Attachment 0015 - B333 Parapet Evaluation Report Rev 1 (27AUG26).pdf

PDF 3 MB Posted

Attached to
Building 333 - Roof Repair
Solicitation number
W519TC-26-R-A067
Issued by

About this file

This is a commercial roofing inspection and assessment report for a parapet evaluation project (B.333 Western Roof Parapets) conducted at Rock Island Arsenal, Rock Island, Illinois on August 27, 2026. The inspection included visual examination and photo documentation with localized exposure of parapet coping components to assess existing conditions and deterioration.

The existing parapet assembly consists of prefinished sheet-metal coping (approximately 15.5" to 16" wide), modified-bitumen roof membrane, modified-bitumen vertical base flashing, wood nailers beneath the metal coping, and concealed metal support and attachment components. The main parapet height measures 34" to 35", with lower parapet sections ranging from 16" to 18" and overall wall thickness of approximately 14" to 16". Investigation revealed significant concealed deterioration including: deteriorated wood nailers exhibiting extensive moisture staining and loss of material integrity; significant corrosion of concealed steel components and attachment elements; and evidence of chronic moisture infiltration concentrated beneath coping areas and flashing transitions. The assessment concludes that replacement of surface components alone will not adequately address existing deficiencies. Recommended corrective work includes: removing coping assemblies in affected areas for full evaluation, removing and replacing deteriorated wood nailers, inspecting and replacing corroded metal support and attachment components as required, installing new metal coping assemblies, and replacing associated modified-bitumen flashing at parapet locations. The evaluation was completed by Brandt McCormick and prepared by Angie Smith, Assistant Service Manager.

View the file

Other files

File Type Posted
Solicitation Amendment W519TC26RA067 0009.pdf PDF
Solicitation Amendment W519TC26RA067 0008.pdf PDF
Solicitation Amendment W519TC26RA067 0007.pdf PDF
Solicitation Amendment W519TC26RA067 0006.pdf PDF
Attachment 0013 - B333 - Inspection Report - 2024.06.04.pdf PDF
Attachment 0014 - Questions and Answers.pdf PDF
Solicitation Amendment W519TC26RA067 0005.pdf PDF
Attachment 0003 - 2025-1649 - SOW - Appendix B - Drawings Rev1.pdf PDF
Solicitation Amendment W519TC26RA067 0004.pdf PDF
Solicitation Amendment W519TC26RA067 0003.pdf PDF
Attachment 0012 - Pictures - Set 2.pdf PDF
Attachment 0009 - Site Visit Attendees List.pdf PDF
Attachment 0011 - Pictures - Set 1.pdf PDF
Solicitation Amendment W519TC26RA067 0002.pdf PDF
Attachment 0010 - Canopy Pictures.pdf PDF
Solicitation Amendment W519TC26RA067 0001.pdf PDF
Attachment 0005 - 2025-1649 - SOW - Appendix D - Construction Debris Submittal.pdf PDF
Attachment 0004 - 2025-1649 - SOW - Appendix C - Submittal Register.pdf PDF
Attachment 0002 - 2025-1649 - SOW - Appendix A - Specification.pdf PDF
B08 - Solicitation - W519TC26RA067.pdf PDF
Attachment 0001 - 2025-1649 - SOW.pdf PDF
Attachment 0006 - Wage Determination (IL20260001 - 21MAY2026).pdf PDF
Attachment 0007 - Contractor Vendor Guide.pdf PDF
Attachment 0008 - B333 Roof Site Visit Map.pdf PDF
Attachment 0003 - 2025-1649 - SOW - Appendix B - Drawings.pdf PDF
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project: Parapet Evaluation Inspection Method: Visual inspection and photo documentation, including localized exposure of parapet coping components

Date of Evaluation: August 27, 2026

Existing Construction

Observed parapet assembly consists of:

Prefinished sheet-metal coping system Modified-bitumen roof membrane Modified-bitumen vertical base flashing Wood nailers located beneath metal coping Concealed metal support and attachment components

Approximate Dimensions

Field measurements obtained from photo documentation indicate:

Component Approximate Dimension

Main Parapet Height 34" to 35"

Lower Parapet Sections 16" to 18"

Coping Width 15.5" to 16"

Overall Wall Thickness Approximately 14" to 16"

Dimensions are approximate and based on accessible field measurements and photographic documentation.

Observed Conditions

1. Deteriorated Wood Nailers

Removal of portions of the coping system revealed wood nailers exhibiting:

Extensive moisture staining Visible deterioration Loss of material integrity in localized areas Evidence of prolonged moisture exposure

Wood nailers are a critical attachment component for the coping system. Continued deterioration can impact the long-term performance and secure attachment of the coping assembly.

2. Corroded Metal Components

Exposed sections revealed:

Significant corrosion of concealed steel components Rusting beneath coping assemblies Corrosion of attachment and support elements

The degree of corrosion observed indicates chronic moisture infiltration within the parapet assembly.

3. Moisture Intrusion

Evidence suggests long-term moisture intrusion within the parapet system, including:

Deteriorated wood nailers Corroded metal components Rust staining beneath membrane and coping assemblies Deterioration concentrated beneath coping areas and flashing transitions

Conclusions

The parapet assemblies are not limited to cosmetic deterioration. Investigation confirms concealed deterioration within the coping support system, including both wood nailers and metal attachment components.

The observed conditions indicate that moisture has infiltrated the parapet assembly over an extended period. As a result, replacement of surface components alone may not fully address existing deficiencies.

Recommendations

1. Remove coping assemblies in affected areas for full evaluation.

2. Remove and replace deteriorated wood nailers.

3. Inspect and replace corroded metal support and attachment components as required.

4. Install new metal coping assemblies.

5. Replace associated modified-bitumen flashing at parapet locations.

Overall Assessment

The parapet wall assemblies consist of with approximately 16-inch-wide metal coping systems. Investigation confirmed moisture-related deterioration of concealed wood nailers and significant corrosion of metal components beneath the coping system. Corrective work should include consideration of both visible roofing/flashing repairs and concealed parapet support components to ensure long-term performance of the assembly.

Work Completed by: Brandt McCormick

Prepared by:

Angie Smith Assistant Service Manager

Pictures attached