Lightning Inspection Building 305.pdf
PDF 20 MB Posted
- Attached to
- Lightning Protection Systems Repair Federal contract opportunity
- Solicitation number
- W50S8V-24-B-0003
- Issued by
- Department of the Army National Guard
About this file
The document is a Request for Bid (RFB) for the repair of lightning protection systems. The project is a Total Small Business Set-Aside with a NAICS code of 238210 and a size standard of $19.0M. The expected contract value is between $25,000.00 and $100,000.00. Davis-Bacon wage rates apply, and performance bonds are not required if the bid is less than $150,000.00, but payment bonds are required if the bid exceeds $35,000.00. Award will be made to the responsible bidder with the most advantageous bid, considering only price. The U.S. Department of the Army National Guard is the procuring agency, and funding is anticipated to be available prior to but not later than September 30, 2024. Relevant lightning protection system inspection reports are attached for reference.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W50S8V-24-B-0003-0002.pdf | ||
| QA - Lightning Protection System W50S8V-24-B-0003.pdf | ||
| Site Visit PP - Lightning Protection System Repairs.pptx | PPTX presentation | |
| W50S8V-24-B-0003-0001.pdf | ||
| Lightning Protection Systems Repair Site Visit Attendance Sheet.pdf | ||
| WD WV20240034 12 July 2024.pdf | ||
| SOW - Repair LPS Base Wide.pdf | ||
| W50S8V-24-B-0003 Repair LPS.pdf | ||
| Lightning Inspection Building 307.pdf | ||
| Lightning Inspection Building 306.pdf | ||
| Lightning Inspection Building 119.pdf | ||
| Visitor and Contractor Background Check Form Repair LPS.docx | DOCX document | |
| Lightning Inspection Building 302.pdf | ||
| Lightning Inspection Building Hangar 308.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MULTIVARIABLE SYSTEMS TECH, LLC
DUNS: 080122060 || FEIN: 81-0768594 || 3923 S. TAVISTOCK PL. || MERIDIAN, ID 83642 || Tel. (208)
867-713ON & TESTING CHECKLIST
Date: _______11/7/23________ Inspected and Tested By: __MVS (Jesse, Dustin, Lumuli)________
Structure/Building Identification: ________305 Hangar (building under construction)_________
Date Last Known Rainy Day: ____10 days__________ Humidity: ___1%______________________
A. Visual Inspection of Roof Top Components
B. Visual Inspection Ground System:
Item Descriptions Notes/Correction
1 Visual inspections of the overall system condition. Appearance (neat, dislodged, broken cables etc.). ✔
2 Visually inspect all air terminals. Verify that size and quantity is sufficient per NFPA 780/UL96A requirements.
See Notes
3 Verify that all air terminals (lightning rods) have been placed at 20’-0” maximum spacing around roof perimeter and/or roof ridges.
4 Verify that perimeter air terminals are within 2’-0” of the outside edge including corners of the structure.
5 Verify that mid-roof air terminals are spaced at maximum spacing of 50’-0” in accordance with NFPA 780.
6 Verify interconnecting mid-roof cables connecting mid-roof air terminals are properly spaced. Further verify 150’-0” maximum length of cross run conductor to the main perimeter or down conductor in accordance with
NFPA 780.
See Notes
7 Verify that copper materials are not mounted or in contact with aluminum materials and vice-versa.
8 Verify that all conductors are fastened horizontally and vertically not more than 3’-0” maximum spacing.
9 Verify inductive metallic bodies located within 6’ 0” of lightning conductor or another bonded metal body shall be interconnected to the lightning conductor system, unless inherently connected.
10 Verify air terminals and bonding connectors are installed on rooftop, fans, ventilators. A/C units etc. in accordance with NFPA 780 UL96A.
See Notes
11 Remove and clean all cable connections including but not limited to;
Bonding plates, lugs, cable to cable connectors etc.
N/A
Item Descriptions Notes/Correction
3923 S. TAVISTOCK PL. || MERIDIAN, ID 83642
C. Ground Resistance & Continuity Testing:
D. Additional Notes (If Necessary):
1 Locate all through roof connection to down runs or to structural steel. Visually inspect for damage and tightness.
2 Verify the quantity of down runs/connection to ground is adequate per NFPA 780 and UL96A based on the size of the structure.
3 If the connection is to steel, verify that connection is made in accordance with NFPA 780 and that the area under connection is clean of all paint, oil, grease etc.
4 Verify that spacing of down conductors at roof level are installed in accordance with NFPA 780 and UL96A (100’ on average).
5 Visually inspect connections to rebar/structural steel etc. for corrosion remove connections clean and reinstall. Replace if necessary.
6 Visually inspect ground rods and cable connections to ground rods. Remove and clean if necessary.
Item Descriptions Notes/Correction
1 Record the device readings for all tested points: See Additional Notes
2 Inspect and document status of surge protection - transient voltage surge suppression (TVSS) systems. Verify TVSS systems are installed in accordance to NEC 70 or other applicable codes or standards.
N/A
Perform ground resistance on lightning protection grounding system.
Performed, see notes.
3 Take additional photographic or video documentation of particular areas of the lightning protection system that needs further long term repair that may go beyond the scope of this inspection but needs attention.
See Notes
READING LOCATIONS RESISTANCE READINGS
EAST SLOPE
Air Terminals on East side Each air terminal should have an additional line completing the loop. Recommend additional approximately 75’ of cable and 11 new plates.
Lead Pipe 0.98Ω
East 0.028Ω
East 2 0.022Ω
West 0.055Ω
West 2 0.019Ω
SW Corner Needs a plate and wire connecting down to coupler.
CENTER DOME
SE Corner 0.043Ω
S Red Lights 0.085Ω
S Center Red Lights 0.028Ω
S Red Lights 0.026Ω
SW Corner 0.022Ω
West 0.028Ω
W2 0.020Ω
W3 0.026Ω
NW Corner 0.026Ω
N Red Light 0.018Ω
N Red Light 2 0.028Ω
N Red Light 3 0.029Ω
N Antenna 0.022Ω
N Antenna 2 0.21Ω
NE Corner 0.099Ω
East 0.019Ω
East 2 Lo.01
Center Three air terminals have broken off and will need replaced along with 2 couplers and approximately 3’ of wire.
WEST SLOPE
Center Cable Recommend Splice for frayed cable
SE Corner 0.60Ω
East 0.042Ω
East 2 lo.01
Lead Pipe 0.036Ω
North 0.46Ω
Lead Pipe 2 0.78Ω
NW 0.024Ω
Lead Pipe 3 0.031
W 0.027Ω
W2 0.019Ω
Lead Pipe 0.033Ω
SW 0.014Ω
S Lead Pipe 0.013Ω
Center 3 Air Terminals were laying down. These were repaired.
HVAC Recommend addition of air terminal to HVAC Vent