RFI 23 response.pdf
PDF 73 KB Posted
- Attached to
- ADD/ALTER B403 CC Federal contract opportunity
- Solicitation number
- W50S8R-21-B-0001
About this file
This document contains a federal contract solicitation and a related request for information response. The solicitation is for construction services to renovate and add onto Building 403 at Mansfield Air National Guard Base in Ohio for corrosion control. Services required include interior and exterior demolition, new sidewalks and drive access, antiterrorism force protection doors and windows, a sprinkler system, compressed air lines and air handling equipment, electrical upgrades, and a new wireless network. The estimated construction duration is 300 calendar days with a bid opening date of December 7, 2020. Additive bid items are included for additional work areas, an air shower, and a motorized overhead door. The solicitation is set aside for small businesses with a magnitude between $1 million and $5 million. The request for information response clarifies that exterior walls will have R-19 minimum insulation and there is no interior insulation specified on the wall sections in the solicitation documents.
View the file
Other files for this federal contract opportunity
Show all 50
ADD/ALTER B403 CC has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR INFORMATION
R E
Q U
E S
T O
R S
E C
T
IO
N
From:
Date:
11/23/2020
To: Contracting Officer
1. Solicitation Number:
W50S8R-21-B-0001
2. Location of Project:
Building 403
3. Information Requested: (Include Specification Section and/or Drawing Number and Page if inquiring about a discrepancy)
Please provide R-value and thickness for rigid insulation on interior side of exterior walls per wall sections shown on A-302 and A-303.
Attachments:
Date Response Required:
By:
Title:
Requestor's FAX Number:
Requestor's Telephone Number:
C E
R E
S P
O N
S E
To:
Date:
11/25/2020
Response:
Sections show exterior insulated metal panel, R-19 minimum. There is no insulation on the interior side of the exterior walls shown.
This information is a clarification of the solicitation/contract and does not change the contract terms or conditions.
This information is a proposed change to the solicitation/contract. An amendment will be issued.