Q_A for RFQ W519TC-23-R-2076 Mooring Eyes Repair Installation at Dirab KAA KSA.pdf

PDF 128 KB Posted

Attached to
Mooring Eyes Repair & Installation at Dirab & KAA
Solicitation number
W519TC-23-R-2076
Issued by

About this file

This document contains questions and answers regarding solicitation number W519TC-23-R-2076 for mooring eyes repair and installation at Dirab and KAA airbases in Saudi Arabia. The U.S. Army Contracting Command is seeking to repair and install 384 mooring eyes and 48 grounding points at the two airbases within 200 calendar days of contract signing, with all work to be completed within 90 days of notice to proceed for each installation. Bidders may propose constructing both airbases in parallel to meet the schedule. Long lead items may be substituted if technically acceptable.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

No. Reference (i.e. document - SOW) Reference Text (i.e. paragraph #) Vendor Question/Comment Government Response:

1 Dirab and KAA - Mooring Eyes SOW Final 20230813

4.2.5 The KTR shall provide the following equipment

IAW TM 1-1500-250-23, to be delivered with installation:

• One (1) MB-1 Chain Adjuster Assembly per mooring eye, NSN 160-00-212-1149 or equivalent

There is a missing number in the NSN provided. Please provide the NSN number for the chain adjuster assembly.

Reference Attachment #2 for MB-1 Chain Adjuster Assembly

2 Dirab and KAA - Mooring Eyes SOW Final 20230814

4.2.1 Kashm Al Aan Airfield (KAA) – (Reference

Attachment 1 Tab B)

Please advise if attachment 1 Tab B is for Dirab AirBase or Kashm Al Aan Air Base.

Attachment #1 Tab B is for Kashm Al Aan Air Base

3 Dirab and KAA - Mooring Eyes SOW Final 20230815

4.2.3 Total build Includes 384 mooring eyes and 48

grounding points..

Please advise that the total quantity in this RFQ for mooring eyes are 384 and ground points area 48

Correct.

4 Attachment 1_Approved Mooring Eyes Airfield Diagrams_hawk eagle exempt

Page 3 Attachment 1 – Tab C Sunshade Additional Mooring Eyes, Specifying All markings will be highlighted with black paint, Please advise us that the existing marking available only a black border or a complete re-marking of each AC parking.

This is for new markings only.

5 Attachment 1_Approved Mooring Eyes Airfield Diagrams_hawk eagle exempt

Page 3 Attachment 1 – Tab D Wash Rack Mooring Eyes, Specifying Wash Rack Drain.

Please advise that the wash rack drain is already in place and only a black border marking is required.

Wash rack Mooring eyes is not a requirement any longer. No quantities in SOW and no installation location in attachment 1 Tab-A or Tab-B.

6 Reference to Attachment 3, B11-2.4 Installation.

Please provide the depth of the existing pavement in Dirab and Kashm al aan airfield.

thickness of existing concrete parking pads for Hawk and Eagle at KAA. Attachment# B208-DAB-SHD-S-201-01-Rev2_concrete thickness

There are many long lead items procurement in this project.

In order to reach 200 days PoP, Can contractor propose the construction of both airfields in parallel?

yes. For long lead time items an appropriate replacement may be considered if technically acceptable. Must meet or exceed specifications if the construction of both airfields in parallel is not acceptable, then 240 days of PoP is acceptable for this solicitation.

RFQ#W519TC-23-R-2076 Mooring Eyes Repair & Installation at Dirab & KAA, KSA - Question Form

1.2.1 The overall period of performance will not exceed

200 calendar days from signing of contract.

1.2.2 All work (design and construction) must be

completed and ready for use no later than ninety (90) calendar days after Notice to Proceed (NTP) is issued for each install request.

Dirab and KAA - Mooring Eyes SOW Final 20230814

Questions _Concerns