Lightning Inspection Building Hangar 308.pdf
PDF 21 MB Posted
- Attached to
- Lightning Protection Systems Repair Federal contract opportunity
- Solicitation number
- W50S8V-24-B-0003
- Issued by
- Department of the Army National Guard
About this file
The provided document is a Solicitation for a Lightning Protection Systems Repair project. The project is being solicited as a Total Small Business Set-Aside, with an expected value between $25,000.00 and $100,000.00. The NAICS code for this project is 238210, with a corresponding size standard of $19.0M. Davis Bacon Wage Rates are applicable, and payment bonds are required if the bid is greater than $35,000.00. The award will be made to the responsible bidder whose bid is most advantageous to the Government, considering only price. The solicitation is being issued by the Department of the Army National Guard. LPS Inspection Reports are attached for reference only.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W50S8V-24-B-0003-0002.pdf | ||
| WD WV20240034 12 July 2024.pdf | ||
| Site Visit PP - Lightning Protection System Repairs.pptx | PPTX presentation | |
| W50S8V-24-B-0003-0001.pdf | ||
| Lightning Protection Systems Repair Site Visit Attendance Sheet.pdf | ||
| QA - Lightning Protection System W50S8V-24-B-0003.pdf | ||
| Lightning Inspection Building 302.pdf | ||
| W50S8V-24-B-0003 Repair LPS.pdf | ||
| Lightning Inspection Building 305.pdf | ||
| Lightning Inspection Building 307.pdf | ||
| Lightning Inspection Building 306.pdf | ||
| Lightning Inspection Building 119.pdf | ||
| Visitor and Contractor Background Check Form Repair LPS.docx | DOCX document | |
| SOW - Repair LPS Base Wide.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MULTIVARIABLE SYSTEMS TECH, LLC
DUNS: 080122060 || FEIN: 81-0768594 || 3923 S. TAVISTOCK PL. || MERIDIAN, ID 83642 || Tel. (208)
867-713ON & TESTING CHECKLIST
Date: _______11/8/23________ Inspected and Tested By: __MVS (Jesse, Dustin, Lumuli________
Structure/Building Identification: ________308 Hangar___________________________________
Date Last Known Rainy Day: ____11 days prior__________ Humidity: ___1%______________________
A. Visual Inspection of Roof Top Components
Item Descriptions Notes/Correction
1 Visual inspections of the overall system condition.
Appearance (neat, dislodged, broken cables etc.).
Several loose cables, downed air terminals, and missing/damaged cables.
2 Visually inspect all air terminals. Verify that size and quantity is sufficient per NFPA 780/UL96A requirements.
X
3 Verify that all air terminals (lightning rods) have been placed at 20’-0” maximum spacing around roof perimeter and/or roof ridges.
X
4 Verify that perimeter air terminals are within 2’-0” of the outside edge including corners of the structure.
X
5 Verify that mid-roof air terminals are spaced at maximum spacing of 50’-0” in accordance with NFPA 780.
X Repaired and re-glued 7 air terminals. 2 are still missing pending roof repairs.
6 Verify interconnecting mid-roof cables connecting mid-roof air terminals are properly spaced. Further verify 150’-0” maximum length of cross run conductor to the main perimeter or down conductor in accordance with NFPA 780.
3 Lines broken and need replaced, however, the roof is damaged (missing gutters, downspouts and soffit panels. Can not repair some LPS cables until the roof is repaired.
7 Verify that copper materials are not mounted or in contact with aluminum materials and vice-versa.
X
8 Verify that all conductors are fastened horizontally and vertically not more than 3’-0” maximum spacing.
Reconnected and glued down.
9 Verify inductive metallic bodies located within 6’ 0” of lightning conductor or another bonded metal body shall be interconnected to the lightning conductor system, unless inherently connected.
X
3923 S. TAVISTOCK PL. || MERIDIAN, ID 83642
B. Visual Inspection Ground System:
C. Ground Resistance & Continuity Testing:
10 Verify air terminals and bonding connectors are installed on rooftop, fans, ventilators. A/C units etc. in accordance with NFPA 780 UL96A.
X
11 Remove and clean all cable connections including but not limited to; Bonding plates, lugs, cable to cable connectors etc.
X
Item Descriptions Notes/Correction
1 Locate all through roof connection to down runs or to structural steel. Visually inspect for damage and tightness.
X
2 Verify the quantity of down runs/connection to ground is adequate per NFPA 780 and UL96A based on the size of the structure.
X
3 If the connection is to steel, verify that connection is made in accordance with NFPA 780 and that the area under connection is clean of all paint, oil, grease etc.
X
4 Verify that spacing of down conductors at roof level are installed in accordance with NFPA 780 and UL96A (100’ on average).
3 Lines Missing. Need repairs but must repair damaged roof prior. (See photos)
5 Visually inspect connections to rebar/structural steel etc. for corrosion remove connections clean and reinstall. Replace if necessary.
X
6 Visually inspect ground rods and cable connections to ground rods. Remove and clean if necessary.
X
Item Descriptions Notes/Correction
1 Record the device readings for all tested points: See Additional Notes
2 Inspect and document status of surge protection - transient voltage surge suppression (TVSS) systems. Verify TVSS systems are installed in accordance to NEC 70 or other applicable codes or standards.
N/A
3 Perform ground resistance on lightning protection grounding system.
See Additional Notes
D. Additional Notes (Building 308):
4 Take additional photographic or video documentation of particular areas of the lightning protection system that needs further long term repair that may go beyond the scope of this inspection but needs attention.
See Attached
HANGER 308 READING
LOCATIONS:
RESISTENCE READINGS: NOTES:
EASTERN SLOPE (lower section):
SE Corner 0.040Ω
East 1 0.23Ω
NE Corner 0.24Ω
North 1 0.054Ω
NW Corner lo.01
SW Corner 2 0.039
CENTER DOME
SW Corner 0.064Ω
East 0.023Ω
NW Corner 0.077Ω
West 3 down lines missing with gutters that have fallen off.
Roof needs repairs before LPS can be repaired on this side.
Removed debris and repaired 7 air terminals. 2 are still missing where lines are gone.
WESTERN SLOPE (lower section)
South 1 0.13Ω
South 2 0.084Ω
East 1 0.11Ω
NE Corner 0.16Ω
NW Corner 0.079Ω
West 0.023Ω
SW Corner 0.077Ω