PWSWYTD232003.docx

DOCX document 74 KB Posted

Attached to
Construct Wall Bldg . 150 and 101 Federal contract opportunity
Solicitation number
W50S8S23B0001
Issued by
Department of the Army National Guard

About this file

This performance work statement outlines requirements for constructing walls and renovating office spaces at two buildings on an Air Force base. The contractor will receive a notice to proceed and have 60 days to complete the work, which includes constructing partition walls, installing doors and hardware, repairing ceilings, relocating HVAC and electrical items, and demolishing existing structures. For building 150, the work involves building an interior wall to separate an office space and modifying finishes and systems. For building 101, additional requirements include installing communications conduits and grounding systems. The contractor must follow all applicable federal, state and local regulations, and submit training certificates for antiterrorism and operations security training. The COR will inspect the work for quality assurance.

View the file

Other files for this federal contract opportunity

Other files attached to Construct Wall Bldg . 150 and 101, newest first.
File Type Posted
W50S8S23B0001 Construct Walls.pdf PDF
W50S8S23B0001 00001 Conform.pdf PDF
Attendance Site Visit Agenda.pdf PDF
Floor plan - Bldg. 101.pdf PDF
Lighting plan - 101.pdf PDF
Electrical Plan - Bldg. 101.pdf PDF
Demolition Plan - 101.pdf PDF
Electrical Demolition Plan - 101.pdf PDF
W50S8S23B0001 0001 Amendment.pdf PDF
Reflected ceiling plan - 101.pdf PDF
PWS WYTD232003 Const walls 150 Rev 1.docx DOCX document
Existing lighting plan - 150.pdf PDF
W50S8S23B0001 Construct Wall.pdf PDF
Bldg-150 Partial Floor Plan.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT (PWS)

FOR

WYTD232003: CONSTRUCT WALLS – Buildings 150 & 101

1.0 General:

1.1 Scope: The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary, except as specified in Paragraph 3.0 as Government Furnished, to construct a wall and perform interior renovations as defined in this PWS.

1.1.1 Objectives: Construct a drywall partition and modify existing finishes & MEP systems creating an office space for the 180th FW Contracting Office.

1.2 Background: The contracting office requires a space separated from other base functions to perform their duties.

1.3 Period of Performance (PoP): The Period of Performance shall be 60 days after issuance of the notice to proceed.

1.4 General Information:

1.4.1 Place and Performance of Services: The contractor shall provide services between the hours of 0700 - 1600 on Monday through Friday except on recognized US holidays or when the Government facility/installation is closed due to local or national emergencies, administrative closings, or similar Government-directed facility/installation closings. Performance shall be at Aircraft Parking Apron of the 180th Fighter Wing, 2660 S. Eber Rd., Swanton, OH 43558. The contractor shall at all times maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS when the Government facility/installation is not closed for the above reasons. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential.

1.4.1.1 Telework: Not Applicable.

1.4.1.2 Unscheduled gate closures by the Security Police may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented. Contractors are not compensated for unexpected closures or delays. Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.

1.4.1.3 The contractor’s employees shall become familiar with and obey the regulations of the installation; including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All contractor employees shall carry proper identification with them at all times and shall be subject to such checks as may be deemed necessary. The contractor shall ensure compliance with all regulations and orders of the installation, which may affect performance. The Government reserves the right to direct the removal of an employee from Government property or revoke access to Government systems for misconduct, security reasons, or any overt evidence of communicable disease. Removal of contractor employees for reasons stated above does not relieve the Contractor from responsibility for total performance of this contract.

1.4.2 Recognized Holidays: The following are recognized United States (US) holidays. The contractor shall not perform services on these days unless otherwise approved in advance by the COR and the contracting officer. Requests to work holidays shall be made a minimum of 3 working days prior to the requested day(s).

1.4.2.1 New Year’s Day: January 1st

1.4.2.2 Martin Luther King, Jr.’s Birthday

1.4.2.3 President’s Day

1.4.2.4 Memorial Day

1.4.2.5 Juneteenth National Independence Day: June 19th

1.4.2.6 Independence Day: July 4th

1.4.2.7 Labor Day

1.4.2.8 Columbus Day

1.4.2.9 Veteran’s Day: November 11th

1.4.2.10 Thanksgiving Day

1.4.2.11 Christmas Day: December 25th

1.4.3 Quality Control (QC): The contractor shall develop and maintain an effective QC Plan (QCP) to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s QCP is the means by which it assures itself that its work complies with the requirements of the contract. As a minimum, the contractor shall develop QC procedures that address the areas identified in Technical Exhibit 1, Performance Requirements Summary (PRS).

1.4.4 Quality Assurance (QA): The Government will evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government will do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and acceptable quality level(s) or defect rate(s).

1.4.5 Access and General Protection/Security Policy and Procedures. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, Headquarters Air Force (HAF) and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

1. The contractor shall obtain base identification and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished, contractor identification badges while visiting or performing work on the installation.

2. The contractor shall submit a written request on company letterhead to the contracting officer listing the following: contract number, location of work site, start and stop dates, and names of employees and subcontractor employees needing access to the base. The letter will also specify the individual(s) authorized to sign for a request for base identification credentials or vehicle passes. The contracting officer will endorse the request and forward it to the issuing base pass and registration office or Security Forces for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver s license, current vehicle registration, valid vehicle insurance certificate, and [insert any additional requirements to comply with local security procedures] to obtain a vehicle pass.

3. During performance of the contract, the contractor shall be responsible for obtaining required identification for newly assigned personnel and for prompt return of credentials and vehicle passes for any employee who no longer requires access to the work site.

4. Reserved.

5. Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.

6. Failure to comply with these requirements may result in withholding of final payment.

1.4.5.1. For Contractors Requiring Common Access Card (CAC). Not Required.

1.4.5.2 For Contractors that do not require CAC but require access to a DoD Facility and/or Installation. Contractor and all associated sub-contractor’s employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Air Force Instruction (AFI) 10-245, AFI 31-101 and Air Force Manual (AFMAN) 31-113), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by Government representative)

1.4.5.3 Antiterrorism Awareness Level I Training (AT Level I). All contractor employees, to include subcontractor employees, requiring access to US Government installations, facilities and controlled access areas shall complete AT Level I training within 15 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. AT Level I may be accomplished by a Level I qualified instructor, completing the Force Protection computer-based training (CBT) course on the Advanced Distributed Learning System (ADLS) or Joint Knowledge Online at http://jko.jten.mil. Tracking for each contractor or subcontractor employee is the responsibility of unit AT Representative. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee to the COR within 15 calendar days after completion of training by each employee or subcontractor personnel.

1.4.5.4 Reserved.

1.4.5.5 Communications Security/Information Technology (COMSEC/IT) Security. All communications with DoD organizations are subject to COMSEC review. All telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. DoD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DoD organizations. Therefore, the contractor is advised that any time contractor personnel place or receive a call they are subject to COMSEC procedures. The contractor shall ensure wide and frequent dissemination of the above information to all employees dealing with DoD information. The contractor shall abide by all Government regulations concerning the authorized use of the Government's computer network, including the restriction against using the network to recruit Government personnel or advertise job openings.

1.4.5.6 Reserved

1.4.5.7 Reserved.

1.4.5.8 Reserved

1.4.5.9 Reserved

1.4.5.10 Reserved

1.4.5.11 Requirement for OPSEC Training. In accordance with AFI 10-701, Operations Security, OPSEC PMs/Signature Managers/Coordinators will provide OPSEC training or training materials to contract employees within 30 days of employees’ initial assignment to the contract and prior to having access to any critical information (CI) and annually thereafter. General organizational orientations may need to be supplemented by duty-related orientations in the work center targeted toward specific critical information and vulnerabilities associated with the work. Initial training (OPSE 1301 - OPSEC Fundamentals) is located on the ADLS website and refresher OPSEC training is conducted annually (at Commander's Call). The contractor shall submit certificates of completion for each contractor employee to the COR within 15 calendar days after completion of training.

1.4.5.12 OPSEC Plan. Not Required.

1.4.5.13 Contracts that require Handling or Access to Classified Information: Not Required.

1.4.6 Physical Security. The contractor shall safeguard all Government property provided for contractor use. At the close of each work period, Government facilities, equipment and materials shall be secured.

1.4.6.1 Key Control: Not Required

1.4.7 Special Qualifications: Reserved.

1.4.8 Post Award Conference/Periodic Progress Meetings: The contractor agrees to attend any post award conference convened by the KO in accordance with FAR 42.5. The KO, COR and other Government personnel, as appropriate, may meet periodically with the contractor to review the contactor’s performance. At these meetings, the KO will apprise the contractor of how the Government views the contractor’s performance and the contractor shall apprise the Government of problems, if any, being experienced. The contractor shall resolve outstanding issues raised by the Government. Contractor attendance at these meetings shall be at no additional cost to the Government.

1.4.9 Contract Manager (CM): The contactor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO. The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the COR to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.

1.4.10 Identification of Contractor Employees: All contractor personnel attending meetings, answering Government telephones and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government employees. The contractor shall ensure that all documents or reports produced by contractor personnel are suitably marked as contractor products or that contractor participation is appropriately disclosed. The contractor’s status as a “contractor” shall be predominantly displayed in all correspondence types (to include signature blocks on e-mail) and dealings with Government or non-Government entities. Contractor personnel shall wear identification badges distinguishing themselves as such. The badges shall have the company name, employee name and the word “contractor” displayed.

1.4.10.1 The contractor shall retrieve all identification media (including vehicle passes) from its employees who depart employment for any reason. The contractor shall return all identification media (i.e., badges and vehicles passes) to the KO within 14 days of an employee’s departure.

1.4.11. Combating Trafficking in Persons: The United States Government has adopted a zero tolerance policy regarding trafficking in persons. Contractors and contractor employees shall not engage in severe forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. The contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at FAR 22.17.

1.4.12 Contractor Travel: Not Applicable

1.4.13 Data Rights: Not Applicable

1.4.14 Organizational Conflicts of Interest (OCI): The contractor and subcontractor personnel performing services under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent OCIs, as defined in FAR Subpart 9.5. The contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO. In the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may impose other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.

1.4.15 Phase In / Phase Out Periods: Not Applicable

2.0 Definitions and Acronyms:

2.1 Definitions:

2.1.1 Contractor: A supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.

2.1.2 Defective Service: A service output that does not meet the standard of performance associated with the PWS.

2.1.3 Deliverable: Anything that can be physically delivered and includes non-manufactured things such as meeting minutes or reports.

2.1.4 Key Personnel: Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.5 Physical Security: Actions that prevent the loss or damage of Government property.

2.1.6 Quality Assurance: The Government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

2.1.7 Quality Assurance Surveillance Plan (QASP): An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

2.1.8 Quality Control: All necessary measures taken by the Contractor to ensure that the quality of an end product or service shall meet contract requirements.

2.1.9 Subcontractor: One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

2.2 Acronyms:

AEIArmy Enterprise Infostructure
ARArmy Regulation
AT/OPSECAntiterrorism/Operational Security
BIBackground Investigation
CMContract Manager
CORContracting Officer Representative
DADepartment of the Army
DD254Department of Defense Contract Security Classification Specification
DFARSDefense Federal Acquisition Regulation Supplement
DoDDepartment of Defense
DSCADefense Counterintelligence and Security Agency
FARFederal Acquisition Regulation
GFP/M/E/SGovernment Furnished Property/Material/Equipment/Services
HQDAHeadquarters, Department of the Army
HSPDHomeland Security Presidential Directive
IAInformation Assurance
ISInformation System(s)
KOContracting Officer
NGBNational Guard Bureau
OCIOrganizational Conflict of Interest
PIIPersonally Identifiable Information
PIPOPhase In/Phase Out
POCPoint of Contact
PRSPerformance Requirements Summary
PWSPerformance Work Statement
QAQuality Assurance
QASPQuality Assurance Surveillance Plan
QCQuality Control
QCPQuality Control Program
SCRService Contract Reporting
SSNSocial Security Number
TETechnical Exhibit
USD(I)Under Secretary of Defense for Intelligence

3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S): The Government will provide the property, material, equipment, and/or services listed below solely for the purpose of performance under this contract:

3.1 Property: None

3.2 Materials: 4 LED recessed troffer light fixtures.

3.3 Equipment: None

3.4 Services: None

3.5 Utilities: All utilities in the facility will be available for the contactor’s use in the performance of this contract. The contractor shall instruct employees in utilities conservation practices. The contractor shall operate under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount.

4.0 Contractor Furnished Property, Materials, and Equipment (CFP/M/E): RESERVED

5.0 Requirements: The contractor shall furnish all supervision, labor, materials, equipment, and supplies and other items of expense required to perform the work specified in this document in strict accordance with the specifications and drawings for this project and provide the government a complete and useable end product. This project will bid in 2 CLINs. The first CLIN will be for the work in building 150 (Paragraphs 5.1 through 5.9.6 and associated drawings). The second CLIN is work in building 101 (Paragraphs 5.10 through 5.17 and the associated drawings).

5.1 Construct wall and perform interior renovations at building 150 (Civil Engineering) as described below and as shown on the drawings in Room 118 (CLIN 1).

5.1.1 The following drawings are attached:

Existing Lighting Plan – 150 Bldg. 150 Partial Floor Plan

5.2 Submittals: Submit technical data, catalog cut sheets, samples, test reports or other items as listed below:

5.2.1 180th FW Solid Waste Disposal and Tracking Form.

5.2.2 180th FW Ozone Depleting Substances Form for all material & equipment containing refrigerants – Not applicable for this project.

5.2.3 As-built drawings – Not applicable for this project.

5.2.4 Operations and maintenance manuals, and operating instructions for all installed material and equipment – Door hardware

5.2.5 Schedule and schedule of values

5.2.6 Submittals shall be provided with an AF Form 3000 filled out and signed by the contractor certifying the material is in compliance with the project requirements.

5.3 General:

5.3.1 Portable Toilet: Provide a portable toilet for use of contractor personnel. Not applicable for this project

5.3.2 Provide lighted barricades around perimeter of demolished pavements, sidewalks and excavations until the new concrete is properly cured.

5.3.3 The work area shall be kept clean on a continual basis to prevent items from becoming FOD. Ensure all construction debris is properly contained in dumpsters, cans, etc. and covered until removed from base.

5.3.4 The contractor shall remove and properly dispose of all demolished materials and construction debris from installation.

5.3.5 The contractor shall verify existing dimensions and conditions prior to submitting a bid and again prior to beginning work.

5.3.6 The contractor shall provide the government project manager or COR 7 days written notice before performing any disturbance of the ground to a depth below 3”. The notice shall include a drawing of the area where the work is to be done. Mark the work area and proposed excavations with white flags or marking paint if required by the government, so existing utilities can be properly identified before beginning any demolition or excavation. Contractor shall ensure an approved Air Force Form 103 Work Clearance is issued before beginning any excavations.

5.3.7 Provide a minimum of 7 days advance notice in writing to the Contracting Officer or COR prior to the shutdown of any building utility system, street or parking lot.

5.3.8 The contractor shall insure that all work complies with all federal state and local laws and ordinances applicable to the construction of this project. Install all equipment according to the manufacturer’s written instructions. If a conflict is found, notify the Contracting Officer for resolution of the conflict prior to proceeding.

5.3.9 Prior to performing any operation requiring use of an open flame, or spark producing work obtain a burn permit from the base fire department (419-868-4116). The contractor shall provide and maintain fire extinguishers and other safety equipment at the job site at all times as required to perform the work.

5.3.10 Provide dust partitions as needed to minimalize dust and debris from migrating to other occupied portions of the facility.

5.4 Demolition:

5.4.1 Base personnel shall remove the existing system furniture from the project area and store outside of the work area.

5.4.2 The contractor shall perform all miscellaneous demolition as required to construct the new wall, door, finishes and perform the electrical & HVAC work shown on the drawings.

5.4.3 Carpet and cove base to remain on existing walls except where needed to construct the new walls.

5.4.4 Remove ceiling tiles and grid as needed to construct the new wall. Remove all ceiling tiles inside the new room. These tiles may be used to repair and replace the ceiling the tiles outside of the new office area. Dispose of excess tiles. Rework the existing ceiling grid as needed and repair to match the existing ceiling layout.

5.4.5 Remove 4 lights from the new office area. Wiring to remain for new lights but they will be rewired to be controlled by a new switch inside the office.

5.4.6 Relocate 2 existing lights near the proposed new east wall to the adjacent hallway area. Extend wiring as needed. These lights shall remain on the existing circuit and 3-way switch.

5.4.7 HVAC: Relocate one return air grille and supply diffuser to new location shown on the drawings. Modify ceiling grid as needed to accommodate the HVAC items.

5.5 Doors, Frames and Hardware:

5.5.1 Provide a new 3070 solid core wood door with narrow lite glass. Door shall be 1-3/4” thick and match existing finish as adjacent doors.

5.5.2 Provide a new 16-gauge hollow metal frame for the new door as indicated on the drawing. Frame shall be reinforced for door hardware. Provide door silencers with frame.

5.5.3 Provide door hardware as follows:

5.5.3.1 Medium duty hinges with ball bearings, 4.5” x 4.5”

5.5.3.2 Cylindrical Lockset – Office function, Lockset shall be able to accept a Schlage Primus full size interchangeable core. The government shall provide the core and keys. The contractor shall furnish the appropriate tail piece to work with the Schlage core.

5.5.3.3 Dome stile, floor mounted door stop.

5.5.3.4 Hardware shall match existing satin chrome finish.

5.6 Walls

5.6.1 Provide 3-5/8” wide, 25-gauge metal studs at 16” on center from floor to roof deck above unless noted otherwise.

5.6.2 Insulation to 10’ above finished floor. Provide 3.5” thick unfaced fiberglass batts.

5.6.3 Provide 5/8” drywall on each side of framing to 10’ above finished floor. Tape and finish drywall to a Level 4 finish ready to accept paint to 10’. Finish drywall where new walls intersect existing wall surfaces to blend as if original construction.

5.6.4 Paint new and existing walls where indicated. Provide one coat of latex acrylic primer and 2 finish coats of latex acrylic paint. Color to match existing walls (SW 7647 Crushed Ice).

5.6.5 Paint to match existing door frames in the building (SW 1034 Dolphin).

5.6.5 Provide 4” cove base on new walls (both sides) and existing walls if removed. Color, height and thickness to match existing.

5.7 Ceiling:

5.7.1 Repair/replace ceiling grid at new wall to match existing.

5.7.2 Provide new ceiling tiles inside of the new office area. Match or approximate the existing color and finish.

5.7.3 Reinstall or replace ceiling tiles outside of the new walls to match existing.

5.8 HVAC: Relocate HVAC items as shown on the drawings. Extend ductwork if necessary to move the location shown.

5.9 Electrical:

5.9.1 Install new receptacles as indicated on the drawings. Reuse existing circuits from the existing system furniture feed to power new receptacles. The feed for these circuits is panel EM-2, circuits 31, 33 & 35. Connect the new receptacles equally across all three phases to evenly split the electrical load.

5.9.2 Relocate two existing lights to outside of the new office. Circuit and switching for these lights to remain.

5.9.3 Install 4 new Government Provided Lights LED 2’ x 4’ troffers with acrylic lens in the new office as shown on the drawings. Disconnect these lights from the existing 3-way switches. Provide a new single pole switch to control these lights. These lights are powered from panel EM-2 circuit 1.

5.9.4 Install a ¾” EMT conduit from 12” above new ceiling down to a new 4” x 4” x 2” deep box for a future 4 jack computer/telephone outlet where indicated. Provide pull string in conduit. Flexible conduit may be used where installed in existing walls.

5.9.5 Conduit for all electrical feeds will be EMT or IMC in new walls. Flexible conduit may be used in existing walls.

5.9.6 All work shall be in accordance with the most recent version of the National Electrical Code.

5.10 Construct a wall and perform interior renovations as described below and as shown on the drawings for building 101, rooms 109 and 111 (CLIN 2).

5.11 The following drawings apply to the work at building 101:

Demolition Plan – 101 Floor Plan – Bldg. 101 Existing Reflected Ceiling Plan - 101 Electrical Demolition Plan – 101 Electrical Plan – Bldg. 101 Lighting Plan - 101

5.12 Construct drywall partition walls as outlined in paragraph 5.6 above. The wall at building 101 shall not be insulated.

5.12.1 Match existing colors for walls (SW1002, Big Chill), doors/frames (SW1005, Silverado) and cove base (Johnsonite No. DC-48, Grey).

5.13 Door, Frame and Hardware:

5.13.1 Provide a new 3070 hollow metal door with narrow lite glass. Door shall be 18-gauge steel, 1/3/4” thick and match existing finish as adjacent doors. Glass shall be ¼” safety glass.

5.13.2 Provide a new 16-gauge hollow metal frame for the new door where indicated on the drawing. Frame shall be reinforced for door hardware. Provide door silencers with frame.

5.13.3 Provide blocking in new wall for ground bus bar. Coordinate with the electrical contractor for requirements.

5.13.4 Provide door hardware as follows:

5.13.4.1 Medium duty hinges with ball bearings, 4.5” x 4.5”

5.13.4.2 Passage set, cylindrical

5.13.4.3 Door closer, medium duty

5.13.4.4 Floor mounted door stop, dome style

5.13.4.5 Hardware shall match existing style and finish.

5.14 Repair/replace ceiling grid where the old wall was removed and on each side of the new wall. Provide new tegular edge ceiling tiles in the area around the old and new walls to complete the ceiling. Match existing style, color and texture. Ceiling tiles not affected by construction shall remain.

5.15 Electrical:

5.15.1 All work shall be in accordance with the most recent version of the National Electrical Code.

5.15.2 Remove ground bus bar, ground cable reel, and static ground touch pad and reinstall extending to the new wall. Provide new fasteners, and other miscellaneous materials if damaged during removal. The government has additional pieces of bus bar and standoff insulators if needed. Coordinate blocking in walls for ground bar and touch pad with the General Contractor.

5.15.3 Remove and replace receptacles (or reinstall existing) where shown on the drawings. Provide new conduit, wire, boxes and accessories as needed to install the receptacles.

5.15.4 Remove existing communications outlets as shown on the drawings.

5.15.5 Provide new boxes and conduits for future outlets as shown on the drawings. Provide pull strings in all empty conduits.

5.15.6 Perform all demolition and removals as shown on the drawing and as needed to facilitate the work. Where patching of finish materials is required due to demolition, repairs shall be made and finished to match existing construction in color and texture.

5.16 Provide submittals outlined in paragraph 5.2 if applicable.

5.17 Follow general conditions outlined in paragraph 5.3.

5.x Service Contract Reporting: Reserved for projects over $3 million.

6.0 Applicable Publications: Publications applicable to this PWS are listed below:

Publication (Chapter/Page)

Date of Publication
Mandatory or Advisory
Website

Federal Acquisition Regulation

Advisory
https://www.acquisition.gov/?q=browsefar

Defense Federal Acquisition Regulation Supplement

Advisory
http://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html or https://www.acquisition.gov/dfars

Joint Travel Regulation (JTR)

Advisory
https://www.defensetravel.dod.mil/site/travelreg.cfm

DoDM 1000.13-M-V1 DoD Identification (ID) Cards (Enclosure 2, paragraph 3.b) 01/23/2014 (Change 1: 07/28/2020)

Advisory
http://www.esd.whs.mil/Directives/issuances/dodm

Federal Information Processing Standards (FIPS) Publication 201-2 Personal Identity Verification (PIV) of Federal Employees and Contractors (paragraph 9)

August 2013
Advisory
http://nvlpubs.nist.gov/nistpubs/FIPS/NIST.FIPS.201-2.pdf
DoDM 5200.2 Procedures for the DoD Personnel Security Program (PSP)
04/03/2017
Advisory
https://www.esd.whs.mil/Directives/issuances/dodm/

DoDI 5200.46 DoD Investigative and Adjudicative Guidance for Issuing the Common Access Card (CAC) 09/09/14 (Change 1: 05/04/2018)

Advisory
https://www.esd.whs.mil/Directives/issuances/dodi/

Homeland Security Presidential Directive (HSPD)-12 Policy for a Common Identification Standard for Federal Employees and Contractors

08/27/2004
Advisory
https://www.dhs.gov/homeland-security-presidential-directive-12

DoDI 5400.11 Department of Defense Privacy and Civil Liberties Programs 01/29/2019

Advisory
https://www.esd.whs.mil/Directives/issuances/dodi/

DoD 5400.11-R Department of Defense Privacy Program

05/14/2007
Advisory
https://www.esd.whs.mil/Directives/issuances/dodm/

DoDD 8140.01 Cyberspace Workforce Management

10/05/2020

Advisory
https://www.esd.whs.mil/Directives/issuances/dodd/

DoD 8570.01-M Information Assurance Workforce Improvement Program

12/19/2005 (Change 4: 11/10/2015)
Advisory
https://www.esd.whs.mil/Directives/issuances/dodm/

DoD 5220.22-M National Industrial Security Program Operating Manual (NISPOM) 02/28/2006 (Change 2: 05/18/2016)

Advisory
https://www.esd.whs.mil/Directives/issuances/dodm/

AFI 10-245

Antiterrorism 03/28/2013 (Certified current 03/30/2017)

Advisory
https://www.e-publishing.af.mil/Product-Index/#/?view=pubs&orgID=10141&catID=1&series=-1&modID=449&tabID=131

AFI 31-101

Security Forces Standards and Procedures

08/18/2020
Advisory
https://www.e-publishing.af.mil/Product-Index/#/?view=pubs&orgID=10141&catID=1&series=-1&modID=449&tabID=131

AFMAN 31-113

Security Forces Standards and Procedures 03/05/2013 Change 1:

12/02/2015

Advisory
https://www.e-publishing.af.mil/Product-Index/#/?view=pubs&orgID=10141&catID=1&series=-1&modID=449&tabID=131

AFPD 17-1

Information Dominance Governance and Management

04/12/2016
Advisory
https://www.e-publishing.af.mil/Product-Index/#/?view=pubs&orgID=10141&catID=1&series=-1&modID=449&tabID=131

AFMAN 17-1301

Computer Security (COMPUSEC)

02/12/2020
Advisory
https://www.e-publishing.af.mil/Product-Index/#/?view=pubs&orgID=10141&catID=1&series=-1&modID=449&tabID=131

AFI 10-701

Operations Security 7/24/2019 (Change 1:

06/09/2020)

Advisory
https://www.e-publishing.af.mil/Product-Index/#/?view=pubs&orgID=10141&catID=1&series=-1&modID=449&tabID=131

6.1 Applicable Forms: Forms applicable to the PWS are listed below:

Form
Date
Website

DD 1172-2

Application for Identification Card/DEERS Enrollment

Mar 2017
http://www.dtic.mil/whs/directives/forms/index.htm

I-9 Employment Eligibility Verification 10/21/2019 https://www.uscis.gov/sites/default/files/files/form/i-9.pdf

DD 441

Department of Defense Security Agreement Feb 2020 http://www.dtic.mil/whs/directives/forms/dd/ddforms0001-0499.htm

DD 250

Material Inspection and Receiving Report

Aug 2000
https://www.esd.whs.mil/Directives/forms/dd0001_0499/
AF Form 3000 Material Approval Submittal
Most recent version

TECHNICAL EXHIBIT 1

Performance Requirements Summary (PRS) This PRS includes performance objectives the Government will use to determine contractor performance and will compare contractor performance to the Acceptable Quality Level (AQL).

Performance Objective
Performance Standard
Acceptable Quality Levels (AQL)
Surveillance Method / By Whom

Para. 5.0, Construct a wall and office space Construct a wall and office space as outlined in para. 5.0 and as shown on the drawings.

Construction must meet the requirements of this PWS and all federal codes and regulations.
On-site inspection by the COR/Project Manager

TECHNICAL EXHIBIT 2

Deliverables Schedule

PWS Reference / Deliverable Title
Frequency
Number of Copies
Medium/Format
Submit To

Para. 5.0.

Construct Wall and office renovations

Once, at completion of project
0
Construct project on site
COR
1.4.5.3 AT Level 1 Awareness Training Certificates
Provide within 15 calendar days after employee completes training.
1
Electronic Submission
COR

1.4.5.11 OPSEC

Training Certificates

Provide within 15 calendar days after employee completes training.
1
Electronic Submission
COR
1.4.10 Identification Media
Return within 14 days of employee’s departure from contract performance.
Original(s)
Hard Copy
KO

Ver. October 2022

File details come from the government source that posted it. Updated .