Questions and Answers W50S9B26BA003.pdf
PDF 145 KB Posted
- Attached to
- RHS HVAC Replacement ERVD172002
- Solicitation number
- W50S9B26BA003
- Issued by
-
Department of the Army National Guard
About this file
This is a Questions and Answers document for federal contract opportunity W50S9B26BA003, addressing clarifications on project scope, staffing requirements, technical specifications, and operational constraints for a facility renovation project.
The project involves HVAC, chilled water, controls, and kitchen exhaust replacement at Facility 203. Key scope clarifications include: asbestos-containing materials (ACM) are not anticipated to be disturbed and will be addressed through contract modification if encountered; all work is contractor-furnished with no government-furnished equipment; furniture consolidation will be performed by the government to prevent damage to electronics. Critical operational requirements mandate that Server Rooms 122, 153, and 154 remain continuously conditioned at 68 degrees and powered at all times, while the remainder of the building will be unoccupied during construction. The contractor must provide a Qualified Fire Protection Engineer and Environmental Manager (with training per UFGS 01 57 19 1.6.4), though these positions may be combined with other staffing roles. Site Safety and Health Officer and Quality Assurance/Quality Control duties may be dual-hatted if project requirements are sustained. Commissioning, testing and balancing, and Honeywell DDC controls integration requirements are specified in sections 01 91 00.15, 23 05 93, and Division 25 specifications respectively, with an authorized Honeywell representative required for controls work. Government review periods are 14 days for submittals and 7 days for RFIs. The existing standing seam metal roof, warranted through Drexel Metals with TST Roofing as the approved contractor, requires prior written authorization from Drexel before alterations. The contractor laydown area is designated in the northeast quadrant of the parking lot, with deliveries restricted to Monday-Friday 0700-1600 hours, and after-hours requests requiring 72-hour advance notice. Additional site visits beyond those already conducted are not available.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers W50S9B26BA003
1. Specification section 02 82 00 Asbestos Remediation, Section 1.3 Requirements states to remove ACM floor tile and black mastic located under carpet on the first and second floor, HVAC mastic, and transit panels. Please verify that these asbestos containing materials are to be abated and can a HAZMAT Report be provided?
ANSWER: No ACM on site as per client information. Remove from specification.
2. On the site visit, it was mentioned that the owner will move/relocate some of the furniture for the work to take place. Can you please clarify the extent of furniture removal?
ANSWER: Electronics will be relocated by government to prevent/minimize damage. Furniture in office areas will be consolidated to corners within the offices
3. Prime Contractor Staffing Question: Concerning single/dual/triple-hat requirements, clarify what the Prime Contractor staffing requirements are for the following positions: Superintendent, Project Manager, Site Safety and Health Officer, and Quality Assurance/Quality Control manager.
ANSWER: From COR’s perspective, SSHO and QA/QC duties can be dual hatted so long as project requirements are being sustained. Failure to meet project requirements will remove dual hat option.
4. Prime Contractor On-Site Presence
Question: Clarify on-site presence expectations for the Prime Contractor to staff the following positions on this project: Superintendent, Project Manager, Site Safety and Health Officer, and Quality Assurance/Quality Control manager.
ANSWER: From COR’s perspective, SSHO and QA/QC duties can be dual hatted so long as project requirements are being sustained. Failure to meet project requirements will remove dual hat option.
5. Qualified Fire Protection Engineer
Question: Confirm that a Qualified Fire Protection Engineer (QFPE) must be provided by the Prime Contractor and what efforts will be required by the QFPE this project (e.g., fire protection drawing reviews/approval, quantity of construction surveillance efforts, acceptance testing witness requirements, etc.).
ANSWER: QFPE must be provided by the contractor. Refer to specification 28 31 70 for QFPE efforts.
6. Commissioning
Question: Please clarify commissioning requirements, including whether a third-party Commissioning Authority (CxA) is required, minimum qualifications, witnessing requirements, documentation requirements, and final acceptance procedures.
ANSWER: Refer to specification 01 91 00.15 for commissioning requirements.
7. Commissioning Site Visits
Question: Confirm the total quantity of Commissioning Authority (CxA) site visits required for the entire contract, including post-award, construction, testing, acceptance, and warranty phases.
ANSWER: Refer to specification 01 91 00.15 for commissioning requirements.
8. Sustainability Reference: UFGS 01 33 29 – Sustainability Action Plan and Indoor Air Quality Plan.
Question: Confirm responsibility for completion of all Sustainability Action Plan requirements, High Performance Sustainable Building (HPSB) checklist requirements, energy analyses, Indoor Air Quality calculations, documentation, reporting, and final submissions. If these requirements are the responsibility of the Prime Contractor, please identify the minimum professional qualifications required to perform these services.
ANSWER: These requirements are for the contractor. There are no minimum qualifications to complete this work.
9. Environmental Manager
Reference: UFGS 01 57 19 – Submit Environmental Manager Qualifications to the Contracting Officer.
Question: Please identify the minimum acceptable qualifications for the Environmental Manager and clarify whether this position may be combined with another Prime Contractor staffing position.
ANSWER: The Environmental Manager must be trained to perform the duties outlined in UFGS 01 57 19 paragraph 1.6.4. The position may be combined with other staffing positions.
10. Temporary Systems Criteria
Question: Define acceptable temporary HVAC systems required during each phase of construction and identify the minimum temperature, humidity, and ventilation requirements that must be maintained in occupied areas throughout construction.
ANSWER: Server Rooms 122, 153 and 154 must be conditioned at all times, 68 degrees is acceptable as a set point. Server Rooms 122, 153 and 154 must be powered at all times. The rest of the building will be unoccupied during construction.
11. Temporary Cooling
Question: Is temporary cooling required during phased HVAC replacement? If so, identify the required performance criteria, monitoring requirements, occupied areas to be served, and allowable outage durations.
ANSWER: Server Rooms 122, 153 and 154 must be conditioned at all times, 68 degrees is acceptable as a set point.
12. Structural Rooftop Support
Question: Confirm the structural support and roof reinforcement requirements for all new rooftop mechanical equipment and identify whether any additional structural modifications beyond those shown in the contract documents will be required.
ANSWER: There is no structural work beyond what is shown on the construction document. The existing roof joist system was verified for the designed loads shown on this set of plans.
13. Electrical Outages
Question: Can outages occur during business hours? What are the approved shutdown windows? Can temporary feeders remain energized continuously?
ANSWER: Server Rooms 122, 153 and 154 must be power at all times. The rest of the building will be unoccupied during normal construction hours. Outages require notification but can occur during business hours so long as rooms 122, 153 and 154 remain energized.
14. Government-Furnished Equipment Question: Identify all Government-Furnished Equipment (GFE), Government-Furnished Information (GFI), Government-installed work, utility-provider work, and third-party contractor support anticipated for this project.
ANSWER: All scope for this project is Contractor Furnished.
15. Logistics
Question: Please identify contractor laydown areas, storage locations, crane staging areas, parking locations, delivery restrictions, and any limitations on after-hours or weekend access.
ANSWER: Contractor laydown area will be North East quadrant of the parking lot North East of the facility. This area should accommodate storage, crane and contractor parking. Delivery is restricted to duty hours from Monday-Friday 0700- 1600. Requests for after hours deliveries must be submitted 72 hours in advance and will be approved on a case by case basis.
16. Schedule
Question: Please confirm Government review durations for RFIs, submittals, controls shop drawings, and long-lead equipment requests, and identify whether early procurement of long-lead equipment is permitted prior to submittal approval.
ANSWER: Government review duration for submittals is typical at 14 days. RFI’s will have a 7 day review window.
17. Asbestos Abatement Responsibility
Question: Identify the party responsible for asbestos-containing material removal, abatement, disposal, testing, air monitoring, and clearance requirements for all identified ACM within the project area.
ANSWER: ACM is not anticipated to be disturbed within the scope of project. Any ACM encountered will be treated as a contract modification.
18. Abatement Schedule
Question: Will asbestos abatement be completed prior to contractor Notice to Proceed, or must the contractor coordinate and phase construction activities around existing ACM?
ANSWER: ACM is not anticipated to be disturbed within the scope of project. Any ACM encountered will be treated as a contract modification.
19. Hidden Conditions
Question: The hazardous materials survey excludes certain concealed and inaccessible areas. If hazardous materials are encountered in excluded areas, will associated testing, abatement, schedule impacts, and disposal costs be addressed through contract modification?
ANSWER: Yes.
20. Fire Alarm
Question: Does the Government currently maintain a contract with a Gamewell-FCI fire alarm service provider? If so, identify the provider and define the scope of support available to the contractor.
ANSWER: No current contract. All support is addressed via individual purchase requests.
21. Controls
Question: Does the Government currently maintain a contract with a Siemens or other controls service provider? If so, identify the provider and define the scope of support available to the contractor.
ANSWER: We do not currently maintain a contract.
22. Phasing Requirements
Question: Please define the required construction phasing sequence for HVAC, chilled water, controls, and kitchen exhaust replacement, and identify any areas that must remain continuously operational.
ANSWER: Server Rooms 122, 153 and 154 must be conditioned at all times, 68 degrees is acceptable as a set point. Server Rooms 122, 153 and 154 must be
23. Occupancy Restrictions
Question: Please identify any mission-critical, communications, operations, testing, or administrative spaces that require continuous HVAC service, after-hours work, or special scheduling restrictions.
ANSWER: ANSWER: Server Rooms 122, 153 and 154 must be conditioned at all times, 68 degrees is acceptable as a set point. Server Rooms 122, 153 and 154 must be powered at all times. The rest of the building will be unoccupied during
24. Building Occupancy During Construction
Question: Please confirm whether Facility 203 will remain occupied and operational during construction. If so, identify the occupied areas, required hours of operation, access restrictions, and any limitations on outages, shutdowns, noise, dust-generating work, or work affecting occupant comfort and facility operations.
ANSWER: Server Rooms 122, 153 and 154 must be conditioned at all times, 68 degrees is acceptable as a set point. Server Rooms 122, 153 and 154 must be
25. Honeywell Controls Integration
Question: The solicitation identifies Honeywell DDC controls. Please confirm whether programming, graphics, licensing, database modifications, integration, startup, and commissioning must be performed by an authorized Honeywell representative and identify the authorized provider.
ANSWER: The solicitation identifies Honeywell DDC, we are unable to identify the provider but they must be an authorized Honeywell representative.
26. Roof Warranty
Question: Please provide information regarding any existing roof warranty and identify requirements, approved contractors, inspections, or procedures necessary to preserve warranty coverage for new rooftop equipment and penetrations.
ANSWER: Building 203 Standing Seam Metal Roof is under active Warranty through Drexel Metals. Installation and Approved Metal Contractor is TST Roofing. Alterations to SSMR are required to receive prior written authorization from Drexel.
1234 Gardiner Lane
Louisville, KY 40213
(502) 716-7143, direct
(888) 321-9630, toll free
• Starting date of warranty: 31 OCTOBER 21
27. Structural Discrepancies
Question: If field conditions differ from the structural drawings, including roof framing, joist spacing, panel points, or existing support conditions, will resulting redesign and construction costs be addressed by contract modification?
ANSWER: Yes
28. Temporary Chiller Connections Question: Please clarify the intended purpose of the temporary chiller connections shown in the contract documents and confirm whether temporary cooling equipment is included in the contractor’s base scope.
ANSWER: Temporary chiller connection is intended only to be used if the building chiller is not operating. Temporary chiller during construction is not required.
29. TAB and Commissioning
Question: Please clarify requirements for testing, adjusting, balancing, commissioning authority coordination, controls trend logging, seasonal testing, and final system acceptance.
ANSWER: Refer to specification 01 91 00.15 for commissioning requirements, and refer to 23 05 93 for Testing, Adjusting, and Balancing requirements.
30. Government Network Requirements
Question: Please identify cybersecurity, network connectivity, licensing, server, BACnet integration, and Authority-to-Operate requirements applicable to the DDC controls system.
ANSWER: Refer to Division 25 specifications regarding cybersecurity requirements. Refer to sheet M-701 for additional network information regarding the DDC system.
31. Working Hour Restrictions
Question: Please identify any planned restrictions on outages, shutdowns, noisy work, crane operations, or activities that must occur during nights, weekends, holidays, or nonoccupied hours.
ANSWER: The facility will be unoccupied during construction.
32. Kitchen Hood Fire Suppression
Question: Please confirm whether kitchen hood fire suppression modifications, testing, recertification, monitoring interface requirements, and Authority Having Jurisdiction inspections are included in contractor scope.
ANSWER: Confirmed, scope is in contractor scope.
33. Existing Utilities Verification Question: Please confirm that existing electrical, domestic water, sanitary, and storm utility capacities serving the facility are adequate for the new HVAC systems shown in the contract documents. If utility upgrades beyond the contract drawings are required, will such work be addressed through contract modification
ANSWER: Scope of this project is designed to provide an adequate HVAC system.
If there are any design flaws or unforeseen conditions are encountered in the project they will be addressed via contract modification.
34. Our company just came across this solicitation and are very interested in bidding the work. We saw that there was already a site visit that took place, but we were hoping we could reach out and possibly schedule a time to come by the site to put our eyes on it. I totally understand if this is not possible and should be able to bid this without seeing the site, but it would be helpful to us if we could.
ANSWER: We are not able to offer another site visit.
35. Have you heard about any funding issues with this work?
ANSWER: We have not been advised of any funding issues.
File details come from the government source that posted it. Updated .