About this file
This document contains a request for information and related federal contract opportunity notice. The request for information seeks clarification on the existing roof makeup and insulation for Building 403 at Mansfield Air National Guard Base, with the response confirming a single-ply roof system and R40 insulation.
The related federal contract opportunity is a solicitation notice for project number PBXP 169102 to add and alter Building 403 for corrosion control services. The project scope includes interior and exterior demolition, new sidewalk and drive access, antiterrorism force protection compliant doors and windows, a sprinkler system upgrade, new compressed air lines and air handling equipment, and electrical and wireless network upgrades. The construction duration is estimated at 300 calendar days with a bid opening date of December 7, 2020. The solicitation is set aside for small businesses with a NAICS code of 236220 and magnitude between $1,000,000 to $5,000,000. Additive bid items are included for additional work areas and equipment.
View the file
Other files for this federal contract opportunity
Show all 50
ADD/ALTER B403 CC has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR INFORMATION
R E
Q U
E S
T O
R S
E C
T
IO
N
From:
Date:
11/30/2020
To: Contracting Officer
1. Solicitation Number:
W50S8R-21-B-0001
2. Location of Project:
Building 403
3. Information Requested: (Include Specification Section and/or Drawing Number and Page if inquiring about a discrepancy)
Ref Drawing A104- Can you provide the existing roof makeup, including insulation height/thickness?
Attachments:
Date Response Required:
By:
Title:
Requestor's FAX Number:
Requestor's Telephone Number:
C E
R E
S P
O N
S E
To:
Date:
12/1/2020
Response:
Roof over the existing structure to be single ply system same product as the new roof. Insulation to be R‐40.
See spec section 07 22 00 for roof insulation requirements including protection board
See spec section 07 54 19 roofing material and associated requirements
This information is a clarification of the solicitation/contract and does not change the contract terms or conditions.
This information is a proposed change to the solicitation/contract. An amendment will be issued.
Contracting Officer:
File details come from the government source that posted it. Updated .