This solicitation notice seeks proposals for construction services for the Add/Alter B403 Corrosion Control project at Mansfield Air National Guard Base in Mansfield, Ohio. The scope of work includes interior and exterior demolition, construction of new sidewalks and drive access, installation of ATFP-compliant doors, windows and walls, a new sprinkler system, compressed air lines, air handling equipment, stratification fans and ductwork, electrical upgrades, and a new WLAN infrastructure and intercom system. The construction duration is estimated at 300 calendar days with adequate time for punch list completion and final inspection. Additive bid items include additional corrosion work areas, an air shower, motorized overhead door, and blast resistant windows. Proposals are due by December 7, 2020 and the project is set aside for small businesses with a size standard of $39.5 million in average annual revenue for the previous three years. The pre-bid conference is scheduled for November 5, 2020 and the solicitation is available through the Contract Opportunities section of beta.SAM.gov.
View the file
Other files for this federal contract opportunity
Show all 50
ADD/ALTER B403 CC has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
T Y P E B - 3 F I N A L
Add/Alter Building 403 Project Number PBXP169102
Volume 5 - Specifications Division 23-33
Prepared for
179th Civil Engineering Squadron Ohio Air National Guard
Mansfield Lahm ANG Base
May 2020
CH2M HILL – HDR JV
241 Taylor Street, Suite 100
Dayton, Ohio, 45402
ADD/ALTER B403 FOR CORROSION CONTROL
MANSFIELD LAHM ANG BASE, OH
PROJECT TABLE OF CONTENTS
VOLUME
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 33 29 SUSTAINABILITY REPORTING
01 35 13 SPECIAL PROJECT PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 45 00.00 10 QUALITY CONTROL
01 45 35 SPECIAL INSPECTIONS
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 PROJECT IDENTIFICATION
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
DIVISION 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION 04 - MASONRY
04 20 00 UNIT MASONRY
DIVISION 05 - METALS
05 12 00 STRUCTURAL STEEL
05 21 00 STEEL JOIST FRAMING
05 30 00 STEEL DECKS
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 51 33 METAL LADDERS
VOLUME
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 11 13 BITUMINOUS DAMPPROOFING
07 21 13 BOARD AND BLOCK INSULATION
07 22 00 ROOF AND DECK INSULATION
PROJECT TABLE OF CONTENTS Page 1
PW\DEN003\708540
07 42 13 METAL WALL PANELS
07 60 00 FLASHING AND SHEET METAL
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 31 00
08 51 13
08 71 00 08 81 00
08 91 00
ALUMINUM WINDOWS
DOOR HARDWARE
GLAZING
METAL WALL LOUVERS
DIVISION 09 - FINISHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 30 10 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 ACOUSTICAL CEILINGS
09 90 00 PAINTS AND COATINGS
09 96 00 HIGH-PERFORMANCE COATINGS
DIVISION 10 - SPECIALTIES
10 21 13 TOILET COMPARTMENTS
10 28 13 TOILET ACCESSORIES
10 44 16 FIRE EXTINGUISHERS
10 51 13 METAL LOCKERS
DIVISION 21 - FIRE SUPPRESSION
21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
22 60 70 GAS AND VACUUM SYSTEMS FOR HEALTHCARE FACILITIES
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 09 33.00 40 ELECTRIC AND ELECTRONIC CONTROL SYSTEM FOR HVAC
23 11 25 FACILITY GAS PIPING
23 23 00 REFRIGERANT PIPING
23 81 00 DECENTRALIZED UNITARY HVAC EQUIPMENT
PROJECT TABLE OF CONTENTS Page 2
PW\DEN003\708540
08 36 13
ACCESS DOORS AND PANELS
OVERHEAD COILING DOORS
SECTIONAL OVERHEAD DOORS
09 65 00 RESILIENT FLOORING
VOLUME 5
08 33 23
DIVISION 26 - ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 41 00 LIGHTNING PROTECTION SYSTEM
26 51 00 26 56 00
INTERIOR LIGHTING
EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
27 51 16 RADIO AND PUBLIC ADDRESS SYSTEMS
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 64.00 10 FIRE DETECTION AND ALARM SYSTEM, ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 05 19 GEOTEXTILE
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 05 33 LANDSCAPE ESTABLISHMENT
32 11 23 AGGREGATE BASE COURSES
32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 92 23 SODDING
DIVISION 33 - UTILITIES
33 11 00 WATER UTILITY DISTRIBUTION PIPING
33 11 23 NATURAL GAS AND LIQUID PETROLEUM PIPING
33 30 00 SANITARY SEWERAGE
33 40 00 STORM DRAINAGE UTILITIES
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 3
26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION
SECTION 23 00 00 Page 1 May 2020
SECTION 23 00 00
AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
08/18
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AIR MOVEMENT AND CONTROL ASSOCIATION INTERNATIONAL, INC. (AMCA)
AMCA 201 (2002; R 2011) Fans and Systems
AMCA 210 (2016) Laboratory Methods of Testing Fans for Aerodynamic Performance Rating
AMCA 300 (2014) Reverberant Room Method for Sound Testing of Fans
AMCA 301 (2014) Methods for Calculating Fan Sound
Ratings from Laboratory Test Data
AMCA 500-D (2018) Laboratory Methods of Testing Dampers for Rating
AMERICAN BEARING MANUFACTURERS ASSOCIATION (ABMA)
ABMA 9 (2015) Load Ratings and Fatigue Life for
Ball Bearings
ABMA 11 (2014) Load Ratings and Fatigue Life for Roller Bearings
AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING
ENGINEERS (ASHRAE)
ASHRAE 52.2 (2012) Method of Testing General
Ventilation Air-Cleaning Devices for Removal Efficiency by Particle Size
ASHRAE 62.1 (2010) Ventilation for Acceptable Indoor Air Quality
ASHRAE 70 (2006; R 2011) Method of Testing for Rating the Performance of Air Outlets and Inlets
ASME INTERNATIONAL (ASME)
ASME A13.1 (2015) Scheme for the Identification of Piping Systems
SECTION 23 00 00 Page 2 May 2020
ASTM INTERNATIONAL (ASTM)
ASTM A53/A53M (2018) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless
ASTM A123/A123M (2017) Standard Specification for Zinc
(Hot-Dip Galvanized) Coatings on Iron and Steel Products
ASTM A167 (2011) Standard Specification for
Stainless and Heat-Resisting Chromium-Nickel Steel Plate, Sheet, and Strip
ASTM A924/A924M (2018) Standard Specification for General
Requirements for Steel Sheet, Metallic-Coated by the Hot-Dip Process
ASTM B117 (2016) Standard Practice for Operating
Salt Spray (Fog) Apparatus
ASTM B152/B152M (2013) Standard Specification for Copper Sheet, Strip, Plate, and Rolled Bar
ASTM B766 (1986; R 2015) Standard Specification for
Electrodeposited Coatings of Cadmium
ASTM C553 (2013) Standard Specification for Mineral Fiber Blanket Thermal Insulation for Commercial and Industrial Applications
ASTM C916 (2014) Standard Specification for
Adhesives for Duct Thermal Insulation
ASTM C1071 (20162019) Standard Specification for Fibrous Glass Duct Lining Insulation (Thermal and Sound Absorbing Material)
ASTM D520 (2000; R 2011) Zinc Dust Pigment
ASTM D1654 (2008; R 2016; E 2017) Standard Test
Method for Evaluation of Painted or Coated Specimens Subjected to Corrosive Environments
ASTM D3359 (2017) Standard Test Methods for Rating
Adhesion by Tape Test
ASTM E84 (2018a) Standard Test Method for Surface Burning Characteristics of Building Materials
ASTM E2016 (2015) Standard Specification for
Industrial Woven Wire Cloth
CALIFORNIA DEPARTMENT OF PUBLIC HEALTH (CDPH)
CDPH SECTION 01350 (2010; Version 1.1) Standard Method for
SECTION 23 00 00 Page 3 May 2020 the Testing and Evaluation of Volatile Organic Chemical Emissions from Indoor Sources using Environmental Chambers
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
NEMA MG 1 (2016; SUPP 20162018) Motors and Generators
NEMA MG 10 (2017) Energy Management Guide for Selection and Use of Fixed Frequency Medium AC Squirrel-Cage Polyphase Induction Motors
NEMA MG 11 (1977; R 2012) Energy Management Guide for Selection and Use of Single Phase Motors
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2;
TIA 17-3; TIA 17-4; TIA 17-5; TIA 17-6;
TIA 17-7; TIA 17-8; TIA 17-9; TIA 17-10;
TIA 17-11; TIA 17-12; TIA 17-13; TIA
17-14; TIA 17-15; TIA 17-16; TIA 17-17 )
National Electrical Code
NFPA 90A (2018) Standard for the Installation of Air Conditioning and Ventilating Systems
NFPA 701 (2019) Standard Methods of Fire Tests for Flame Propagation of Textiles and Films
SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION
(SMACNA)
SMACNA 1966 (2005) HVAC Duct Construction Standards
Metal and Flexible, 3rd Edition
SMACNA 1981 (2008) Seismic Restraint Manual Guidelines for Mechanical Systems, 3rd Edition
SOUTH COAST AIR QUALITY MANAGEMENT DISTRICT (SCAQMD)
SCAQMD Rule 1168 (2017) Adhesive and Sealant Applications
U.S. DEPARTMENT OF ENERGY (DOE)
Energy Star (1992; R 2006) Energy Star Energy
Efficiency Labeling System (FEMP)
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
40 CFR 82 Protection of Stratospheric Ozone
UNDERWRITERS LABORATORIES (UL)
UL 6 (2007; Reprint Nov 2014) Electrical Rigid Metal Conduit-Steel
UL 181 (2013; Reprint Apr 2017) UL Standard for
SECTION 23 00 00 Page 4 May 2020
Safety Factory-Made Air Ducts and Air Connectors
UL 586 (2009; Reprint Dec 2017) UL Standard for
Safety High-Efficiency Particulate, Air Filter Units
UL 705 (2017; Reprint Oct 2018) UL Standard for
Safety Power Ventilators
UL 723 (2018) UL Standard for Safety Test for Surface Burning Characteristics of Building Materials
UL 900 (2015) Standard for Air Filter Units
UL Bld Mat Dir (updated continuously online) Building
Materials Directory
1.2 SYSTEM DESCRIPTION
Furnish ductwork, piping offsets, fittings, and accessories as required to provide a complete installation. Coordinate the work of the different trades to avoid interference between piping, equipment, structural, and electrical work. Provide complete, in place, all necessary offsets in piping and ductwork, and all fittings, and other components, required to install the work as indicated and specified.
1.2.1 Mechanical Equipment Identification
The number of charts and diagrams must be equal to or greater than the number of mechanical equipment rooms. Where more than one chart or diagram per space is required, mount these in edge pivoted, swinging leaf, extruded aluminum frame holders which open to 170 degrees.
1.2.1.1 Charts
Provide chart listing of equipment by designation numbers and capacities such as flow rates, pressure and temperature differences, heating and cooling capacities, horsepower, pipe sizes, and voltage and current characteristics.
1.2.2 Service Labeling
Label equipment, including fans, fan coils, energy recovery ventilators, etc., with labels made of self-sticking, plastic film designed for permanent installation. Provide labels matching the designations indicated in the Equipment Schedules on the Drawings.
Identify similar services with different temperatures or pressures. Where pressures could exceed 125 pounds per square inch, gage, include the maximum system pressure in the label. Label and arrow piping in accordance with the following:
a. Each point of entry and exit of pipe passing through walls.
b. Each change in direction, i.e., elbows, tees.
c. In congested or hidden areas and at all access panels at each point
SECTION 23 00 00 Page 5 May 2020 required to clarify service or indicated hazard.
d. In long straight runs, locate labels at distances within eyesight of each other not to exceed 75 feet. All labels must be visible and legible from the primary service and operating area.
For Bare or Insulated Pipes for Outside Diameters of Lettering
1/2 thru 1-3/8 inch 1/2 inch
1-1/2 thru 2-3/8 inch 3/4 inch
2-1/2 inch and larger 1-1/4 inch
1.2.3 Color Coding
Color coding of all piping systems must be in accordance with ASME A13.1.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-03 Product Data
Metallic Flexible Duct
Insulated Nonmetallic Flexible Duct Runouts
Duct Connectors
Duct Access Doors; G
Manual Balancing Dampers; G
Diffusers
Registers and Grilles
Louvers
In-Line Centrifugal Fans
Panel Type Power Wall
Ventilators
McMurren, Jamin/BOI Formatting problem. This should be a single line, one product data submittal “Power Type Panel Wall Ventilators”.
SECTION 23 00 00 Page 6 May 2020
Ceiling Exhaust Fans
Energy Recovery Devices; G
Test Procedures
Diagrams; G
SD-06 Test Reports
Performance Tests; G
SD-07 Certificates
Ozone Depleting Substances Technician Certification
SD-08 Manufacturer's Instructions
Manufacturer's Installation Instructions
Operation and Maintenance Training
SD-10 Operation and Maintenance Data
Operation and Maintenance Manuals; G
Manual Balancing Dampers; G
Motorized Dampers; G
In-Line Centrifugal Fans; G
Panel Type Power Wall
Ventilators; G
Ceiling Exhaust Fans; G
Energy Recovery Devices; G
1.4 QUALITY ASSURANCE
Except as otherwise specified, approval of materials and equipment is based on manufacturer's published data.
a. Where materials and equipment are specified to conform to the standards of the Underwriters Laboratories, the label of or listing with reexamination in UL Bld Mat Dir, and UL 6 is acceptable as sufficient evidence that the items conform to Underwriters Laboratories requirements. In lieu of such label or listing, submit a written certificate from any nationally recognized testing agency, adequately equipped and competent to perform such services, stating that the items have been tested and that the units conform to the specified requirements. Outline methods of testing used by the specified agencies.
b. Where materials or equipment are specified to be constructed or tested, or both, in accordance with the standards of the ASTM International (ASTM), the ASME International (ASME), or other
SECTION 23 00 00 Page 7 May 2020 standards, a manufacturer's certificate of compliance of each item is acceptable as proof of compliance.
c. Conformance to such agency requirements does not relieve the item from compliance with other requirements of these specifications.
1.4.1 Prevention of Corrosion
Protect metallic materials against corrosion. Provide rust-inhibiting treatment and standard finish for the equipment enclosures. Do not use aluminum in contact with earth, and where connected to dissimilar metal.
Protect aluminum by approved fittings, barrier material, or treatment.
Provide hot-dip galvanized ferrous parts such as anchors, bolts, braces, boxes, bodies, clamps, fittings, guards, nuts, pins, rods, shims, thimbles, washers, and miscellaneous parts not of corrosion-resistant steel or nonferrous materials in accordance with ASTM A123/A123M for exterior locations and cadmium-plated in conformance with ASTM B766 for interior locations.
1.4.2 Asbestos Prohibition
Do not use asbestos and asbestos-containing products.
1.4.3 Ozone Depleting Substances Technician Certification
All technicians working on equipment that contain ozone depleting refrigerants must be certified as a Section 608 Technician to meet requirements in 40 CFR 82, Subpart F. Provide copies of technician certifications to the Contracting Officer at least 14 calendar days prior to work on any equipment containing these refrigerants.
1.4.4 Test Procedures
Submit proposed test procedures and test schedules for the performance tests of systems, at least 2 weeks prior to the start of related testing.
1.5 DELIVERY, STORAGE, AND HANDLING
Protect stored equipment at the jobsite from the weather, humidity and temperature variations, dirt and dust, or other contaminants.
Additionally, cap or plug all pipes until installed.
PART 2 PRODUCTS
2.1 STANDARD PRODUCTS
Provide components and equipment that are "standard products" of a manufacturer regularly engaged in the manufacturing of products that are of a similar material, design and workmanship. "Standard products" is defined as being in satisfactory commercial or industrial use for 2 years before bid opening, including applications of components and equipment under similar circumstances and of similar size, satisfactorily completed by a product that is sold on the commercial market through advertisements, manufacturers' catalogs, or brochures. Products having less than a 2-year field service record are acceptable if a certified record of satisfactory field operation, for not less than 6000 hours exclusive of the manufacturer's factory tests, can be shown. Provide equipment items that are supported by a service organization.
SECTION 23 00 00 Page 8 May 2020
2.2 IDENTIFICATION PLATES
In addition to standard manufacturer's identification plates, provide engraved laminated phenolic identification plates for each piece of mechanical equipment. Identification plates are to designate the function of the equipment. Submit designation with the shop drawings. Provide identification plates that are layers, black-white-black, engraved to show white letters on black background. Letters must be upper case.
Identification plates that are 1-1/2-inches high and smaller must be 1/16-inch thick, with engraved lettering 1/8-inch high; identification plates larger than 1-1/2-inches high must be 1/8-inch thick, with engraved lettering of suitable height. Identification plates 1-1/2-inches high and larger must have beveled edges. Install identification plates using a compatible adhesive.
2.3 EQUIPMENT GUARDS AND ACCESS
Fully enclose or guard belts, pulleys, chains, gears, couplings, projecting setscrews, keys, and other rotating parts exposed to personnel contact according to OSHA requirements. Properly guard or cover with insulation of a type specified, high temperature equipment and piping exposed to contact by personnel or where it creates a potential fire hazard. The requirements for ladders and guardrails are specified in Section 05 50 13 MISCELLANEOUS METAL FABRICATIONS.
2.4 ELECTRICAL WORK
a. Provide motors, controllers, integral disconnects, contactors, and controls with their respective pieces of equipment, except controllers indicated as part of motor control centers. Provide electrical equipment, including motors and wiring, as specified in Section 26 20 00INTERIOR DISTRIBUTION SYSTEM. Provide manual or automatic control and protective or signal devices required for the operation specified and control wiring required for controls and devices specified, but not shown. For packaged equipment, include manufacturer provided controllers with the required monitors and timed restart.
b. For single-phase motors, provide high-efficiency, electronically commutated type, fractional-horsepower alternating-current motors, including motors that are part of a system, in accordance with NEMA MG 11. Provide premium efficiency type integral size motors in accordance with NEMA MG 1.
c. For polyphase motors, provide squirrel-cage medium induction motors, including motors that are part of a system, and that meet the efficiency ratings for premium efficiency motors in accordance with NEMA MG 1. Select premium efficiency polyphase motors in accordance with NEMA MG 10.
d. Provide motors in accordance with NEMA MG 1 and of sufficient size to drive the load at the specified capacity without exceeding the nameplate rating of the motor. Provide motors rated for continuous duty with the enclosure specified. Provide motor duty that allows for maximum frequency start-stop operation and minimum encountered interval between start and stop. Provide motor torque capable of accelerating the connected load within 20 seconds with 80 percent of the rated voltage maintained at motor terminals during one starting period. Provide motor starters complete with thermal overload
SECTION 23 00 00 Page 9 May 2020 protection and other necessary appurtenances. Fit motor bearings with grease supply fittings and grease relief to outside of the enclosure.
e. Where two-speed or variable-speed motors are indicated, solid-state variable-speed controllers are allowed to accomplish the same function. Use solid-state variable-speed controllers for motors rated 10 hp or less and adjustable frequency drives for larger motors.
2.5 ANCHOR BOLTS
Provide anchor bolts for equipment placed on concrete equipment pads or on concrete slabs. Bolts to be of the size and number recommended by the equipment manufacturer and located by means of suitable templates.
Installation of anchor bolts must not degrade the surrounding concrete.
2.6 SEISMIC ANCHORAGE
Anchor equipment in accordance with applicable seismic criteria for the area and as defined in SMACNA 1981.
2.7 PAINTING
Paint equipment units in accordance with approved equipment manufacturer's standards unless specified otherwise. Field retouch only if approved.
Otherwise, return equipment to the factory for refinishing.
2.8 INDOOR AIR QUALITY
Provide equipment and components that comply with the requirements of ASHRAE 62.1 unless more stringent requirements are specified herein.
2.9 DUCT SYSTEMS
2.9.1 Metal Ductwork
Provide metal ductwork construction, including all fittings and components, that complies with SMACNA 1966, as supplemented and modified by this specification.
a. Provide radius type elbows with a centerline radius of 1.5 times the width or diameter of the duct where space permits. Otherwise, elbows having a minimum radius equal to the width or diameter of the duct or square elbows with factory fabricated turning vanes are allowed.
b. Provide ductwork that meets the requirements of Seal Class A.
c. Provide sealants that conform to fire hazard classification specified in Section 23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS and are suitable for the range of air distribution and ambient temperatures to which it is exposed. Do not use pressure sensitive tape as a sealant. Provide duct sealant products that meet either emissions requirements of CDPH SECTION 01350 (limit requirements for either office or classroom spaces regardless of space type) or VOC content requirements of SCAQMD Rule 1168 (HVAC duct sealants are classified as "Other" within the SCAQMD Rule 1168 sealants table). Provide validation of indoor air quality for duct sealants.
d. Make spiral lock seam duct, and flat oval with duct sealant and lock with not less than 3 equally spaced drive screws or other approved
SECTION 23 00 00 Page 10 May 2020 methods indicated in SMACNA 1966. Apply the sealant to the exposed male part of the fitting collar so that the sealer is on the inside of the joint and fully protected by the metal of the duct fitting. Apply one brush coat of the sealant over the outside of the joint to at least 2 inch band width covering all screw heads and joint gap. Dents in the male portion of the slip fitting collar are not acceptable.
Fabricate outdoor air intake ducts and plenums with watertight soldered or brazed joints and seams.
2.9.1.1 Insulated Nonmetallic Flexible Duct Runouts
Use flexible duct runouts only at final connection to supply diffusers.
Runout length is not to exceed 5 feet. Provide runouts that are preinsulated, factory fabricated, and that comply with NFPA 90A and UL 181.
Provide either field or factory applied vapor barrier. Insulated flexible connectors are allowed as runouts. Provide insulated material and vapor barrier that conform to the requirements of Section 23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS. Do not expose the insulation material surface to the air stream.
2.9.1.2 General Service Duct Connectors
Provide not less than 20 ounce glass fabric duct connectors coated on both sides with neoprene. Provide a flexible duct connector approximately 6 inches in width where sheet metal connections are made to fans or where ducts of dissimilar metals are connected. For round/oval ducts, secure the flexible material by stainless steel or zinc-coated, iron clinch-type draw bands. For rectangular ducts, install the flexible material locked to metal collars using normal duct construction methods. Provide a composite connector system that complies with NFPA 701 and is classified as "flame-retardant fabrics" in UL Bld Mat Dir.
2.9.1.3 Corrosion Resisting (Stainless) Steel Sheets
ASTM A167.
2.9.2 Duct Access Doors
Provide hinged access doors conforming to SMACNA 1966 in ductwork and plenums where indicated and at all air flow measuring primaries, coils, thermostats, and other apparatus requiring service and inspection in the duct system. Provide access doors upstream of air flow measuring primaries and heating and cooling coils. Provide doors that are a minimum 15 by 18 inches, unless otherwise shown. Where duct size does not accommodate this size door, make the doors as large as practicable. Equip doors 24 by 24 inches or larger with fasteners operable from inside and outside the duct. Use insulated type doors in insulated ducts.
2.9.3 Manual Balancing Dampers
Furnish manual balancing dampers with accessible operating mechanisms.
Use chromium plated operators (with all exposed edges rounded) in finished portions of the building. Provide manual volume control dampers that are operated by locking-type quadrant operators. Install dampers that are 2 gauges heavier than the duct in which installed. Unless otherwise
SECTION 23 00 00 Page 11 May 2020 indicated, provide opposed blade type multileaf dampers with maximum blade width of 12 inches. Provide access doors or panels for all concealed damper operators and locking setscrews. Provide stand-off mounting brackets, bases, or adapters not less than the thickness of the insulation when the locking-type quadrant operators for dampers are installed on ducts to be thermally insulated, to provide clearance between the duct surface and the operator. Provide stand-off mounting items that are integral with the operator or standard accessory of the damper manufacturer. Provide damper operator extensions to common locations for dampers above solid ceilings to minimize the number of access doors.
2.9.4 Entry Connectors and Branch Connections
Provide 45-degree entry connectors with manual dampers at all duct-mounted supply outlets, at takeoff or extension collars to supply outlets, and at duct branch takeoff connections, as well as at locations as indicated on the drawings or otherwise specified. Conical branch connections are allowed in lieu of 45-degree entry connectors for branch connections. Furnish all volume dampers with an approved means of adjustment. Provide easily accessible means for adjustment inside the duct or from an adjustment with sturdy lock on the face of the duct. When installed on ducts to be thermally insulated, provide external adjustments with stand-off mounting brackets, integral with the adjustment device, to provide clearance between the duct surface and the adjustment device not less than the thickness of the thermal insulation.
Provide fixed turning vanes, in 90 degree elbows.
2.9.5 Diffusers, Registers, and Grilles
Provide factory-fabricated units of steel or aluminum as indicated that distribute the specified quantity of air evenly over space intended
SECTION 23 00 00 Page 12 May 2020 without causing noticeable drafts, air movement faster than 50 fpm in occupied zone, or dead spots anywhere in the conditioned area. Provide outlets for diffusion, spread, throw, and noise level as required for specified performance. Certify performance according to ASHRAE 70.
Provide sound rated and certified inlets and outlets according to ASHRAE 70.
Provide sound power level as indicated. Where the inlet and outlet openings are located less than 7 feet above the floor, protect them by a grille or screen according to NFPA 90A.
2.9.7.1 Diffusers
Provide diffuser types indicated. Furnish ceiling mounted units with anti-smudge devices, unless the diffuser unit minimizes ceiling smudging through design features. Provide diffusers with air deflectors of the type indicated. Install ceiling mounted units with rims tight against ceiling. Provide sponge rubber gaskets between ceiling and surface mounted diffusers for air leakage control. Provide suitable trim for flush mounted diffusers. For connecting the duct to diffuser, provide duct collar that is airtight and does not interfere with volume controller. Provide return, transfer, and exhaust units that are similar to supply diffusers.
2.9.7.2 Registers and Grilles
Provide transfer return and exhaust registers that are fixed horizontal or vertical louver type similar in appearance to the supply register face.
Furnish registers with sponge-rubber gasket between flanges and wall or ceiling. Install wall supply registers at least 6 inches below the ceiling unless otherwise indicated. Locate return and exhaust registers 6 inches above the floor unless otherwise indicated.
2.9.6 Louvers
Provide louvers for installation in exterior walls that are associated with the air supply and distribution system as specified in Section
08 91 00 METAL WALL AND DOOR LOUVERS.
2.9.7 Bird Screens and Frames
Provide bird screens that conform to ASTM E2016, No. 2 mesh, aluminum or stainless steel. Provide "medium-light" rated aluminum screens. Provide "light" rated stainless steel screens. Provide removable type frames fabricated from either stainless steel or extruded aluminum.
2.10 AIR SYSTEMS EQUIPMENT
2.10.1 Fans
Test and rate fans according to AMCA 210. Calculate system effect on air moving devices in accordance with AMCA 201 where installed ductwork differs from that indicated on drawings. Install air moving devices to minimize fan system effect. Where system effect is unavoidable, determine the most effective way to accommodate the inefficiencies caused by system effect on the installed air moving device. The sound power level of the fans must not exceed 85 dBA when tested according to AMCA 300 and rated in accordance with AMCA 301. Provide all fans with an AMCA seal. Connect fans to the motors either directly or indirectly with V-belt drive. Use V-belt drives designed for not less than 150 percent of the connected driving capacity. Provide variable pitch motor sheaves for 15 hp and below.
SECTION 23 00 00 Page 13 May 2020
Select variable pitch sheaves to drive the fan at a speed which can produce the specified capacity when set at the approximate midpoint of the sheave adjustment. When fixed pitch sheaves are furnished, provide a replaceable sheave when needed to achieve system air balance. Provide motors for V-belt drives with adjustable rails or bases. Provide removable metal guards for all exposed V-belt drives, and provide speed-test openings at the center of all rotating shafts. Provide fans with personnel screens or guards on both suction and supply ends, except that the screens need not be provided, unless otherwise indicated, where ducts are connected to the fan. Provide fan and motor assemblies with vibration-isolation supports or mountings as recommended by manufacturer.
Use vibration-isolation units that are standard products with published loading ratings. Select each fan to produce the capacity required at the fan static pressure indicated. Provide sound power level as indicated.
Obtain the sound power level values according to AMCA 300. Provide standard AMCA arrangement, rotation, and discharge as indicated. Provide power ventilators that conform to UL 705 and have a UL label.
2.10.1.1 In-Line Centrifugal Fans
Provide in-line fans with centrifugal backward inclined blades, internal and external belt guards, and adjustable motor mounts. Mount fans in a bolted galvanized housing. Provide a plenum-type fan. Provide with inlet venturi overlapping the wheel inlet, and field-selectable outlet orientation. Provide duct collar on inlet and outlet. Provide precision, self aligning ball or roller type fan bearings that are sealed against dust and dirt and are permanently lubricated. Provide L50 rated bearing life at not less than 200,000 hours as defined by ABMA 9 and ABMA 11.
Provide motors with open, dripproof, or totally enclosed enclosure.
Provide magnetic motor starters across-the-line with general-purpose enclosures.
2.10.1.2 Panel Type Power Wall Ventilators
Provide propeller type fans, assembled on a reinforced metal panel with venturi opening spun into panel. Provide direct or V-belt driven fans with wheels less than 24 inches in diameter and provide V-belt driven fans with wheels 24 inches in diameter and larger. Provide fans with wall mounting collar. Provide lubricated bearings. Equip fans with wheel and motor side metal or wire guards which have a corrosion-resistant finish. Provide dripproof or totally enclosed fan-cooled type motor enclosure. Install motor-operated backdraft dampers where indicated.
2.10.1.3 Ceiling Exhaust Fans
Provide centrifugal type, direct driven suspended cabinet-type ceiling exhaust fans. Provide fans with acoustically insulated housing. Provide chatter-proof backdraft damper. Provide egg-crate design or louver design integral face grille. Mount fan motors on vibration isolators. Furnish
SECTION 23 00 00 Page 14 May 2020 unit with mounting flange for hanging unit from above. Provide UL listed fans. Provide Energy Star labeled ceiling exhaust fan product.
2.10.2 Air Filters
List air filters according to requirements of UL 900, except list high efficiency particulate air filters of 99.97 percent efficiency by the DOP Test method under the Label Service to meet the requirements of UL 586.
2.10.2.1 Extended Surface Pleated Panel Filters
Provide 2 inch depth, sectional, disposable type filters of the size indicated with a MERV of 8 when tested according to ASHRAE 52.2. Provide initial resistance at 500 fpm that does not exceed 0.36 inches water gauge.
Provide UL Class 2 filters, and nonwoven cotton and synthetic fiber mat media. Attach a wire support grid bonded to the media to a moisture resistant fiberboard frame. Bond all four edges of the filter media to the inside of the frame to prevent air bypass and increase rigidity.
2.10.2.2 Filter Gauges
Provide dial type filter gauges, diaphragm actuated draft for all filter stations, including those filters which are furnished as integral parts of factory fabricated air handling units. Provide gauges that are at least 3-7/8 inches in diameter, with white dials with black figures, and graduations with a minimum range of 1 inch of water beyond the specified final resistance for the filter bank on which each gauge is applied.
Provide each gauge with a screw operated zero adjustment and two static pressure tips with integral compression fittings, two molded plastic vent valves, two 5 foot minimum lengths of 1/4 inch diameter vinyl tubing, and all hardware and accessories for gauge mounting.
2.11 ENERGY RECOVERY DEVICES
2.11.1 Plate Heat Exchanger
Provide energy recovery ventilator unit that is factory-fabricated for indoor installation, consisting of a flat plate cross-flow heat exchanger, cooling coil, supply air fan and motor and exhaust air fan and motor. The casing must be 20 gauge G90, galvanized steel, double wall construction with one inch insulation. Provide fibrous desiccant cross-flow type heat exchanger core capable of easy removal from the unit. Provide 2-inch deep MERV 8 filters on inlets to heat exchangers.
2.12 FACTORY PAINTING
Factory paint new equipment, which are not of galvanized construction.
Paint with a corrosion resisting paint finish according to ASTM A123/A123M or ASTM A924/A924M. Clean, phosphatize and coat internal and external ferrous metal surfaces with a paint finish which has been tested according to ASTM B117, ASTM D1654, and ASTM D3359. Submit evidence of satisfactory paint performance for a minimum of 125 hours for units to be installed indoors and 500 hours for units to be installed outdoors. Provide rating
SECTION 23 00 00 Page 15 May 2020 of failure at the scribe mark that is not less than 6, average creepage not greater than 1/8 inch. Provide rating of the inscribed area that is not less than 10, no failure. On units constructed of galvanized steel that have been welded, provide a final shop docket of zinc-rich protective paint on exterior surfaces of welds or welds that have burned through from the interior according to ASTM D520 Type I.
Field paint factory painting that has been damaged prior to acceptance by the Contracting Officer in compliance with the requirements of paragraph
FIELD PAINTING OF MECHANICAL EQUIPMENT.
2.13 SUPPLEMENTAL COMPONENTS/SERVICES
2.13.1 Condensate Drain Lines
Provide and install condensate drainage for each item of equipment that generates condensate in accordance with Section 22 00 00 PLUMBING, GENERAL PURPOSE, except as modified herein.
2.13.2 Backflow Preventers
The requirements for backflow preventers are specified in Section 22 00 00
PLUMBING, GENERAL PURPOSE.
2.13.3 Insulation
The requirements for shop and field applied insulation are specified in Section 23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS.
2.13.4 Controls
The requirements for controls are specified in Section 23 05 93 TESTING, ADJUSTING, AND BALANCING OF HVAC SYSTEMS, and Section 23 09 00
INSTRUMENTATION AND CONTROL FOR HVAC.
PART 3 EXECUTION
3.1 EXAMINATION
After becoming familiar with all details of the work, verify all dimensions in the field, and advise the Contracting Officer of any discrepancy before performing the work.
3.2 INSTALLATION
a. Install materials and equipment in accordance with the requirements of the contract drawings and approved manufacturer's installation instructions. Accomplish installation by workers skilled in this type of work. Perform installation so that there is no degradation of the designed fire ratings of walls, partitions, ceilings, and floors.
b. No installation is permitted to block or otherwise impede access to any existing machine or system. Install all hinged doors to swing open a minimum of 120 degrees. Provide an area in front of all access doors that clears a minimum of 3 feet. In front of all access doors to electrical circuits, clear the area the minimum distance to energized circuits as specified in OSHA Standards, part 1910.333 (Electrical-Safety Related work practices)and NFPA 70 Working Space and Dedicated Space.
SECTION 23 00 00 Page 16 May 2020
c. Except as otherwise indicated, install emergency switches and alarms in conspicuous locations. Mount all indicators, to include gauges, meters, and alarms in order to be easily visible by people in the area.
3.2.1 Condensate Drain Lines
Provide water seals in the condensate drain from all cooling units.
Provide a depth of each seal of 2 inches plus the number of inches, measured in water gauge, of the total static pressure rating of the unit to which the drain is connected. Provide water seals that are constructed of 2 tees and an appropriate U-bend with the open end of each tee plugged. Provide pipe cap or plug cleanouts where indicated. Connect drains indicated to connect to the sanitary waste system using an indirect waste fitting. Insulate air conditioner drain lines as specified in Section 23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS.
3.2.2 Equipment and Installation
Provide frames and supports for tanks, compressors, pumps, valves, air handling units, fans, coils, dampers, and other similar items requiring supports. Floor mount or ceiling hang air handling units as indicated.
Anchor and fasten as detailed. Set floor-mounted equipment on not less than 6 inch concrete pads or curbs doweled in place unless otherwise indicated. Make concrete foundations heavy enough to minimize the intensity of the vibrations transmitted to the piping, duct work and the surrounding structure, as recommended in writing by the equipment manufacturer. In lieu of a concrete pad foundation, build a concrete pedestal block with isolators placed between the pedestal block and the floor. Make the concrete foundation or concrete pedestal block a mass not less than three times the weight of the components to be supported.
Provide concrete for foundations as specified in Section 03 30 00
CAST-IN-PLACE CONCRETE.
3.2.3 Access Panels
Install access panels for concealed valves, vents, controls, dampers, and items requiring inspection or maintenance of sufficient size, and locate them so that the concealed items are easily serviced and maintained or completely removed and replaced. Provide access panels as specified in Section 05 50 13 MISCELLANEOUS METAL FABRICATIONS.
3.2.4 Flexible Duct
Install pre-insulated flexible duct in accordance with the latest printed instructions of the manufacturer to ensure a vapor tight joint. Provide hangers, when required to suspend the duct, of the type recommended by the duct manufacturer and set at the intervals recommended.
3.2.5 Metal Ductwork
Install according to SMACNA 1966 unless otherwise indicated. Install duct supports for sheet metal ductwork according to SMACNA 1966, unless otherwise specified. Do not use friction beam clamps indicated in SMACNA 1966. Anchor risers on high velocity ducts in the center of the vertical run to allow ends of riser to move due to thermal expansion.
Erect supports on the risers that allow free vertical movement of the duct. Attach supports only to structural framing members and concrete slabs. Do not anchor supports to metal decking unless a means is provided
SECTION 23 00 00 Page 17 May 2020 and approved for preventing the anchor from puncturing the metal decking.
Where supports are required between structural framing members, provide suitable intermediate metal framing. Where C-clamps are used, provide retainer clips.
3.2.5.1 Underground Ductwork
Do not install ductwork below grade or under concrete slabs.
3.2.6 Dust Control
To prevent the accumulation of dust, debris and foreign material during construction, perform temporary dust control protection. Protect the distribution system (supply and return) with temporary seal-offs at all inlets and outlets at the end of each day's work. Keep temporary protection in place until system is ready for startup.
3.2.7 Insulation
Provide thickness and application of insulation materials for ductwork, piping, and equipment according to Section 23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS. Externally insulate outdoor air intake ducts and plenums up to the point where the outdoor air reaches the conditioning unit.
3.2.8 Duct Test Holes
Provide holes with closures or threaded holes with plugs in ducts and plenums as indicated or where necessary for the use of pitot tube in balancing the air system. Plug insulated duct at the duct surface, patched over with insulation and then marked to indicate location of test hole if needed for future use.
3.2.9 Power Transmission Components Adjustment
Test V-belts and sheaves for proper alignment and tension prior to operation and after 72 hours of operation at final speed. Uniformly load belts on drive side to prevent bouncing. Make alignment of direct driven
SECTION 23 00 00 Page 18 May 2020 couplings to within 50 percent of manufacturer's maximum allowable range of misalignment.
3.3 EQUIPMENT PADS
Provide equipment pads to the dimensions shown or, if not shown, to conform to the shape of each piece of equipment served with a minimum 3-inch margin around the equipment and supports. Allow equipment bases and foundations, when constructed of concrete or grout, to cure a minimum of 14 calendar days before being loaded.
3.4 CUTTING AND PATCHING
Install work in such a manner and at such time that a minimum of cutting and patching of the building structure is required. Make holes in exposed locations, in or through existing floors, by drilling and smooth by sanding. Use of a jackhammer is permitted only where specifically approved. Make holes through masonry walls to accommodate sleeves with an iron pipe masonry core saw.
3.5 CLEANING
Thoroughly clean surfaces of piping and equipment that have become covered with dirt, plaster, or other material during handling and construction before such surfaces are prepared for final finish painting or are enclosed within the building structure. Before final acceptance, clean mechanical equipment, including piping, ducting, and fixtures, and free from dirt, grease, and finger marks. When the work area is in an occupied space such as office, laboratory or warehouse, protect all furniture and equipment from dirt and debris. Incorporate housekeeping for field construction work which leaves all furniture and equipment in the affected area free of construction generated dust and debris; and, all floor surfaces vacuum-swept clean.
3.6 PENETRATIONS
Provide sleeves and prepared openings for duct mains, branches, and other penetrating items, and install during the construction of the surface to be penetrated. Cut sleeves flush with each surface. Place sleeves for round duct 15 inches and smaller. Build framed, prepared openings for round duct larger than 15 inches and square, rectangular or oval ducts.
Sleeves and framed openings are also required where grilles, registers, and diffusers are installed at the openings. Provide one inch clearance between penetrating and penetrated surfaces except at grilles, registers, and diffusers. Pack spaces between sleeve or opening and duct or duct insulation with mineral fiber conforming with ASTM C553, Type 1, Class B-2.
3.6.1 Sleeves
Fabricate sleeves, except as otherwise specified or indicated, from 20 gauge thick mill galvanized sheet metal. Where sleeves are installed in bearing walls or partitions, provide black steel pipe conforming with ASTM A53/A53M, Schedule 20.
3.6.2 Framed Prepared Openings
Fabricate framed prepared openings from 20 gauge galvanized steel, unless otherwise indicated.
SECTION 23 00 00 Page 19 May 2020
3.6.3 Insulation
Provide duct insulation in accordance with Section 23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS continuous through sleeves and prepared openings except firewall penetrations. Terminate duct insulation at fire dampers and flexible connections. For duct handling air at or below 60 degrees F, provide insulation continuous over the damper collar and retaining angle of fire dampers, which are exposed to unconditioned air.
3.6.4 Closure Collars
Provide closure collars of a minimum 4 inches wide, unless otherwise indicated, for exposed ducts and items on each side of penetrated surface, except where equipment is installed. Install collar tight against the surface and fit snugly around the duct or insulation. Grind sharp edges smooth to prevent damage to penetrating surface. Fabricate collars for round ducts 15 inches in diameter or less from 20 gauge galvanized steel.
Fabricate collars for square and rectangular ducts, or round ducts with minimum dimension over 15 inches from 18 gauge galvanized steel.
Fabricate collars for square and rectangular ducts with a maximum side of 15 inches or less from 20 gauge galvanized steel. Install collars with fasteners a maximum of 6 inches on center. Attach to collars a minimum of 4 fasteners where the opening is 12 inches in diameter or less, and a minimum of 8 fasteners where the opening is 20 inches in diameter or less.
3.7 FIELD PAINTING OF MECHANICAL EQUIPMENT
Clean, pretreat, prime and paint metal surfaces; except aluminum surfaces need not be painted. Apply coatings to clean dry surfaces. Clean the surfaces to remove dust, dirt, rust, oil and grease by wire brushing and solvent degreasing prior to application of paint, except clean to bare metal on metal surfaces subject to temperatures in excess of 120 degrees F.
Where more than one coat of paint is specified, apply the second coat after the preceding coat is thoroughly dry. Lightly sand damaged painting and retouch before applying the succeeding coat. Provide aluminum or light gray finish coat.
3.7.1 Temperatures less than 120 degrees F
Immediately after cleaning, apply one coat of pretreatment primer applied to a minimum dry film thickness of 0.3 mil, one coat of primer applied to a minimum dry film thickness of 1 mil; and two coats of enamel applied to a minimum dry film thickness of 1 mil per coat to metal surfaces subject to temperatures less than 120 degrees F.
3.7.2 Finish Painting
The requirements for finish painting of items only primed at the factory, and surfaces not specifically noted otherwise, are specified in Section
09 90 00 PAINTS AND COATINGS.
SECTION 23 00 00 Page 20 May 2020
3.8 IDENTIFICATION SYSTEMS
Provide identification tags made of brass, engraved laminated plastic, or engraved anodized aluminum, indicating service and item number on all valves and dampers. Provide tags that are 1-3/8 inch minimum diameter with stamped or engraved markings. Make indentations black for reading clarity. Attach tags to valves with No. 12 AWG 0.0808-inch diameter corrosion-resistant steel wire, copper wire, chrome-plated beaded chain or plastic straps designed for that purpose.
3.9 TESTING, ADJUSTING, AND BALANCING
The requirements for testing, adjusting, and balancing are specified in Section 23 05 93 TESTING, ADJUSTING AND BALANCING FOR HVAC. Begin testing, adjusting, and balancing only when the air supply and distribution, including controls, has been completed, with the exception of performance tests.
3.10 PERFORMANCE TESTS
After testing, adjusting, and balancing is complete as specified, test each system as a whole to see that all items perform as integral parts of the system and temperatures and conditions are evenly controlled throughout the building. Make corrections and adjustments as necessary to produce the conditions indicated or specified. Conduct capacity tests and general operating tests by an experienced engineer. Provide tests that cover a period of not less than 1 day for each system and demonstrate that the entire system is functioning according to the specifications. Make coincidental chart recordings at points indicated on the drawings for the duration of the time period and record the temperature at space thermostats or space sensors and the ambient temperature and humidity in a shaded and weather protected area.
Submit test reports for the performance tests in booklet form, upon completion of testing. Document phases of tests performed including initial test summary, repairs/adjustments made, and final test results in the reports.
3.11 CLEANING AND ADJUSTING
Thoroughly clean inside of air handling units and fans, ducts, plenums, and casing of debris and blow free of small particles of rubbish and dust and then vacuum clean before installing access panels and closure elements.
Wipe equipment clean, with no traces of oil, dust, dirt, or paint spots.
Provide temporary filters prior to startup of all fans that are operated during construction, and provide new filters after all construction dirt has been removed from the building, and the ducts, plenums, casings, and…