This document is a Questions and Answers (Q&A) attachment for the ADAL Corrosion Control Facility federal contract opportunity (Solicitation Number: W50S9525BA001). The Q&A addresses several key technical and administrative details, including acceptable paint products for exposed metal structures, confirmation of toilet partition materials, corner guard heights, and bid bond submission requirements. The document provides additional project-specific information such as temporary facility requirements, including 2,000 square feet of trailers with 5 office spaces, a bathroom, and break area, as well as equipment storage using Conex boxes. The project involves renovating and enlarging a corrosion control facility at McEntire JNGB, with specific notes about site logistics, including crane usage coordination with airfield management and designated staging areas in the parking lot and surrounding grass area.

View the file

Other files for this federal contract opportunity

Other files attached to ADAL Corrosion Control Facility, newest first.
File Type Posted
Pre-Bid Conference Information.pptx PPTX presentation
Pre-Bid Conference Roster.pdf PDF
W50S9525BA0010002 - Amendment 02 SF 30.pdf PDF
Attachment 4 - Hazardous Material Survey - 2019.pdf PDF
Attachment 5 - Form 3 Paint Booth BLDG 1046.pdf PDF
W50S9525BA0010002 - Conformed through Amendment 02.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GOVERNMENT RESPONSES TO BID INQUIRIES: W50S9525BA001, ADAL CORROSION CONTROL FACILITY

1. Clarification on Overhead Coiling Door 101A – Voltage and Dimensions

Could you please confirm the required operating voltage and phase for the motorized overhead coiling door specified under Section 08 33 23 – Overhead Coiling Doors, as well as the exact width and height of Door 101A, since the dimensions are not clearly indicated in the contract drawings or specifications?

Answer: Could not locate a door 101A on the drawings. Please confirm the RFI.

2. What paint product should be used on the exposed metals for all the exposed structure ceilings?

I did not see a Dryfall product and that is what product we typically use on the exposed metals when we paint, I read on page 26 section 099000, Item A, which is a Redular Paint, and it will be very expensive to use cause of the "waste factor" with the structures. Please advise if we are able to substitute for Dryfall product we typically use.

Answer: A Dryfall product for this specific application is acceptable.

3. Are there any underground tanks to be aware of at the site, i.e., like in the courtyard that was identified at the walkthrough.

Answer: HDR civil engineering sheet (CD101) indicates what was discovered during our initial survey. Will defer to SCANG for other historical knowledge of the site. If there is still some uncertainty, HDR would suggest the contractor execute their own survey for any areas needing further confirmation. There is not an underground tank in the courtyard.

4. No Locker manufacturer is stated in the “Interior Finish Legend” on sheet I102. Can you please provide a manufacturer for the lockers?

Answer: HDR defers to SCANG on preference, Gov’t to confirm. See below for a list of potential manufacturers:

a. Art Metal Products

b. DeBourgh Manufacturing

c. List Industries, Inc.

d. Lyon LLC

e. Penco Products

f. Republic Steel

5. No manufacturer is noted for the Toilet Partitions in the “Interior Finish Legend” on sheet i102.

Can you please provide a manufacturer for the toilet partitions?

Answer: HDR defers to SCANG on preference, Gov’t to confirm. See below for a list of potential manufacturers:

a. General Partitions Manufacturing Corp.

b. Accurate Partitions

c. Bobrick

d. American Sanitary Partition Corporation

e. Bradley Corporation

f. Global Partitions Corp., an ASI Group Company

g. Hadrian Manufacturing Inc

GOVERNMENT RESPONSES TO BID INQUIRIES: W50S9525BA001, ADAL CORROSION CONTROL FACILITY

6. In spec section 102113 toilet compartments, can you please confirm the material of the toilet partitions that are required for this project? Phenolic and HDPE Plastic are both stated in the specs.

Answer: Both materials are acceptable.

7. Can you please confirm the height of the corner guards?

Answer: Refer to General Note #28/I-101. Corner guards to extend 4’-0” AFF, starting at the top of any base molding/tiling where indicated.

8. If Is there a REC or any environmental report for the corrosion control building?

Answer: Hazardous Materials Survey and AF Form 3 are provided as attachments 4 and 5 respectively.

9. Based on the following information below from the bid specs. Need to confirm if the original bid bond form needs to be delivered prior to the bid opening or will a scanned copy of the signed and sealed bid bond be acceptable uploaded into the PIEE bid portal?

Answer: A scanned copy of the signed and sealed bid bond uploaded into the PIEE bid portal is required. See Solicitation pages 4-5, section 00 10 00 Notes for complete bid package requirements.

Additional Information

- The building will not be occupied by Government personnel throughout the construction project.

- Contractor is to provide 2,000SF of temporary trailers that will contain 5 office spaces, a bathroom, and a break area/common area. The Government will provide a location where all utilities (power, sewage, water) are available. Contractor will be required to hookup all utilities to the Government’s infrastructure. In addition, Contractor is to provide two 40’ long Conex boxes or four 20’ long Conex boxes for equipment storage. Conex boxes are not required to be climate controlled.

- Usage of a crane on this project will need to be coordinated through airfield management and will need to meet the requirements of FAA.

- The parking lot and surrounding grass area can be utilized for the Bed down staging area.

The staging area will not impeded into the Tree Orchard right beside the parking lot.