CES CEKT182732 Pre-Proposal Presentation.pdf
PDF 318 KB Posted
- Solicitation number
- W50SC2-20-R-0005
- Issued by
-
Department of the Army National Guard
About this file
This pre-proposal presentation outlines requirements for a construction contract to build a quarter mile running track at Bradley Air National Guard Base in East Granby, Connecticut. The project involves civil design, site preparation including tree clearing and grading, stormwater drainage and erosion control, track surface paving, and is a small business set-aside solicited by the Department of the Army National Guard with a project magnitude between $500,000 and $1 million. Work must be completed between 7:00 a.m. and 4:30 p.m. Monday through Friday, with early morning hours and utility interruptions requiring prior approval. COVID-19 medical screening is mandatory, and contractor employee screening, vetting procedures and badging are required prior to unaccompanied base access.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W50SC2-20-R-0005 Amendment 0001 20200821.pdf | ||
| 20200821 RFI Log CTANG Track.pdf | ||
| 20200820 RFI Log CTANG Track CEKT182732.pdf | ||
| 20200813 RFI Log CTANG Track CEKT182732.pdf | ||
| Pre-Proposal Attendance.pdf | ||
| W50SC2-20-R-0005 Pre-Proposal 06 AUG 20.pdf | ||
| EXHIBIT A.docx | DOCX document | |
| EXHIBIT B.docx | DOCX document | |
| W50SC2-20-R-0005.pdf | ||
| EXHIBIT C.docx | DOCX document | |
| EXHIBIT D.docx | DOCX document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CEKT182732
Construct Quarter Mile Track Pre-Proposal Presentation
6 August 2020
FY20 SRM
CEKT182732
Construct Quarter Mile Track Pre-Proposal Presentation
6 August 2020
FY20 SRM
103d AW - BRADLEY ANG, CT
Ready – Reliable - RelevantJune 2014
Purpose NOTE: This briefing is not meant to be all inclusive nor does it relieve the general contractor of all requirements IAW Contract Drawings and Specifications
Purpose:
• Highlight certain key components/details to aid prospective general contractors and ensure Owner/Government concerns and mission requirements are addressed
PROJECT INFORMATION:
Project Identification: Construct Quarter Mile Track
Project Location: Bradley Air National Guard Base, East Granby, Connecticut
Owner: Connecticut Air National Guard
Contracting Officer: MSgt Eric Hoss, United States Property & Fiscal Office for Connecticut, 360 Broad Street, Hartford, CT 06105
Overview
WORK COVERED BY CONTRACT DOCUMENTS:
• Design and construct Quarter Mile Running Track located at Bradley Air National Guard Base East Granby, CT 06026.
• The Work includes civil design, tree clearing, grading, site work, storm water drainage, paving, erosion control plan, and storm water plan.
Work Restrictions
On-Site Work Hours:
7:00 a.m. to 4:30 p.m., Monday through Friday.
Note: Early Morning Hours: Requires prior approval of Owner/Government.
Existing Utility Interruptions:
• Do not interrupt utilities serving surrounding facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:
• Notify Owner not less than two days in advance of proposed utility interruptions.
• Obtain Owner's written permission before proceeding with utility interruptions.
Contract CBYD Requirements: CBYD coordination will be with 103d Civil Engineering POC Kenneth Bergeron at Bldg 17 (860) 292-2744
NOTE: ALL CBYD MUST BE SCHEDULED AT LEAST 5 BUSINESS DAYS BEFORE
DIGGING IS AUTHORIZED
Work Restrictions Cont.
Nonsmoking Building:
• Smoking is not permitted within any buildings or within 25 feet (8 m) of bldg. entrances, operable windows, or outdoor-air intakes
Employee Screening, Vetting Procedures & Badging:
• Complete Contract-Contractor Identification Letter (CCIL)
• CCIL requires fifteen (15) Days for processing
• Once cleared for base access you must be badged to work unaccompanied
• Badging Hours: 0730-0930 Tues &Thurs, 0730-0830 Wed, Fri & every other Mon; or if an appointment is scheduled during off times in advance with SFS
SCHEDULE OF OPTIONAL BID ITEMS
(OBIs)
Optional Bid Item #1:
1. Additional lane stripping (3 lanes)
Optional Bid Item #2:
1. Cleared and seeded infield
COVID 19
Medical Screening:
• A 100% COVID-19 screening will be mandatory to ALL personnel entering the installation Guidance:
• U.S. Center for Disease Control and Prevention (“CDC”) http://www.cdc.gov/coronavirus/2019-nco
• Occupational Safety and Health Administration (“OSHA”) guidance on the virus Identification http://www.osha.gov/covid-19
• The CT Department of Health webpage https://portal.ct.gov/coronavirus
• KO/COR will provide updates from the 103d AW
Ready – Reliable - Relevant
Additional Comments
Utilities: The contractor will be responsible for:
All temp utility services Any special fees/extra fees any utility company might issue;
Back flow meters are mandatory