W519TC25RA011 Contractor QA List Amend 0003.docx

DOCX document 19 KB Posted

Attached to
Request for Proposal (RFP) W519TC25RA011 – Monorail system installation/modernization for McAlester Army Ammunition Plant building 190 east
Solicitation number
W519TC25RA011
Issued by

About this file

The document is a Contractor Q&A List (Amendment 0003) for Solicitation W519TC25RA011, a design-build project for a monorail conveyor system at McAlester Army Ammunition Plant (McAAP) Building 190. The solicitation is a 100% small business set-aside with a projected completion date of March 30, 2029, and an estimated budget between $1,000,000 and $5,000,000. The project requires a Firm Fixed Price contract for designing, engineering, acquiring materials, installing, and validating a new overhead monorail system, including 60 trolleys compatible with the existing 2018-2019 monorail infrastructure.

Key technical requirements include a 6-inch rolled form monorail track, trolleys capable of manual operation through powered sections and drop stations, and compatibility with the existing B190 West system. Contractors must submit detailed technical descriptions, conceptual drawings, and pricing for specific components like the base monorail system, hanger holding rails, spur rail, tar melt out lane, bomb removal station, and paint loop transition. The proposal must be submitted electronically to the Contract Specialist Adam Burgmeier, with questions accepted until 10:00 AM Central Time on August 4, 2025. The United States Army Contracting Command - Rock Island (ACC-RI) will evaluate proposals based on technical acceptability and lowest price.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W519TC-25-R-A011 Contractor Q&A List:

1. How far does the hazard areas extend in zones near paint, stripping, and thermal coating booths?

The hazard area extends three feet around the outer edges of the booth/equipment in question.

2. Does the hazard rating apply all the way to the hoist? Or just a portion of the space?

The hazard rating just pertains to the space around the booth/equipment, not to the hoist itself.

3. Could you tell us what the original Monorail is? And what it looks like?

The existing original monorail track is 6 inch rolled form (in the SOW 3.1.11). The hanger assembly drawing (page 2 of the drawings attachment) also gives dimensions to what the track should be based on fitting that hanger assembly.

4. Is the contractor responsible for supply of the (60) trolleys mentioned in para 3.1.16 of the spec

Yes, the contractor is responsible for the trolleys.

5. Is there any technical specification for the trolley

The trolleys are to be able to hold the loads as specified in the solicitation. They are to be easily maintainable, and they should be made of commercial off the shelf items that can be easily acquired and replaced. They are to fully function in the manual system, have the ability to run in either direction, and readily attach and move through the drop stations and powered sections of the monorail. The trolleys must also be fully compatible to operate on the existing monorail system in B190 West, since system compatibility is essential meeting the requirements of this proposal. This includes moving in manual mode, through all powered sections and drop stations, along the elevation transition sections, and interfacing as necessary with all existing equipment.

6. How old is the current system?

Installation occurred in 2018-2019

7. Is there any hoist mounted on the trolley, are we supply the hoists as well? if yes, please provide technical specs for the hoist

Hangers will be attached to the trolleys, and these will be provided by McAAP.

8. Is there a site visit scheduled for this project, so we can familiarize ourselves with the site conditions?

A mandatory site visit is not required for proposal submission, however, if you would like to schedule a site visit please coordinate with POC Tyler Harper, tyler.c.harper.civ@army.mil, (918) 420-7447

9. When is the soonest possible start date?

As soon as MCAAP clears out the building as needed and a final design has been approved. Coordination will be between MCAAP and the contractor.

10. Would there be milestone progress payments available on this project?

Progress payments were not to be contemplated for this project.

11. With this being expected to be a multi year project, we plan on adding an inflation index escalator on our price, are you expecting this as the format for the multi year pricing? Do you have an expected rate in mind for that or should we use general inflation estimates?

Please use general inflation estimates so a fair and reasonable price can be determined.

12. Is there a ROM budget or expected magnitude?

Between $1,000,000 and $5,000,000.

13. Is the end user open to purchasing engineering hours to design and develop the project?

The proposal as stated is for the contractor to completely design, engineer, acquire materials, install, and validate functionality of a completed monorail system to meet the specifications and requirements of McAAP. All engineering hours are to be included in the bid for the final installed system.

File details come from the government source that posted it. Updated .