About this file

This document contains a request for information response and related federal contract opportunity solicitation. The request for information response clarifies that a standard government specification will be used for the plumbing system on the project, with PVC allowed above ground for drain, waste, and vent lines but cast iron or steel required underground.

The federal contract opportunity is solicitation number W50S8R-21-B-0001 for the ADD/ALTER B403 CC project at Mansfield Air National Guard Base. The project scope includes renovation and new construction/addition to the B403 Corrosion Control facility. The construction/contract duration is estimated at 300 calendar days with a bid opening date of December 7, 2020. The solicitation is set aside for small businesses with a NAICS code of 236220 and magnitude between $1,000,000 to $5,000,000. Additive bid items are included for additional scope. The pre-bid conference is scheduled for November 5, 2020 and the solicitation and plans are available on beta.SAM.gov.

View the file

Other files for this federal contract opportunity

Other files attached to ADD/ALTER B403 CC, newest first.
File Type Posted
Bid opening attendance sheet_B403.pdf PDF
Abstract_B403.pdf PDF
W508SR-21-B-0001 P00002.pdf PDF
RFI 27 response.pdf PDF
RFI 30 response.pdf PDF
RFI 29b response.pdf PDF
RFI 24 response.pdf PDF
RFI 11 attachment.pdf PDF
RFI 11 response.pdf PDF
RFI 32 response.pdf PDF
RFI 36 response.pdf PDF
RFI 35 response.pdf PDF
RFI 29a response.pdf PDF
RFI 22 response.pdf PDF
RFI 26 response.pdf PDF
RFI 23 response.pdf PDF
RFI 19 response.pdf PDF
RFI 10 response.pdf PDF
RFI 18 response.pdf PDF
RFI 28 response.pdf PDF
RFI 20 response.pdf PDF
RFI 17 response.pdf PDF
RFI 16 response.pdf PDF
RFI 03 response.pdf PDF
RFI 014 response.pdf PDF
RFI 12 response.pdf PDF
RFI 09 response.pdf PDF
RFI 21 response.pdf PDF
RFI 15 response.pdf PDF
Exhibit A_Sealed Bid Checklist Reminders.rev01.pdf PDF
RFI 07 response.pdf PDF
RFI 13 response.pdf PDF
RFI 06 response.pdf PDF
RFI 08 response.pdf PDF
RFI 05 response.pdf PDF
RFI 01 response.pdf PDF
Pre-Bid Conference-slides.pptx PPTX presentation
RFI 02 response.pdf PDF
Attendance sheet.pdf PDF
RFI 04 response.pdf PDF
Pre-Bid Conference minutes_B403.pdf PDF
Attachment5_VOL 5_Specs (23-33).pdf PDF
Exhibit A_Sealed Bid Checklist Reminders.pdf PDF
Attachment7_RFI template.doc DOC document
Attachment4_VOL 4_Specs (6-22).pdf PDF
Attachment3_VOL 3_Specs (1-5).pdf PDF
Attachment1_VOL 1_BoD.pdf PDF
Attachment2_VOL 2_Drawings.pdf PDF
Attachment6_Web Based Management Software.docx DOCX document
W50S8R-21-B-0001.pdf PDF
Show all 50

ADD/ALTER B403 CC has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR INFORMATION

R E

Q U

E S

T O

R S

E C

T

IO

N

From:

Date:

11/25/20

To: Contracting Officer

1. Solicitation Number:

W50S8R-21-B-0001

2. Location of Project:

Building 403

3. Information Requested: (Include Specification Section and/or Drawing Number and Page if inquiring about a discrepancy)

Table 1 within plumbing specification 22 00 00 shows PVC can be used above ground for DWV, but not underground. Cast iron or steel pipe must be used underground. This is a little backwards from normal construction. Please confirm.

Attachments:

Date Response Required:

By:

Title:

Requestor's FAX Number:

Requestor's Telephone Number:

C E

R E

S P

O N

S E

To:

Date:

Response:

This is a standard government spec, used on many projects. A/E does not see a reason to deviate.

This information is a clarification of the solicitation/contract and does not change the contract terms or conditions.

This information is a proposed change to the solicitation/contract. An amendment will be issued.

Contracting Officer: