ATT C - Photos of B12 Roof Project.pdf

PDF 1 MB Posted

Attached to
Building 12 Roof Replacement Federal contract opportunity
Solicitation number
W50S8J-20-R-0010
Issued by
Department of the Army New York Army National Guard

View the file

Other files for this federal contract opportunity

Other files attached to Building 12 Roof Replacement, newest first.
File Type Posted
Site visit attendance.pdf PDF
W50S8J20R0010-0001.pdf PDF
Site Visit Questions 6.29.2020.pdf PDF
ATT A - Bldg 12 Roof Plan.pdf PDF
W50S8J-20-R-0010.pdf PDF
ATT B - B12 Asbestos Report.pdf PDF
ATT D - DD1354.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Photo 1 – Access to lower roof. Antenna to be removed and reinstalled by base personnel. Photo 2 – Vent to be temporarily removed and then reattached by Contractor.

Photo 3 – Roof Section #5. Vestibule area.

Photo 4 – Roof Section #5. Vestibule area, alternate view.

Photo 5 – Vent to be unattached and then reattached by Contractor.

Photo 6 – Roof 1. Note HVAC units and vents.

Photo 7 – Exhaust vent to be abandoned and removed. Building EIFS to be repaired, filled, and painted to match.

Photo 8 – Side of upper roof level. Photo taken from lower roof.

New EPDM and metal fastening to be replaced in kind, and to have a similar connection pattern to upper roof side wall. Fasten to prevent capture/entrapment of water beneath EIFS.

Photo 9 – Close up of Photo #8

Photo 12 – Broken roof drain covers to be replaced with new to match.

Photo 11 – Roof Section #3. Insulation to be shaped to promote proper slope to drain and eliminate existing pooling of water.

Photo 10 – Roof Section #2. Eliminate pooling of water.

Photo 13 – Radio antennae to be removed and reinstalled by Base Personnel

Photo 14 – Roof Section #4

Photo 15 – Roof Section #1 – Close up of exhaust vent.

Photo 16 – Roof Section #1 – Close up of HVAC units and pitch pockets.

HVAC to be disconnected, recovered, recharged, and re-installed to existing line sets, in exact same positions, by Contractor.