Attachment 0012 - Solicitation Question and Answer dated 25 June 2024.pdf
PDF 89 KB Posted
- Solicitation number
- W519TC-23-R-0108
About this file
This document is a set of Solicitation Questions and Answers dated 25 June 2024 related to a federal contract opportunity for Metal Parts and Components for Canister Grenades. The key details are:
The solicitation is for an Indefinite Delivery, Indefinite Quantity (IDIQ) contract for a 5-year Firm Price with Economic Price Adjustment (FP-EPA) to provide metal components for canister grenades in support of the Pine Bluff Arsenal. It is a 100% Small Business Set-Aside with a North American Industry Classification System (NAICS) code of 332999 and a size standard of 750 employees. The solicitation number is W519TC-23-R-0108 and the opportunity is being issued by the Army Contracting Command Rock Island (ACC-RI). The solicitation closes on 17 July 2024. Key topics covered in the Q&A include first article inspection requirements, conformance inspection sampling and acceptance criteria, and material certification.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation Questions and Answers dated 25 June 2024
Q1: I noticed that drawing 13-19-1067, Cup calls out MIL-DTL-32743 for inspection requirements, but it was not provided as part of the solicitation. Is that something you can provide?
A1:
4.2 (CUI) First article inspection.
4.2.2 (CUI) First article sampling. A first article sample shall be submitted for inspection in accordance with Table II. The sample shall be randomly selected from the first article lot, and of individual components and assemblies as specified.
4.2.3 (CUI) Inspection requirements. The first article sample items shall be examined and tested for compliance with all of the requirements of the applicable drawings and this specification.
4.2.4 (CUI) Acceptance criteria. If any first article sample item fails to comply with any of the applicable requirements, the first article sample shall be rejected. The Government reserves the right to terminate inspection upon any failure to comply with any of the requirements.
(CUI) TABLE I. First article sampling.
4.3 (CUI) Conformance inspection.
4.3.2 (CUI) Sampling. Sampling shall be conducted in accordance with the conformance criteria of the classification of characteristics in 4.3.5. Samples shall be selected at random.
4.3.3 (CUI) Acceptance criteria. Failure of any sample item to conform to any characteristic in the classification of characteristics based on the sampling and acceptance criteria specified therein shall be cause for rejection of the lot represented.
4.3.4 (CUI) Critical characteristics. Unless otherwise specified in the classification of characteristics, the sampling and acceptance criteria for critical characteristics shall be in accordance with the critical characteristics paragraph of MIL-STD-1916. If any critical defects are encountered the special reservations for critical nonconformance paragraph of
MIL-STD-1916 shall apply.
Item Drawing Verification Inspection
Method
Cup 13-19-1067 32 for examination 4.2.3, 4.3.5.3
Solicitation Questions and Answers dated 25 June 2024
4.3.5 (CUI) Classification of characteristics. Conformance inspections shall be as specified in the following classification of characteristics paragraphs. When verification levels (VLs) are specified for selection of sample sizes and acceptance criteria, the sampling plans of MIL-STD-1916 shall apply unless otherwise specified.
4.4.4 (CUI) Lot numbering and ammunition data cards. Verify that an ammunition lot number has been assigned to each lot of grenades and that the ammunition data card information is complete and correct.
4.4.5 (CUI) Material properties and certification. Verify by examination of objective evidence that the material, components, and assemblies have been tested and accepted in accordance with specification requirements.
Paragraph
4.3.5.3
(CUI)
Title
Cup Sheet 1 of 1
Drawing Number
13-19-1067 Next Higher Assembly
13-19-1066
Category Examination or Test Conformance
Criteria
Requirement
Paragraph Inspection Method
Critical None Defined
Major
101 Shoulder outer diameter Note 1 3.2 AIE
102 Shoulder depth Note 1 3.2 AIE
103 Conical major inner diameter Note 1 3.2 AIE
104 Conical minor inner diameter Note 1 3.2 AIE
105 Flange width Note 1 3.2 AIE
106 Cup cavity depth Note 1 3.2 AIE
107 Material thickness 4.4.5 3.2 4.4.5
Minor
201 Workmanship VL-II 3.6 Visual
Notes:
1. Tool control. 2 cups from each die set shall be inspected at the beginning and end of each shift. If any nonconformance is found all cups produced since the last inspection shall be rejected. To qualify the die set(s), before first article, and after any rework, reconditioning, replacement or after 1000 cups produced from the die set, 5 cups shall be examined for all dimensions.
File details come from the government source that posted it. Updated .