less than one half width are minimized.
a. Wall Molding. Wall molding shall be provided where ceilings abut vertical surfaces.
Wall molding shall be secured no more than 8 cm. (3 inches) from ends of each length and no more than 20 cm. (8 inches) on centers between end fastenings.
b. Ceiling Tiles. Ceiling tiles shall be installed in accordance with the approved installation instructions of the tile manufacturer. Edges of ceiling tiles shall be in close contact with metal supports, with each other, and in true alignment. Tile shall be arranged so that units less than one half width are minimized. Panels in exposed grid system shall be held in place with manufacturer's standard hold-down clips.
10b-03 CLEANING. Following installation, dirty or discolored surfaces of units shall be cleaned and left free from defects. Units that are damaged or improperly installed shall be removed and new units provided, as directed.
SECTION XIIa - GENERAL REQUIREMENTS MECHANICAL SYSTEMS
12a.1 INTRODUCTION The term “mechanical systems” applies to the following systems:
- Plumbing, waste and vent
- Heating and air conditioning
- Ventilation
- Compressed air
- Fire protection.
12a.2 REFERENCE NORMS.
Mechanical systems shall be installed in compliance with the applicable Italian and US norms, including the US Army norms. In case of conflict between the norms mentioned above, the more preservative criteria shall be adopted to enhance safety and energy saving.
The workmanship for the installation of mechanical systems shall be all norms UNI and UNI EN applicable to mechanical systems, even though not specifically listed in these technical specifications, but governing at the date of the provision of the project as indicated on the drawings.
Any references to not Italian or European standards shall be specifically indicated on the drawings and in these technical specifications.
12a.3 REQUIREMENTS OF THE FIRM IN CHARGE OF THE SYSTEM
INSTALLATION.
The firm in charge of the installation shall have all requirements called for by Decree n. 37 of 22 January 2008:
- Shall be enlisted in the roll of firms as per Decreto del Presidente della Repubblica 7 December 1995, n. 581 and subsequent modifications or in the Albo Provinciale delle Imprese Artigiane as per law 8 August 1985, n. 443;
- Shall have the certificates acknowledging the technical-professional requirements, as per the types approved with Decreto del Ministro dell’Industria, del Commercio e dell’Artigianato of 11 June 1992. Specifically the firm shall have the following qualifications:
Plumbing and drainage systems of any type, fire-fighting systems: authorization to work on systems as per paragraph “d.” of article 1 of DM 37/08 Heating, air conditioning and refrigeration system of any type, including exhaustion of burning products and of condense, ventilation and aeration of rooms: authorization to work on systems as per paragraph “c.” of article 1 of DM 37/08.
Fire system: authorization to work on systems as per paragraph “g.” of article 1 of DM 37/08.
Before starting the work, the firm in charge of…