DCFT 102008 RFI Response 3.docx

DOCX document 14 KB Posted

Attached to
183 CES Repair CRF Building P-17
Solicitation number
W50S7U-21-B-0001
Issued by

About this file

This document contains questions and responses regarding a federal solicitation for repair work on Building P-17 at a Civil Engineering Squadron facility. The solicitation requests clarification on insulation and window requirements for the building, seeking confirmation of a total R-value of R-38 as indicated in the drawings rather than the lower R-30 specified. It also asks for confirmation of appropriate light transmission levels of 17% for fiberglass sandwich wall panels rather than the 0.17% listed in the specification. Prior projects using similar panels had U-factors of 0.23 and light transmission of 17%, which is provided as the basis of design. Dimensional details and framing requirements are also sought for the curtainwall system infilling an exterior wall opening between cast-in-place stem walls and insulated metal panels.

View the file

Other files

File Type Posted
Bid Opening Sign in.pdf PDF
Bid Opening Report- Repair CRF Building 17 W50S7U-21-B-0001.pdf PDF
W50S7U-21-B-0001-0001 Amendment 0001.pdf PDF
SECTION 074213.13 - FORMED METAL WALL PANELS.pdf PDF
DCFT 102008 RFI Repsonse 4 Roof and Wall Panels Sec 07413.13.docx DOCX document
DS Boot 2.jpg JPG image
DS Boot 3.jpg JPG image
DCFT 102008 RFI Response 3 - Door Hardware Sets.docx DOCX document
DS Boot 1.jpg JPG image
009113_1 fl - addenda_No1.pdf PDF
61650_Arch_amerzTDZYW-183WG-2090209.png PNG image
009113_2 fl - addenda_No2.pdf PDF
61650_Arch_amerzTDZYW-4-1309292.JPG JPG image
61650_Arch_amerzTDZYW-fsb-fdg-jv-logo-2ver-2090207.png PNG image
61650_Arch_amerzTDZYW-3-1309490.JPG JPG image
DCFT 102008 - RFI-RESPONSE 2.docx DOCX document
61650_Arch_amerzTDZYW-2-1309322.JPG JPG image
61650_Arch_amerzTDZYW-6-1309001.JPG JPG image
61650_Arch_amerzTDZYW-5-1307452.jpg JPG image
61650_Arch_amerzTDZYW-1-1151913.JPG JPG image
123661.16 - SOLID SURFACING COUNTERTOPS.pdf PDF
RFI Response 1 W50S7U-21-B-0001.pdf PDF
A-001.pdf PDF
AD-101.pdf PDF
AE-310.pdf PDF
AE-103.pdf PDF
AE-311.pdf PDF
AE-601.pdf PDF
102800 - TOILET_ BATH_ AND LAUNDRY ACCESSORIES.pdf PDF
AE-301.pdf PDF
AE-401.pdf PDF
105113 - METAL LOCKERS.pdf PDF
090690 - COLOR SCHEDULE.pdf PDF
009113_3 fl - addenda_No3.pdf PDF
A-002.pdf PDF
P17 Reference Civil_Struct_Arch Dwgs Binder.zip ZIP file
Site Visit Sign-In Sheet CES Repair CRF P-17.pdf PDF
Site Visit Slides - CES Repair CRF P-17.pdf PDF
P17 Reference Canopy Door Dwgs Binder.zip ZIP file
P17 Reference Mech_Elect Dwgs Binder.zip ZIP file
SF 1705.pdf PDF
W50S7U-21-B-0001 -Solicitation - Repair Centralized Repair Facility Building P-17.pdf PDF
SOW - 102008 Final.pdf PDF
Show all 43

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Specification Section 072100 indicates a 2 layer insulation system: 4” R-value of R-11, 8” R-value of R-19 for a total R-value of R-30. Drawing sheets A310 and A311 indicate an R-value of R-38. The specification appears to have an incorrect R-value for 4” insulation, has an R-value of R-13 and 8” insulation has an R-value of R-25 for a total of R-38. Please clarify what R-Value and insulation thickness is intended.

Please provide an R-value of R-38 as indicated in the drawings. EJM/ILANG

1. The Specification Section 084523 is calling for a 4” thermally broken wall system, but the listed U-factor of 0.53 would result in no insulation within the panel. They also list a light transmission of 0.17%, which I am assuming should read as 17%. That light transmission would be met with some insulation in the panel (U-factor of 0.11 and light transmission of 17%). No insulation would result in a light transmission of 40%. We believe this project should have insulation within the panel, but can the Govt. confirm the performance they are looking for? Also, the panels require an MCR Factor of 85, which would require insulation within the panel, but the windows have a U-factor of 0.35. Please confirm the requirements of the wall system and windows.

Light transmission should read 17%. Previous projects that have included these panels have had LT of 17% and U-factor of 0.23. Use this as basis of design and product will need to be submitted for approval during construction. EJM/ILANG

1. On the West elevation, the plans do not have jamb details for the curtainwall, but it appears the opening should be one complete opening measuring 60’ wide x 18’ tall, notched around the service door (14’ height), then notched around the overhead door (9’-2” height), then back to full height of 18’ tall. Is this correct? There are no dimensions, but the section cut appears to show support by others at the midspan and then one more maybe 4’ from the head. Please clarify requirements or provide additional details.

Please see S-101 for column locations at the infill and 2/S-301 for framing dimensions at the infilled wall. Coordinate fiberglass sandwich panels and glazing framing with these dimensions. The curtainwall infills the entire opening between the cast-in-place stem wall and insulated metal panels and is notched around the OH door, 100F, and door 100A. EJM/ILANG

File details come from the government source that posted it. Updated .