Site Visit Questions 6.29.2020.pdf

PDF 49 KB Posted

Attached to
Building 12 Roof Replacement Federal contract opportunity
Solicitation number
W50S8J-20-R-0010
Issued by
Department of the Army New York Army National Guard

View the file

Other files for this federal contract opportunity

Other files attached to Building 12 Roof Replacement, newest first.
File Type Posted
Site visit attendance.pdf PDF
W50S8J20R0010-0001.pdf PDF
ATT C - Photos of B12 Roof Project.pdf PDF
ATT B - B12 Asbestos Report.pdf PDF
ATT D - DD1354.pdf PDF
ATT A - Bldg 12 Roof Plan.pdf PDF
W50S8J-20-R-0010.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Building 12 Roof Replacement Project # VBDZ202100 Questions from Site Visit

1. Q: One of the four HVAC units does not have a pitch pocket currently, does the base want one installed?

A: Yes, please make all four HVAC unit installations consistent, with pitch pockets installed.

2. Q: The Manufacturer’s Warranty mentions a no dollar limit warranty requirement, will the cost of the project be considered as a maximum dollar limit instead?

A: Yes, the Manufacturer’s Warranty can be limited up to the full contract value between the Government and the Prime Contractor.

3. Q: We were unable to make the site visit, will we still have an opportunity to view the project site conditions?

A: Yes, please contact MSgt Wanda Yarbor and arrangements can be made for a site visit.

4. Q: We are concerned about having enough time to put a cost proposal together with the upcoming holiday weekend, is it possible to extend the due date?

A: Yes, the due date can be extended until close of business Thursday, July 16th.

5. Q: Is the concrete deck sloped?

A: No as-built information was available to determine if the concrete roof deck is sloped.

6. Q: Is the Colonial Red color acceptable for the fascia and edge material?

A: Color samples will be required in order to make this decision. The fascia and edge material are to match existing color schemes.