This document contains pre-bid questions and answers related to solicitation number W50S7U-21-B-0001 for repair work at CRF Building P-17. The solicitation is issued by the 183rd Civil Engineer Squadron of the Illinois Air National Guard on behalf of the Department of the Army National Guard.

The scope of work involves demolishing the existing fire alarm and mass notification system and installing a new system throughout the building. Other work includes asbestos abatement of roof and wall panels, repair of the HVAC system including furnishing factory controls for new units, electrical work including furnishing and installing branch circuits, and miscellaneous structural steel framing. Bidders must provide unit pricing for hazardous material testing, additions or deductions to allowances, and various construction tasks and materials. The pre-bid questions and answers clarify responsibilities for specialty equipment, qualifications, and other requirements.

View the file

Other files

File Type Posted
Bid Opening Sign in.pdf PDF
Bid Opening Report- Repair CRF Building 17 W50S7U-21-B-0001.pdf PDF
W50S7U-21-B-0001-0001 Amendment 0001.pdf PDF
SECTION 074213.13 - FORMED METAL WALL PANELS.pdf PDF
DCFT 102008 RFI Repsonse 4 Roof and Wall Panels Sec 07413.13.docx DOCX document
DCFT 102008 RFI Response 3.docx DOCX document
DS Boot 2.jpg JPG image
DS Boot 3.jpg JPG image
DCFT 102008 RFI Response 3 - Door Hardware Sets.docx DOCX document
DS Boot 1.jpg JPG image
009113_1 fl - addenda_No1.pdf PDF
61650_Arch_amerzTDZYW-183WG-2090209.png PNG image
009113_2 fl - addenda_No2.pdf PDF
61650_Arch_amerzTDZYW-4-1309292.JPG JPG image
61650_Arch_amerzTDZYW-fsb-fdg-jv-logo-2ver-2090207.png PNG image
61650_Arch_amerzTDZYW-3-1309490.JPG JPG image
61650_Arch_amerzTDZYW-2-1309322.JPG JPG image
61650_Arch_amerzTDZYW-6-1309001.JPG JPG image
61650_Arch_amerzTDZYW-5-1307452.jpg JPG image
61650_Arch_amerzTDZYW-1-1151913.JPG JPG image
123661.16 - SOLID SURFACING COUNTERTOPS.pdf PDF
RFI Response 1 W50S7U-21-B-0001.pdf PDF
A-001.pdf PDF
AD-101.pdf PDF
AE-310.pdf PDF
AE-103.pdf PDF
AE-311.pdf PDF
AE-601.pdf PDF
102800 - TOILET_ BATH_ AND LAUNDRY ACCESSORIES.pdf PDF
AE-301.pdf PDF
AE-401.pdf PDF
105113 - METAL LOCKERS.pdf PDF
090690 - COLOR SCHEDULE.pdf PDF
009113_3 fl - addenda_No3.pdf PDF
A-002.pdf PDF
P17 Reference Civil_Struct_Arch Dwgs Binder.zip ZIP file
Site Visit Sign-In Sheet CES Repair CRF P-17.pdf PDF
Site Visit Slides - CES Repair CRF P-17.pdf PDF
P17 Reference Canopy Door Dwgs Binder.zip ZIP file
P17 Reference Mech_Elect Dwgs Binder.zip ZIP file
SF 1705.pdf PDF
W50S7U-21-B-0001 -Solicitation - Repair Centralized Repair Facility Building P-17.pdf PDF
SOW - 102008 Final.pdf PDF
Show all 43

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DCFT 102008 – Repair CRF, Building 17 Pre-bid RFI’s – Set 2

Schwartz Construction Group

1. In the project file on Beta.Sam.Gov, for addendum 1, I only find drawings P601 and H601, but no actual addendum document. Are pages P601 and H601 the entirety of Addendum 1?

Addenda 1 includes sheets P601 and H601 as well as spec section 009113.1 and changes listed therein. Addenda 2 consist of only spec 009113.2 and changes listed therein. EJM/ILANG & MFlatt/Hanson

1. In the project file on Beta.Sam.Gov, I find the two pages mentioned above for addendum 1, and I find information for addendum3, but no mention of addendum 2. Is there and addendum 2?

See above for Addenda 1 and 2. Addendum 3 will be issued during the bidding based on other contractor pre-bid RFI’s. EJM/ILANG

1. In the responses to questions that have been posted to date regarding the air barrier, the response has been that the plan notes for the air barrier refer only to testing, however the scope of this project is such that the building is being stripped down to the frame, so there will be no existing air barrier left to test. If a new air barrier is to be installed and then tested at completion, a product will need to be specified. Please further clarify this item.

Refer to the revised general note on A-002 and AE-301 in addendum #3 that states, “According to UFC 3-101-01 Paragraph 3-6.3, hangar bay and maintenance bay facilities require air barrier inspection only. Contractor shall notify contracting officer when inspection is scheduled.” FSB/AMertz

1. Can the project bid date be extended? To allow more time to digest forthcoming addenda and answers to questions?

Bid date will not be extended. EJM/ILANG

Alpha Controls

1. DOAS-1 and OAP-1 – Will these units to come with a factory BACnet interface, or will the controls be field installed by Alpha Controls. Alpha can’t make any programming changes to factory supplied DDC controllers for the sequences or points lists on H-503 and H-507.

DOAS-1 shall be provided with factory supplied BACnet controller capable of providing the points and sequences on H-507.

OAP-1 shall be provided with factory supplied BACnet controller capable of providing the points and sequences on H-503.

The outdoor air temperature is required by both pieces of equipment for the referenced sequences. Outdoor air temperature sensor to be provided by controls contractor in the location shown on sheet V-201. Both units shall be enabled/disabled through the new building automation system. - Hanson/JF

2. MAU-1 – Will this unit to come with a factory BACnet interface, or will the controls be field installed by Alpha Controls. Alpha can’t make any programming changes to factory supplied DDC controllers for the sequences or points lists on H-507.

MAU-1 shall be provided with factory supplied BACnet controller capable of providing the points and sequences on H-507. - Hanson/JF

3. FCU-1 & 2 – Will these units to come with a factory BACnet interface, or will the controls be field installed by Alpha Controls. Alpha can’t make any programming changes to factory supplied DDC controllers for the sequences or points lists on H-501. The 238130.2.4.C.1 VRF system indicates the VRF FCUs are to connect with the iTouch Manager installed in the P1 building. Will a new iTouch Manager, or similar integration manager, be provided by the successful VRF contractor for P17?

FCU-1 & 2 shall be provided with factory supplied BACnet controller capable of providing the points and sequences on H-503.

Integration of building controls for P17 are not required with building P1. Specification sections 238130.2.4.B and 238130.2.4.C can be removed. - Hanson/JF

4. FCU-3, 4, 5 & 6 on H-504 indicates the units will come with a BACnet interface. Is the BACnet controller to be provide by Alpha Controls or by the unit manufacturer? The H-601 schedule and the FCU specification doesn’t mention BACnet controls to be provided by the unit manufacturer.

FCU-3, 4, 5, & 6 shall be provided with factory supplied BACnet controller capable of providing the points and sequences on H-504.

The following note shall be added to the MINI-SPLIT FAN COIL SCHEDULE and MINI-SPLIT UNIT SCHEDULE on sheet H-601: “UNIT SHALL BE EQUIPPED WITH PROGRAMMABLE DDC CONTROLLER CAPABLE OF COMMUNICATING WITH BACNET CONTROLS. REFER TO SHEET H-504 FOR ADDITIONAL REQUREMENTS”. - Hanson/JF

Dakota Intertek Corp.

1. Fire alarm & mass notification system

a. Regarding the new fire alarm/MNS system, are we supposed to supply a new Monaco transceiver & antennae only?

The project scope is to demolish the existing FA / MNS system and provide a new fire alarm and mass notification system throughout the entire building. Furnish and install all fire alarm components needed to make the system for this building fully functional with the existing base infrastructure. See section 283176 paragraph 1.1 A. 1. The fire alarm communication panel on FA-701 is the Monaco Transceiver (Transmitter). - FSB/Gus Gagliardi

b. Please confirm there are no requirements to update any existing Monaco head-end computer or software because the fire alarm contractor states he cannot provide that equipment.

The design intent is to provide the equipment for the renovated building only and make it fully functional. The base’s receiving head-end equipment is not expected to be upgraded or updated for this project. -FSB/Gus Gagliardi

2. Sheet AE-103, Note 12 states 60”x30” desk. Are we to provide any furniture?

Contractor will not provide this furniture. For information only. Relevant sheet keynotes on AE-103 were revised in addendum #3 to indicate furniture as Government Furnished- Government Installed (GFGI). EJM/ILANG & FSB/AMertz

3. Is there a government furnished equipment list?

There is no Government furnished equipment that the contractor is responsible for installing. EJM/ILANG

On sheet AE-104, equipment shown is Government Furnished- Government Installed except indicated hoist beams, jib crane, and emergency eyewash stations, which are Contractor Furnished- Contractor Installed. GFGI Equipment is shown for information only to coordinate power and compressed air requirements. FSB/AMertz

4. Is the equipment list shown on AE-104 provided by the government and installed by the contractor?

Equipment shown on sheet AE-104, Specialty Equipment Schedule 1 & 2, is Government Furnished – Government Installed excepting designated hoist beams/hoists and jib crane, and emergency eyewash stations which are Contractor Furnished-Contractor Installed. Specialty Equipment Schedules are shown for information only regarding power and compressed air requirements coordination. EJM/ILANG & MFlatt/Hanson

5. Sheet AE-601, Detail 1, Window Types W5, W6 and W7 appear to show translucent wall panels as in Detail 2, but there are no call-out notes to indicate that those windows are translucent wall panels. Can you confirm Detail 1 windows are translucent wall panels as well? Can you also provide specifications?

Window W5 is a combination of clear glass on the bottom with translucent above. W6 is only the translucent above a door and W7 is only translucent above the OH door. Refer to elevations on AE-201. See spec section 084523. EJM/ILANG

6. Sheet A-001, Typical Accessibility Signage Mounting Heights references AG101 for American Airlines Signage Standards. Can you provide this sheet and the signage requirements?

The reference to AA Signage is a typo. Please ignore. EJM/ILANG

7. Are any of the addenda issued after the original solicitation package considered to be “amendments” that need to be acknowledged on the SF1442? Should the documents posted on beta.sam on 3/25/2021 be considered Addendum No. 2?

No acknowledgment is required. Yes, these documents are part of Add 2. EJM/ILANG

Korte & Luitjohan Contractors:

1. Paragraph 1.8 of the “Scope of Work” states that the hours of operation are from 7:30 AM – 5:00 PM with alternating Fridays off, and that the contractor shall perform their services between these hours.Would it be possible to allow the contractor to start at 7:00 AM and work five days per week every week?

Yes, the contractor can start at 7am and work 7 days a week. EJM/ILANG

2. Paragraph 1.5 of the “Scope of Work” states that the contractor shall develop a Quality Control Plan which shall be delivered with the proposal. Can this be submitted by the low bidder sometime after the bid date?

Yes, this will be submitted by the contract awardee. EJM/ILANG

3. Paragraph 1.11 of the “Scope of Work” states that the security policies and procedures can be obtained from the KO or COR. Could you please provide these policies and procedures?

These will be provided to the contract awardee during pre-construction meeting. These are rules for operating on the base and procedures for entering and exiting. Should not affect bidding. EJM/ILANG

4. Paragraph 1.11.2 of the “Scope of Work” states that all contractor employees shall complete Level 1 AT/FT training. Could you provide information regarding how much time this training will take to complete, and whether it is web-based or conducted on-site?

AT/FP training is web-based and directions will be given during pre-construction meeting. Will take approximately 1 hour to complete. Could also be completed in person at one time prior to work starting. EJM/ILANG

5. Paragraph 52.222-23,(b) of the “Solicitation, Offer, and Award” Scope of Work” states that there are goals for minority and female participation. Could you identify which certifying agencies you will recognize?

There will be no certifying agency for this but it is a Government- wide goal. EJM/ILANG

6. Sheet AE-104 includes a listing of Specialty Equipment. Please confirm that the contractor is not required to purchase and/or install this equipment.

Equipment shown on sheet AE-104 is Government Furnished – Government Installed excepting designated hoist beams/hoists and jib crane, and emergency eyewash stations which are Contractor Furnished-Contractor Installed. It is shown for information only regarding power and compressed air requirements. EJM/ILANG & MFlatt/Hanson

Phelan Construction

1. Please confirm what door types SFGX and SFGI are. Types SFGX and SFGI not shown on door schedule on AE-601.

SFGX should be revised to SGX, and exterior steel door with glazing. SGI should be added to the door types on AE-601. This will be an interior steel door with glazing. – FSB/AMertz

1. Please provide specifications for the Air Barrier System. A-002 General Note A refers to spec sections 07 05 23 and 07 27 10.0010 for all Air Barrier System and Testing Requirements, however spec section is not in the manual.

The requirements of sections 07 05 23 and 07 27 10.0010 are not required; the general notes on A-002 and AE-301 were revised in addendum #3 to state, “According to UFC 3-101-01 Paragraph 3-6.3, hangar bay and maintenance bay facilities require air barrier inspection only. Contractor shall notify contracting officer when inspection is scheduled.”-FSB/AMertz

1. Please confirm who is responsible for furnishing and installing the Specialty Equipment shown on Schedules 1 and 2 on AE-104.

Equipment shown on sheet AE-104 is Government Furnished – Government Installed excepting designated hoist beams/hoists and jib crane, and emergency eyewash stations which are Contractor Furnished-Contractor Installed. Equipment is shown for information only regarding power and compressed air requirements. EJM/ILANG & MFlatt/Hanson

1. Please confirm how many representatives the General Contractor is required to have at the project site during construction.

There must be at least 1 person representing the GC on site at all times that there is work occurring. EJM/ILANG

1. Regarding the Photographic Documentation, the specs call for "An individual who has been regularly engaged as a professional photographer of construction projects for not less than three years". Does a GC's representative who has been performing this task for different projects for over ten years qualify as the photographer for this project?

Yes, this person would qualify. EJM/ILANG

1. Regarding the Photographic Documentation, the specs call for "Construction Webcam Service Provider: A firm specializing in providing photographic equipment, web-based software, and related services for construction projects, with record of providing satisfactory services similar to those required for Project.” Please clarify if this is a requirement for installation of cameras at the project site by the GC.

There is no requirement for this. Would be used during O&M training or other video documentation during construction by the GC. EJM/ILANG

1. Per Survey prepared by Environmental Design International there is 12,750 SF of ACM roof caulk. Is abatement contractor responsible for tear-off of all corrugated metal panels on roof?

The abatement contractor may remove the panels after ACM caulk has been abated. However, panel removal may be performed by others once the regulated area has been released to the general contractor. Alternatively, abatement can be done at ground level. The ACM caulk is not friable; the abatement contractor may elect to abate the panels in this manner (in a regulated area). Alternatively, the abatement contractor may elect to dispose of all panels as asbestos-contaminated waste. – EDI/FM

8. Are all corrugated metal roof panels considered to be asbestos containing material?

Only the seam sealants are considered asbestos-containing. Once abated, metal panels can be recycled. – EDI/FM

9. Drawing HZ-002 lists entire exterior (walls, roof, etc.) as having suspect ACM caulk. Is abatement contractor responsible for removal of all exterior wall corrugated metal?

All caulk on roof panel seams, wall panel seams, louvers, exhaust fans, and doors and windows and any other sealed openings are considered to be asbestos-containing and must be abated. The abatement contractor may remove the panels after ACM caulk has been abated. However, panel removal may be performed by others once the regulated area has been released to the general contractor. Alternatively, abatement can be done at ground level. The ACM caulk is not friable; the abatement contractor may elect to abate the panels in this manner (in a regulated area). Alternatively, the abatement contractor may elect to dispose of all panels as asbestos-contaminated waste. – EDI/FM

10. Asbestos abatement spec note 7 says work to be performed in negative pressure containment. Does this apply to exterior corrugated metal and caulk removal by abatement contractor?

The use of drop cloths and regulated areas is acceptable on the exterior. Abatement design and oversight is delegated to the contractor per the specifications. – EDI/FM

11. Is abatement contractor responsible for hiring of 3rd party air monitoring, daily oversight, project design?

Yes, The general contractor or the abatement contractor must retain the third party air sampling professional. Abatement design 3rd party air monitoring and oversight is delegated to the contractor per the specifications. – EDI/FM

12. Is abatement contractor responsible for providing daily oversight/air monitoring during exterior asbestos abatement?

Air monitoring is not required for exterior abatement. The general contractor or the abatement contractor must retain the 3rd party oversight professional. – EDI/FM

13. What is the proposed phasing of the project? Are all metal walls/roof with ACM caulk to be removed prior to other work beginning?

Project phasing is the responsibility of the general contractor. – EDI/FM

The Mantle Group

1. Please clarify if the abatement contractor will be removing the metal siding on the building. In the inspection report, sealant on the metal siding tested negative for ACM.

All caulk on roof panel seams, wall panel seams, louvers, exhaust fans, and doors and windows and any other sealed openings are considered to be asbestos-containing and must be abated. The abatement contractor may remove the panels after ACM caulk has been abated. However, panel removal may be performed by others once the regulated area has been released to the general contractor. Alternatively, abatement can be done at ground level. The ACM caulk is not friable; the abatement contractor may elect to abate the panels in this manner (in a regulated area). Alternatively, the abatement contractor may elect to dispose of all panels as asbestos-contaminated waste. – EDI/FM

1. The lead liner/sheeting in the X-Ray room is not regulated, will the abatement contractor need to perform the selective demolition to access the lead sheeting and dispose of or recycle the lead? Or can the demolition contractor perform all the demolition needed and set aside the lead sheeting for recycling and or disposal?

The demolition contractor can perform the selective demolition to access the lead liner/sheeting, remove and separate it, and dispose of or recycle the lead sheeting. While IDPH does not regulate the liner removal, OSHA regulations still apply. Coordinate with the general contractor. – EDI/FM

1. Will the ASP/APM need to be on site for duration of the abatement activities?

Specification Section 028213 indicates the APM/ASP may be a single person with licensing as both an asbestos Project Manager and asbestos Air Sampling Professional. If contractor chooses to employ one single person as their APM/ASP, this person must be present throughout the duration of the abatement activities. If an ASP-licensed only individual is engaged, the ASP must only be present to provide asbestos air sampling during Category I asbestos abatement. – EDI/FM

1. Specification Section 012200 addresses multiple unit prices. Please clarify if these are required with our proposal and if so, if there will be a Unit Price Form provided or if we are to make our own form?

Yes, unit prices are required with the proposal. Utilize the attached unit price bid form corresponding to the schedule in 012200. Additionally, utilize the attached allowances bid form corresponding to the schedule in 012100. – MFlatt/Hanson

1. Specification Section 033000 Part 3.11.D – Please clarify what new slab on grade is to receive a dry-shake floor hardener finish.

Dry-shake floor hardener finish is not required for this project. RFiorito/Hanson

1. Specification Section 033000 Part 3.12 – Please clarify what slab on grade is to receive a polished finish.

Polished finish is not required for this project. R.Fiorito/Hanson

1. Specification Section 051200 Part 1.7.A – Fabricator Qualifications – Since most of the steel framing work associated with this project is miscellaneous can the AISC Certification be eliminated?

AISC Certification will not be eliminated. – Rfiorito/Hanson

1. Specification Section 051200 Part 1.7.B – Installer Qualifications – Since most of the steel framing work associated with this project is miscellaneous can the AISC Certification be eliminated?

AISC Certification will not be eliminated. – Rfiorito/Hanson

1. Specification Sections 089000 & 239119 – Louvers – Ventilation General Note 17 on V-001 states that the Louvers are by the Ventilation Contractor. Details on V-502 state that the louvers are by the General Contractor. We understand that the General Contractor is ultimately responsible to make sure the louvers are covered and to be provided, but please clarify who is to provide louvers so that Government doesn’t have to paid for them after the fact.

Louvers are to be provided by the Ventilation Contractor. Coordination between Ventilation and General contractor is required for louver installation and bidding/procurement. - Hanson/JF

UNIT PRICE FORM:

BID INFORMATION

Bidder: ____________________________________________________.

Retain and edit "Prime Contract" Paragraph below for multiple-prime contract.

Prime Contract: _____________________________________________.

Project Identification: DCFT102008 Repair CRF Building P-17 Project Location: Abraham Lincoln Capital Airport, Springfield, IL.

Owner: Illinois Air National Guard, 183D Wing:

Contracting Officer: CMSgt Brent Keller.

Contracting Officer’s Technical Representative: Capt. Erick Marks, Deputy BCE.

Architect/Engineer: Hanson Professional Services Inc. on behalf of FSB Federal Design Group JV.

BID FORM SUPPLEMENT

This form is required to be attached to the Bid Form.

Retain option in first paragraph below when the Unit-Price Allowance quantities are included in Section 012100 "Allowances." Revise statement below if bidders are asked to provide separate prices for additions to and deductions from quantity allowances.

The undersigned Bidder proposes the amounts below be added to or deducted from the Contract Sum on performance and measurement of the individual items of Work.

If the unit price does not affect the Work of this Contract, the Bidder shall indicate "NOT APPLICABLE."

UNIT PRICES PER SECTION 012200

Unit-price descriptions below are model text for illustration purposes.

Unit-Price No. 1: Lead Based Paint Removal Unit of Measurement: Additive cost per square foot of steel surface.

Additive _________________dollars ($____________) per unit.

Unit of Measurement: Deductive cost per square foot of steel surface.

Deductive_______________ dollars ($____________) per unit.

Unit-Price No. 2: Asbestos Containing Material Removal Square foot of surface of asbestos containing flooring and mastic materials.

Additive _________________dollars ($____________) per unit.

Square foot of surface of asbestos containing ceiling tile.

Additive _________________dollars ($____________) per unit.

Square foot of metal roofing panels/cladding with adhered asbestos containing materials.

Additive _________________dollars ($____________) per unit.

Square foot of metal wall panels/cladding with adhered asbestos containing materials.

Additive _________________dollars ($____________) per unit.

Lineal foot of asbestos containing pipe insulation.

Additive _________________dollars ($____________) per unit.

Lineal foot of asbestos containing sealant/caulking.

Additive _________________dollars ($____________) per unit.

Square foot of surface of asbestos containing flooring and mastic materials.

Deductive________________ dollars ($____________) per unit.

Square foot of surface of asbestos containing ceiling tile.

Deductive________________ dollars ($____________) per unit.

Square foot of metal roofing panels/cladding with adhered asbestos containing materials.

Deductive________________ dollars ($____________) per unit.

Square foot of metal wall panels/cladding with adhered asbestos containing materials.

Deductive________________ dollars ($____________) per unit.

Lineal foot of asbestos containing pipe insulation.

Deductive________________ dollars ($____________) per unit.

Lineal foot of asbestos containing sealant/caulking.

Deductive________________ dollars ($____________) per unit.

Unit-Price No. 3: Hazardous Material Testing Unit of Measurement: Additive cost per Lead Based Paint test and report.

Additive _________________dollars ($____________) per unit.

Unit of Measurement: Deductive cost per Lead Based Paint test and report.

Deductive_______________ dollars ($____________) per unit.

Unit of Measurement: Additive cost per Asbestos Containing Material sample, test and report.

Additive _________________dollars ($____________) per unit.

Unit of Measurement: Deductive cost per Asbestos Containing Material sample, test and report.

Deductive_______________ dollars ($____________) per unit.

Unit of Measurement: Additive cost per PCB test and report.

Additive _________________dollars ($____________) per unit.

Unit of Measurement: Deductive cost per PCB test and report.

Deductive_______________ dollars ($____________) per unit.

Unit-Price No. 4: Miscellaneous In-Place Structural Steel Framing Unit of Measurement: Additive cost per pound of miscellaneous in-place structural steel.

Additive _________________dollars ($____________) per unit.

Unit of Measurement: Deductive cost per pound of miscellaneous in-place structural steel.

Deductive _________________dollars ($____________) per unit.

Unit-Price No. 5: Miscellaneous In-Place Light-Gauge Steel Framing (C or Z-Shaped Girts and Purlins) Unit of Measurement: Additive cost per foot of miscellaneous, in-place 12 gauge, C or Z-shaped girts or purlins.

Additive _________________dollars ($____________) per unit.

Unit of Measurement: Deductive cost per foot of miscellaneous, in-place 12 gauge, C or Z-shaped girts or purlins.

Deductive _________________dollars ($____________) per unit.

Unit-Price No. 6: 20 Amp, Single Phase (L-N plus ground) Branch Circuit Unit of Measurement: Additive cost per linear foot of branch circuit inclusive of all items.

Additive _________________dollars ($____________) per unit.

Unit of Measurement: Deductive cost per linear foot of branch circuit inclusive of all items.

Deductive _________________dollars ($____________) per unit.

Unit-Price No. 7: 20 Amp, 3 Phase (3 wire plus ground) Branch Circuit Unit of Measurement: Additive cost per linear foot of branch circuit inclusive of all items.

Additive _________________dollars ($____________) per unit.

Unit of Measurement: Deductive cost per linear foot of branch circuit inclusive of all items.

Deductive _________________dollars ($____________) per unit.

ALLOWANCE FORM:

BID INFORMATION

Bidder: ____________________________________________________.

Project Identification: DCFT102008 Repair CRF Building P-17 Project Location: Abraham Lincoln Capital Airport, Springfield, IL.

Owner: Illinois Air National Guard, 183D Wing:

Contracting Officer: CMSgt Brent Keller.

Contracting Officer’s Technical Representative: Capt. Erick Marks, Deputy BCE.

Architect/Engineer: Hanson Professional Services Inc. on behalf of FSB Federal Design Group JV.

BID FORM SUPPLEMENT

This form is required to be attached to the Bid Form.

The undersigned Bidder certifies that Base Bid submission to which this Bid Supplement is attached includes those allowances described in the Contract Documents and scheduled in Section 012100 "Allowances."

SUBMISSION OF BID SUPPLEMENT

Respectfully submitted this ____ day of ____________,____________.

Submitted By:_______________________________(Insert name of bidding firm or corporation).

Authorized Signature:_______________________________________(Handwritten signature).

Signed By:______________________________________________(Type or print name).

Title:___________________________________(Owner/Partner/President/Vice President).

File details come from the government source that posted it. Updated .