009113_2 fl - addenda_No2.pdf
PDF 83 KB Posted
- Attached to
- 183 CES Repair CRF Building P-17
- Solicitation number
- W50S7U-21-B-0001
- Issued by
-
Department of the Army National Guard
About this file
This addendum pertains to a solicitation for repair work on CRF Building P-17 at the 183rd Air National Guard Wing in Springfield, Illinois. The addendum revises specification sections and drawings for solicitation number W50S7U-21-B-0001, which seeks bids for repairs to correct deficiencies in the building's envelope and mechanical, electrical and plumbing systems. Bids are due on the date specified in the solicitation and the Department of the Army National Guard is the contracting agency. Revisions include adding a required sustainability submittal to the schedule of material submittals and documentation of Energy Star compliance for downlights.
View the file
Other files
Show all 43
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DCFT #102008
Hanson #13D0027004
009113.2 - 1 009113.2
ADDENDA NO. 2
DOCUMENT 009113.2 – ADDENDA NO. 2
1.1 PROJECT INFORMATION
A. Repair CRF Building P-17
Illinois Air National Guard, 183D Wing
Abraham Lincoln Capital Airport, Springfield, IL
IL ANG Project No. DCFT102008
B. Prepared by: Hanson Professional Services Inc.
1525 South Sixth Street
Springfield, IL 62703
Phone: 217.788.2450
Hanson Project No. 13D0027004
C. Prepared on Behalf of: FSB Federal Design Group JV
5801 Broadway Extension, Suite 500
Oklahoma City, OK 73118-7436
Contract No. W9113L-16-D-005
Delivery Order 9E01
Web Site: www/fsb-ae.com
D. Date of Addendum: 9/3/2020.
1.2 NOTICE TO BIDDERS
A. This Addendum is issued to all registered plan holders pursuant to the Conditions of the Contract. This Addendum serves to clarify, revise, and supersede information in the Project Manual, Drawings, and previously issued Addenda as noted below. Portions of the Addendum affecting the Contract Documents will be incorporated into the Contract by enumeration of the Addendum in the Government/Contractor Agreement.
B. The Bidder shall acknowledge receipt of this Addendum in the appropriate space on the Bid Form.
C. The date for receipt of bids is unchanged by this Addendum, at same time and location.
DCFT #102008
Hanson #13D0027004
009113.2 - 2 009113.2
ADDENDA NO. 2
1.3 REVISIONS TO DIVISIONS 01 - 49 SPECIFICATION SECTIONS
A. Specification Section 013300 – PFOIL Form 341Schedule of Material Submittals:
1. Line 564: Add an “S” to the Sustainability Submittals column.
B. Specification Section 265119 LED Interior Lighting, paragraph 1.3.B:
1. Paragraph 1.3.B: Add the following as new item 6:
“6. Documentation of Energy Star Compliance for downlights, “S.”
END OF DOCUMENT 009113.2
| 1.1 PROJECT INFORMATION |
| A. Repair CRF Building P-17 |
| Illinois Air National Guard, 183D Wing |
| Abraham Lincoln Capital Airport, Springfield, IL |
| IL ANG Project No. DCFT102008 |
| B. Prepared by: Hanson Professional Services Inc. |
| 1525 South Sixth Street |
| Springfield, IL 62703 |
| Phone: 217.788.2450 |
| Hanson Project No. 13D0027004 |
| C. Prepared on Behalf of: FSB Federal Design Group JV |
| 5801 Broadway Extension, Suite 500 |
| Oklahoma City, OK 73118-7436 |
| Contract No. W9113L-16-D-005 |
| Delivery Order 9E01 |
| Web Site: www/fsb-ae.com |
| D. Date of Addendum: 9/3/2020. |
| 1.2 NOTICE TO BIDDERS |
| A. This Addendum is issued to all registered plan holders pursuant to the Conditions of the Contract. This Addendum serves to clarify, revise, and supersede information in the Project Manual, Drawings, and previously issued Addenda as noted below. Por... |
| B. The Bidder shall acknowledge receipt of this Addendum in the appropriate space on the Bid Form. |
| C. The date for receipt of bids is unchanged by this Addendum, at same time and location. |
| 1.3 REVISIONS TO DIVISIONS 01 - 49 SPECIFICATION SECTIONS |
| A. Specification Section 013300 – PFOIL Form 341Schedule of Material Submittals: |
| 1. Line 564: Add an “S” to the Sustainability Submittals column. |
| B. Specification Section 265119 LED Interior Lighting, paragraph 1.3.B: |
| 1. Paragraph 1.3.B: Add the following as new item 6: |
| “6. Documentation of Energy Star Compliance for downlights, “S.” |