W50S8X20B0001_Attachment_5_Bid_Schedule.xlsx
XLSX spreadsheet 21 KB Posted
- Attached to
- IFB: Construct Fuel Systems Maintenance and Aircraft Corrosion Control Hangar Federal contract opportunity
- Solicitation number
- W50S8X-20-B-0001
About this file
This solicitation is for the construction of a fuel systems maintenance and aircraft corrosion control hangar at Moffett Federal Airfield in Mountain View, California. The project scope includes construction of an approximately 46,600 gross square foot hangar and support facilities to support HC-130J and HH-60G aircraft. The contract will be a firm-fixed-price award with a period of performance of 532 calendar days from notice to proceed. The estimated value is between $25-100 million. The pre-bid conference will be held on August 11, 2020 at 10:00am at the project site. Questions for the pre-bid conference must be submitted by August 9. Plans and specifications are available as controlled attachments requiring Joint Certification Program approval. Additive bid items include a wash rack, parking lot paving, fencing, landscaping, and site lighting.
View the file
Other files for this federal contract opportunity
Show all 39
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| BIDDING SCHEDULE QMSN199056 Fuel Cell/Corrosion Control Hangar and Shops Moffett Air National Guard Base (NASA), CA | |||||
| Item | Description | Estimated Quantity | Unit | Unit Price (rounded) | Total |
| 0001 | Fuels/Corrosion Control Hangar and Shops (Primary Facility) | --- | --- | --- | --- |
| 0001A | Foundation/Substructure | 465,000 | SF | $0 | |
| 0001B | Structural Steel/Superstructure | 465,000 | SF | $0 | |
| 0001C | Exterior Enclosure | 465,000 | SF | $0 | |
| 0001D | Roofing Systems | 465,000 | SF | $0 | |
| 0001E | Interior Construction | 465,000 | SF | $0 | |
| 0001F | Interior Finishes | 465,000 | SF | $0 | |
| 0001G | Plumbing Systems | 465,000 | SF | $0 | |
| 0001H | HVAC Systems | 465,000 | SF | $0 | |
| 0001I | Fire Suppression Systems | 465,000 | SF | $0 | |
| 0001J | Interior Electrical and Communication Systems | 465,000 | SF | $0 | |
| 0001K | Fire Detection Systems | 465,000 | SF | $0 | |
| 0001L | Equipment | 1 | JB | $0 | |
| 0001 | Base Bid ITEM 0001 (ITEM 0001A through ITEM 0001L) | 1 | Job | $0 |
| 0002 | Supporting Facilities | --- | --- | --- | --- |
| 0002A | Site Clearing and Demolition | 1 | JB | $0 | |
| 0002B | Earthwork (Grading, Fill & Borrow,Temp Erosion Control) | 1 | JB | $0 | |
| 0002C | Exterial Electrical and Communication Service | 1 | JB | $0 | |
| 0002D | Water (Domestic and Fire) Systems | 1 | JB | $0 | |
| 0002E | Sanitary Sewer System | 1 | JB | $0 | |
| 0002F | Gas Distribution System | 1 | JB | $0 | |
| 0002G | Storm Drainage Improvements | 1 | JB | $0 | |
| 0002H | Pavements, Curb, Gutter, Flatwork | 1 | JB | $0 | |
| 0002I | Site Improvements (Fencing, Gates, Landscaping, Irrigation) | 1 | JB | $0 | |
| 0002 | BASE BID ITEM 0002 (ITEM 0002A through ITEM 0002I) | 1 | Job | $0 |
| GRAND TOTAL BASE BID (BASE BID ITEM 0001 + BASE BID ITEM 0002) | 1 | Total | $0 | |
| 0003 | Bid Option #1 - ABI-1 Wash Rack | 20,925 | SF | $0 |
| 0004 | Bid Option #2 - ABI-2 Parking Lot Paving and Curbing | 10,547 | SY | $0 |
| 0005 | Bid Option #3 - ABI-3 ASE Yard - Fencing Alternate | 1 | JB | $0 |
| 0006 | Bid Option #4 - ABI-4 Landscape | 1 | JB | $0 |
| 0007 | Bid Option #5 - ABI-5 Site Lighting | 1 | JB | $0 |
| 0008 | Bid Option #6 - ABI-6 Copper OSP Cabling | 1 | JB | $0 |
| BASE PLUS ALL OPTIONS | $0 |