Attachment 0009 - RCIS Technical Review Criteria
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Route Clearance & Interrogation Systems (RCIS)
TECHINICAL REVIEW CRITERIA
28 April 2015
SRR Details Area SRR Review Details
Chairperson APM Appliqué (or designee)
PMO Participants PdM ALUGS
Members of RCIS IPT(Contracting, Cost Analysis, Scheduler, LSE, Engineering, Software, Test, Logistics)
Contracting Officer
Anticipated
Stakeholder Participant
Organizations
PM Force Projection
PdM CE/MHE
PdM AMS
MSCoE
ATC/ATEC
Anticipated Peer and
Program-Independent
SME Participant Orgs.
TARDEC
Purpose of the review Ensures the contractor understands the RCIS Performance Specification and the proposed approach is compliant with these requirements.
Entrance Criteria SRR Agenda Per the DAG Section 4.2.10
Exit Criteria Per the DAG Section 4.2.10
Products/Artifacts
(from the review)
Contractor documentation per contract delivered and accepted.
Government Documents per the DAG Section 4.2.10.
PDR Details Area PDR Review Details
PMO Participants PdM ALUGS
Members of RCIS IPT(Contracting, Cost Analysis, Scheduler, LSE, Engineering, Software, Test, Logistics)
Contracting Officer
Anticipated
Stakeholder
Participant
Organizations
PM Force Projection
PdM CE/MHE
PdM AMS
MSCoE
ATC/ATEC
Anticipated Peer and
Program-Independent
SME Participant Orgs.
TARDEC
Purpose of the review
The Preliminary Design Review (PDR) ensures the preliminary design and basic system architecture are complete, and that there is technical confidence the capability need can be satisfied within cost and schedule goals. The PDR provides the acquisition community, end user, and other stakeholders with an opportunity to understand the trade studies conducted during the preliminary design, and thus confirm that design decisions are consistent with the user’s performance and schedule needs. The PDR also establishes the system’s allocated baseline.
Entrance Criteria PDR Agenda Action items from the SRR have been closed
Per the DAG Section 4.2.12
Exit Criteria Per the DAG Section 4.2.12
Products/Artifacts
(from the review)
Government Documents per the DAG Section 4.2.12.
CDR Details Area CDR Review Details
PMO Participants PdM ALUGS
Members of RCIS IPT(Contracting, Cost Analysis, Scheduler, LSE, Engineering, Software, Test, Logistics)
Contracting Officer
Anticipated
Stakeholder Participant
Organizations
PM Force Projection
PdM CE/MHE
PdM AMS
MSCoE
ATC/ATEC
Anticipated Peer and
Program-Independent
SME Participant Orgs.
TARDEC
Purpose of the review
The Critical Design Review (CDR) confirms the system design is stable and is expected to meet system performance requirements, confirms the system is on track to achieve affordability and should cost goals as evidenced by the detailed design documentation, and establishes the system’s initial product baseline.
Entrance Criteria CDR Agenda Action items from the PDR have been closed
Per the DAG Section 4.2.13
Exit Criteria Per the DAG Section 4.2.13
Products/Artifacts
(from the review)
Government Documents per the DAG Section 4.2.13.
SVR/FCA Details Area SVR/FCA Review Details
PMO Participants PdM ALUGS
Members of RCIS IPT(Contracting, Cost Analysis, Scheduler, LSE, Engineering, Software, Test, Logistics)
Contracting Officer
Anticipated
Stakeholder
Participant
Organizations
PM Force Projection
PdM CE/MHE
PdM AMS
MSCoE
ATC/ATEC
Anticipated Peer and
Program-Independent
SME Participant Orgs.
TARDEC
Purpose of the review
The System Verification Review (SVR) is the technical assessment point at which the actual system performance is verified to meet the requirements in the system performance specification and is documented in the system functional baseline. The Functional Configuration Audit
(FCA) is the technical audit during which the actual performance of a system element is verified and documented to meet the requirements in the system element performance specification in the allocated baseline.
Entrance Criteria
SVR/FCA Agenda Action items from the CDR have been closed
Per the DAG Section 4.2.14
Exit Criteria Per the DAG Section 4.2.14
Products/Artifacts
(from the review)
Government Documents per the DAG Section 4.2.14.
PRR Details Area PRR Review Details
PMO Participants PdM ALUGS
Members of RCIS IPT(Contracting, Cost Analysis, Scheduler, LSE, Engineering, Software, Test, Logistics)
Contracting Officer
Anticipated
Stakeholder
Participant
Organizations
PM Force Projection
PdM CE/MHE
PdM AMS
MSCoE
ATC/ATEC
Anticipated Peer and
Program-Independent
SME Participant Orgs.
TARDEC
Purpose of the review
The Production Readiness Review (PRR) for the system determines whether the system design is ready for production, and whether the developer has accomplished adequate production planning for entering
Low-Rate Initial Production (LRIP) and Full-Rate Production (FRP).
Production readiness increases over time with incremental assessments accomplished at various points in the life cycle of a program.
Entrance Criteria
PRR Agenda Action items from the SVR/FCA have been closed
Per the DAG Section 4.2.15
Exit Criteria Per the DAG Section 4.2.15
Products/Artifacts
(from the review)
Government Documents per the DAG Section 4.2.15.
TRR Details Area TRR Review Details
Chairperson APM Appliqué (or designee)
PMO Participants PdM ALUGS
Members of RCIS IPT(Contracting, Cost Analysis, Scheduler, LSE, Engineering, Software, Test, Logistics)
Contracting Officer
Anticipated
Stakeholder Participant
Organizations
PM Force Projection
PdM CE/MHE
PdM AMS
MSCoE
ATC/ATEC
Anticipated Peer and
Program-Independent
SME Participant Orgs.
TARDEC
Purpose of the review
The Test Readiness Review (TRR) is a technical review designed to ensure that the subsystem or system under review is ready to proceed into formal test. The TRR assesses test objectives, test methods and procedures, scope of tests, and safety and confirms that required test resources have been properly identified and coordinated to support planned tests. The TRR verifies the traceability of planned tests to program requirements and user needs. It determines the completeness of test procedures and their compliance with test plans and descriptions. The TRR also assesses the system under review for development maturity, cost/ schedule effectiveness, and risk to determine readiness to proceed to formal testing.
Entrance Criteria
Program manager's and T&E WIPT's determination that preliminary, functional, and pre-qualification test evaluation results form a satisfactory basis to initiate formal, system-level testing.
System has stabilized in configuration Compliance with Pre-TRR checklist
Exit Criteria
Necessary stakeholders were involved.
All planned tests verify a requirement that is directly traceable back to a system specification or other program requirement.
The system under test (i.e. configuration) is sufficiently mature, defined, and representative to accomplish planned test objectives and or support defined program objectives.
All planned preliminary, informal, functional, unit level, subsystem, system, and qualification tests were conducted, and are the results are satisfactory.
All expected results are known and their affect on the program is also known.
All planned tests resources (people, test article or articles, facilities, data systems, support equipment, logistics, etc.) are identified.
All risks associated with the tests are known and mitigation plans are complete.
Hazards and ESOH risks associated with the specific testing are identified.
The necessary “Safety Releases” from the Program Manager (PM) are provided to developmental and operational testers prior to any test using personnel.
A fall-back plan (should a technical issue or potential showstopper arise during testing) is available.
Products/Artifacts
(from the review)
Completed and approved test plans for the system under test.
Completed identification and coordination of required test resources.
Previous component, subsystem, and system test results form a satisfactory basis for proceeding into planned tests.
Identified risk level acceptable to the program leadership.
PCA Details Area PCA Review Details
PMO Participants PdM ALUGS
Members of RCIS IPT(Contracting, Cost Analysis, Scheduler, LSE, Engineering, Software, Test, Logistics)
Contracting Officer
Anticipated
Stakeholder
Participant
Organizations
PM Force Projection
PdM CE/MHE
PdM AMS
MSCoE
ATC/ATEC
Anticipated Peer and
Program-Independent
SME Participant Orgs.
TARDEC
Purpose of the review
The Physical Configuration Audit (PCA) is a formal examination to verify the “to be fielded” configuration of a validated system against its design and manufacturing documentation. The objective of the PCA is to resolve any discrepancies between the production-representative item that has successfully passed Operational Test and Evaluation (OT&E) and the associated documentation currently under configuration control.
Entrance Criteria
PCA Agenda Action items from the PRR have been closed
Per the DAG Section 4.2.16
Exit Criteria Per the DAG Section 4.2.16
Products/Artifacts
(from the review)
Government Documents per the DAG Section 4.2.16.