Attachment_15rev01_W50S8F-20-B-0001_400HzPwr_Bid_Q and A_20200508.xlsx

XLSX spreadsheet 12 KB Posted

Attached to
AQRC172001: ACA: Install 400Hz Electric Power
Solicitation number
W50S8F-20-B-0001
Issued by

View the file

Other files

File Type Posted
W50S8F-20-B-0001_400HzPwr_OF_1419_BID_OPENING_SIGNED.pdf PDF
Attach_01_rev03_20-B-0001_Attachment_Schedule.xlsx XLSX spreadsheet
Attach_03rev01_W50S8F-20-B-0001_AMEND03_SECT00100_ITEM_09rev01.docx DOCX document
Attachment_15rev01_W50S8F-20-B-0001_400HzPwr_Bid_QA_20200508.pdf PDF
W50S8F-20-B-0001_SF30_AMEND_03.pdf PDF
Attach_01_rev02_20-B-0001_Attachment_Schedule.xlsx XLSX spreadsheet
Attachment_15_W50S8F-20-B-0001_400HzPwr_Bid_Q and A_20200508.xlsx XLSX spreadsheet
Attach_014_Aircraft_Shelter_Dimensions.pdf PDF
Attach_01_rev01_20-B-0001_Attachment_Schedule.xlsx XLSX spreadsheet
W50S8F-20-B-0001_AMEND02.pdf PDF
Attach_013_400HzPwr_Pre-Bid_PPT and Virtual_Site_Visit.pdf PDF
W50S8F-20-B-0001_AMEND01_SECT00100_ITEM05.pdf PDF
Attach_08_InsuranceRequirements.docx DOCX document
Attach_03_400Hz_Pwr_Section 00100_20200416.docx DOCX document
W50S8F-20-B-0001_SF1442_400HzPwr_Solicitation_20200423.pdf PDF
Attach_02_400Hz_Pwr_Section 00010_20200416.docx DOCX document
Attach_06_AQRC172002_400Hz Pwr_IFC_DWG.pdf PDF
Attach_012_177FW_VicinityMaps.pdf PDF
Attach_09_EnviroManagSystem.pdf PDF
Attach_01_20-B-0001_Attachment_Schedule.xlsx XLSX spreadsheet
Attach_07_NJ20200025_MOD_01_date01312020.pdf PDF
Attach_010_OPSEC_Letter.docx DOCX document
Attach_05_AQRC172002_400Hz_Pwr_IFC_Specs.pdf PDF
Attach_04_AQRC172001_SOW_20200416.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

177th Fighter Wing
Pre-Bid Questions & Clarifications
Solicitation #:W50S8F-20-B-0001
Project Name & Number:AQRC172001 ACA: Install 400Hz Converters
Updated:Friday, May 08, 2020
RFI #SubmittedAnsweredQuestionResponseResponse By
101-May-2008-May-20What size and length is the cable required on the cord reels?- Cable and plug shall in accordance with Specification Section 26 3543-2.2 Aircraft Power Cable Assembly.
- Cable length shall be 90 feet.177 MSC
201-May-2008-May-20What style/configuration and size plug is required on the end of the cord?see Answer # 1 above177 MSC
301-May-2008-May-20What voltage is the output of the 400Hz converters?In accordance with Specification SECTION 26 35 43 400-HERTZ (HZ) SOLID STATE FREQUENCY CONVERTER177 MSC
401-May-2008-May-20What is the interior elevation on the shelters?
Sheet note 5 states to install the conduit as high as possible tight to the bay overhead trusses.Shelter As-Built drawings with dimesions & elevations were posted to beta.SAM.gov in Amendment 02 on May 5th.177 MSC
506-May-2008-May-20We don’t see a service disconnect in the documents, does the 400 Hz. Converter have its own switch disconnect or can the circuit breaker be locked in the open position?Equipmement had main breaker disconnect & emergency stop button. Service disconnect not required.177 CES
606-May-2008-May-20a) Is the Cable Reel to be supplied by the contractor or is GFCI?
b) If the Contractor is to supply the cable reel, what is the length and size of the cable?a) Cable Reel is contractor supplied.
b) see anser # 1 above177 MSC
706-May-2008-May-20What is the height shelters?Shelter As-Built drawings with dimesions & elevations were posted to beta.SAM.gov in Amendment 02 on May 5th.177 MSC
806-May-2008-May-20I don’t see the video portion of yesterdays site visit. Is that going to be up loaded to the beta.sam.gov site?The video of the Pre-Bid Video Confernence will not be posted. The Power Point Presentation & Virtual Site Visit pictures were posted to beta.SAM.gov in Amendment 02 Attachment 13177 MSC
908-May-2008-May-20Which model of the Hannay CR6600 Series cord reel is required? i.e. Manual driven, Electric driven, Air driven or Hydraulic driven?Manual Driven177 MSC
1008-May-2008-May-20Is the government supplying the cable assembly and MS 25486-17 Cord end for the cable reel?No, the cable assembly and cord end are Contractor Furnished items in accordance with Key Note 2 in the Drawings177 MSC
1108-May-2008-May-20Will the 1st POD be empty of aircraft, thus allowing contractor to use as a lay down or storage area?The contractor will only have access to one shelter at a time.

One shelter will be empty at a time and designated at the Contractor's work area. Only the shleter that the Contractor is working in will be allowed as a laydown & sotrage area. All euipment & material must be moved to the next shelter after completion of the first.

The 2 shelters not being worked in at the time will be restricted for access & use by the contractor. 177 MSC

177 CES
177 MSC
A&E
End User
Other