Attachment_15_W50S8F-20-B-0001_400HzPwr_Bid_Q and A_20200508.xlsx
XLSX spreadsheet 12 KB Posted
- Attached to
- AQRC172001: ACA: Install 400Hz Electric Power
- Solicitation number
- W50S8F-20-B-0001
- Issued by
-
Department of the Army National Guard
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| 177th Fighter Wing |
| Pre-Bid Questions & Clarifications |
| Solicitation #: | W50S8F-20-B-0001 |
| Project Name & Number: | AQRC172001 ACA: Install 400Hz Converters |
| Updated: | Friday, May 08, 2020 |
| RFI # | Submitted | Answered | Question | Response | Response By | |
| 1 | 01-May-20 | What size and length is the cable required on the cord reels? | Under Review by Government | |||
| 2 | 01-May-20 | What style/configuration and size plug is required on the end of the cord? | Under Review by Government | |||
| 3 | 01-May-20 | 08-May-20 | What voltage is the output of the 400Hz converters? | 120/208V AC 3 phase | 177 CES | |
| 4 | 01-May-20 | 08-May-20 | What is the interior elevation on the shelters? | |||
| Sheet note 5 states to install the conduit as high as possible tight to the bay overhead trusses. | Shelter As-Built drawings with dimesions & elevations were posted to beta.SAM.gov in Amendment 02 on May 5th. | 177 MSC | ||||
| 5 | 06-May-20 | 08-May-20 | We don’t see a service disconnect in the documents, does the 400 Hz. Converter have its own switch disconnect or can the circuit breaker be locked in the open position? | Equipmement had main breaker disconnect & emergency stop button. Service disconnect not required. | 177 CES | |
| 6 | 06-May-20 | Is the Cable Reel to be supplied by the contractor or is GFCI? | ||||
| If the Contractor is to supply the cable reel, what is the length and size of the cable? | Cable Reel is contractor supplied. |
Remainder of Question under review by Government
| 7 | 06-May-20 | 08-May-20 | What is the height shelters? | Shelter As-Built drawings with dimesions & elevations were posted to beta.SAM.gov in Amendment 02 on May 5th. | 177 MSC |
| 8 | 06-May-20 | 08-May-20 | I don’t see the video portion of yesterdays site visit. Is that going to be up loaded to the beta.sam.gov site? | The video of the Pre-Bid Video Confernence will not be posted. The Power Point Presentation & Virtual Site Visit pictures were posted to beta.SAM.gov in Amendment 02 Attachment 13 | 177 MSC |
| 9 | 08-May-20 | Which model of the Hannay CR6600 Series cord reel is required? i.e. Manual driven, Electric driven, Air driven or Hydraulic driven? | |||
| 10 | 08-May-20 | Is the government supplying the cable assembly and MS 25486-17 Cord end for the cable reel? | |||
| 11 | 08-May-20 | Will the 1st POD be empty of aircraft, thus allowing contractor to use as a lay down or storage area? | The contractor will only have access to one shelter at a time. |
One shelter will be empty at a time and designated at the Contractor's work area. Only the shleter that the Contractor is working in will be allowed as a laydown & sotrage area. All euipment & material must be moved to the next shelter after completion of the first.
The 2 shelters not being worked in at the time will be restricted for access & use by the contractor. 177 MSC
| 177 CES |
| 177 MSC |
| A&E |
| End User |
| Other |