Bldg 42 Pre-Bid QA.xlsx
XLSX spreadsheet 13 KB Posted
- Attached to
- Jefferson Barracks, Demolish Building 42 Federal contract opportunity
- Solicitation number
- W50S8K-20-B-0001
About this file
This document contains a pre-bid question and answer log and related federal contract opportunity for the demolition of Building 42 at Jefferson Barracks in St. Louis, Missouri. The Missouri Air National Guard is seeking a firm-fixed price contract to demolish the approximately 11,000 square foot masonry building. The scope of work includes demolishing the structure while salvaging reusable materials for repairing other historic buildings on base. The contract value is between $250,000 and $500,000 and is set aside exclusively for service-disabled veteran owned small businesses. The pre-bid log addresses questions from contractors regarding asbestos and lead reports, utility coordination, fill material specifications, salvage requirements, and hazardous waste removal procedures. The opportunity is available through the Department of the Army Missouri Army National Guard.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Abstract of Bids.pdf | ||
| Updated Lead Report for Building 42 (March 2020).pdf | ||
| Building 42 Asbestos Report Recertification.pdf | ||
| Building 42 Asbestos Report.pdf | ||
| W50S8K20B00010002 Amendment 2.pdf | ||
| Bldg 42 Lead Report.pdf | ||
| Attach 1 - WD (Updated).pdf | ||
| W50S8K20B00010001 Amendment 1.pdf | ||
| Attach 2 - SOW (Updated).pdf | ||
| Bldg 42 Demolition Plans.pdf | ||
| Bldg 42 Demo Environmental Key Talking Points.docx | DOCX document | |
| Site-Visit Sign In Sheet.pdf | ||
| Attach 3 - EAL.docx | DOCX document | |
| Attach 1 - Wage Determination.pdf | ||
| Attach 2 - SOW.pdf | ||
| W50S8K20B0001 Demolish Building 42.pdf | ||
| Attach 4 - Bid Bonds Checklist.docx | DOCX document |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Pre-Bid Inquiry Log: W50S8K-20-B-0001 | ||
| Pre-Bid Inquiry No. | Bid Inquiry Request | Remarks |
| 1 | When the bid bond form is supposed to be submitted? Is it at the same time as we submit the bid or after? | Bid bond is due with the bid. See FAR clause 52.228-1 in the solicitation. |
| 2 | Does this project already have an asbestos report associated with it. If not will one be provided prior to bidding? | Asbestos and lead report dated 2014 will be provided. |
| 3 | Can you tell us if there is a Asbestos report for this building? B42 the old firing range building. | Asbestos and lead report dated 2014 will be provided. |
| 4 | Is the project tax exempt? | Yes, for material. |
| 5 | What material will be approved for the backfill of the foundation after its removal? | Engineered fill that must be approved by Civil Engineering in coordination with the State Historic Preservation Office. It may be in the contractor's best interest to submit several sources. The material for fill shall be a soils or soils/rock mixture that is free from organic matter or other deleterious substances. |
Fill material shall be spread in uniform lifts not exceeding 8 inch max lift thickness.
One density test per lift, ensuring 95% Standard Proctor Test Compaction.
Testing should be conducted by an independent engineering firm.
| 6 | Is there a hazardous environmental report for this project? | Asbestos and lead report dated 2014 will be provided. |
| 7 | In the SOW line item 2.b it indicates that the applicable salvaged items are to be abated prior to handing them over to the government…and if it can not be abated then it is to be disposed of as required per the regs. Who is to determine if it can be successfully abated? Is that determined by the labor involved on each item as an allowance? How are we to determine how much labor and cost is associated with each item to abate before its determined to not be worth it to salvage each individual item? How will each of the bid responses be evaluated on lowest price technically acceptable if it is unclear on what is determined as salvageable or unsalvageable before and or after abatement? | No items with asbestos containing material will be salvaged. Salvaged items with lead based paint should be hand scraped so flaking paint is removed, but does not need fully remediated. Any questionable items will be identified to the COR immediately and the Government will determine if it shall be salvaged. The contractor will be responsible for estimating what is salvagable. Any item intact should be considered salvagable, i.e. if an item is immediately usable once removed and paint scraped off, it is considered salvagable. |
| 8 | It is understood that the government will get the required utility permits for shut off and disconnects? | The contractor is responsible for coordinating with any commercial utilities for shut offs and disconnects. |
| 9 | Are there any Asbestos or Lead surveys on Building 42? | Asbestos and lead report dated 2014 will be provided. |
| 10 | Can nearby fire hydrants be utilizes as a water source for use with dust suppression? | Yes, but must meter water usage and pay water provider directly. Coordinate with Civil Engineering Resource Advisor. |
| 11 | What percentage of the foundation block is to be salvaged and how is it to be palletized? | Goal of 100% salvaged, stones palletized in a compact arrangement on wooden pallets at a weight that the pallets can support. |
| 12 | Is the contractor responsible for transporting salvaged doors, window to nearby storage area? | Yes. Government will move items from nearby storage area to permanent storage. |
| 13 | What items located in the basement are to be salvaged if any? | Pierced steel plating door, the iron barred door on the exterior, any other metal items. |
| 14 | Could the government provide the latest asbestos inspection for building 42? | Asbestos and lead report dated 2014 will be provided. |
| 15 | Could the government provide the standards/types of acceptable fill materials? | Backfill material will now be Engineered Fill using ML and CL type soil. Fill must be approved by CE. The material for fill shall be a soils mixture that is less than 3% organic matter or other deleterious substances. |
Fill material shall be spread in uniform lifts not exceeding 8 inch max lift thickness.
One density test per lift, ensuring 95% Standard Proctor Test Compaction.
Testing should be conducted by an independent engineering firm.
| 16 | Could the government provide a list of approved suppliers of fill materials acceptable to the government? | Combine with Line 7 |
| 17 | Is there a penalty if less than 80% of the masonry can be saved? | 80% is an estimate. A COR will be on-site to ensure due dilligence is made by the contractor when salvaging material. |
| 18 | Is there a required percentage of compaction standard for the fill material, and are compaction test required? Are the electrical lines to be disconnected from building 42 above or below ground. | The engineered fill will require compaction tests. Loose compaction is not acceptable. Must comply with AASHTO standard. Electrical lines are all located above ground. The material for fill shall be a soils or soils/rock mixture that is free from organic matter or other deleterious substances. |
Fill material shall be spread in uniform lifts not exceeding 8 inch max lift thickness.
One density test per lift, ensuring 95% Standard Proctor Test Compaction.
Testing should be conducted by an independent engineering firm.
| 19 | Will Dig - Rite locate utilities on the base? | Yes, contractor to coordinate with Dig-Rite directly. |
| 20 | A copy of the Air National Guard work schedule and duty hours. | Provided with this amendment. |
| 21 | An analysis of the building’s structural integrity. | No |
| 22 | Could you provide lead times for hazardous materials entering the site i.e. gas or diesel? Additionally, could you provide lead times for approval of hazardous waste manifests for abated materials leaving the base. | Lead time for hazordous materails: Gas or diesel tow behind tanks require a 2 business day notice and must be accompanied by approved secondary containment and spill response supplies. Fuel trucks require a 1 business day notice if they will not remain on site. If remaining on site, we require a 2 business day notice with approved secondary containment and spill response supplies. For hazardous waste manifest, 1 hour notice is required between the hours of 8:00 AM thru 3:00 PM local time. Any other HAZMAT requires 3 business days notice and applicable Safety Data Sheet and submitted on an AF 3000. |
| 23 | The asbestos Analytical report mentioned on the site visit? | Provided with this amendment. |
| 24 | Was the Analytical Survey done within the last three years? | No. |
| 25 | Will a remedial action plan be provided? | No, the contractor is responsible for complying with state, local, and federal regulations regarding abatement of hazardous materials. |
| 26 | Will the lead paint be considered general debris, or will a lead remediation plan be required? | Yes, and shall be handled IAW MDNR PUB 2045. If lead paint is scraped for salvage, the scrapings will be considered hazardous waste and will be disposed of as such. |
| 27 | Who will be responsible for moving the palletized materials to the storage location? | The contractor. |
| 28 | How often will the palatized materials be moved to the storage location? | As needed by the contractor, however the final location for storing pallets will be the footprint of Bldg. 42. |
| 29 | There is a possibility that interior materials are exposed to inclement weather while palletized materials are stacked on the demolition site. What happens if such materials are damaged? | Notify the COR the same business day these types of materials will be exposed. The Government will be repsonsible for these materials if notified in this timely manner. |
| 30 | What is the footprint of the basement? | The size of the basement is approximately 57'x36'. |
| 31 | Does the Air National Guard want sod/gravel placed over the entire footprint of the demolished building? | Reference Statement of Work section 2F. |
| 32 | Where will palletized material be placed while awaiting movement to storage location? | 170' west of Bldg. 42, the gravel lay down yard. |
| 33 | Who will move the palletized bricks/limestone from the storage location to the backfilled basement area? | The contractor. |
| 34 | During the site visit, it was stated that the general contractor is not responsible for cleaning lead paint off of items being kept for salvage; however, “section 2. Principle items of work", subsection b. states otherwise. Please clarify this. | Lead paint will only need hand scraping for flaking paint on salvaged items. |