This is a Standard Form 30 (SF 30) Amendment to Solicitation/Modification of Contract, issued on May 13, 2026, by the U.S. Air Force (W50S76 code, USAF SPFO Activity TXANG 136). The amendment modifies solicitation W50S7626QA001 dated May 3, 2026, with an effective date of May 13, 2026. The contracting officer is Donald Crabtree, and the document is administered from Fort Worth, Texas (76127-1672).

The amendment incorporates revision 1 to the B1672 (CLIN 0001) Plans and modifies clause 252.236-7001 (Contract Drawings and Specifications, Aug 2000). The modification updates the contract drawing and specification references to include the Statement of Work (DDPM262101-Alter CP and NDI-SOW dated 05032026) and two versions of drawings (DDPM262101_Alter CP and NDI_Plans dated 20260512 and 03272026). The clause establishes standard contractor responsibilities including immediate verification of all drawings upon receipt, notification of discrepancies to the Contracting Officer, and compliance with marked figures in preference to scale measurements. The clause specifies that omissions or misdescriptions in drawings do not relieve the contractor from performing the intended work as if fully and correctly described. All other terms and conditions of the original solicitation remain unchanged and in full force and effect.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Section I - Contract Clauses

Additional Information/Notes

The following clauses were modified:

252.236-7001 Contract Drawings and Specifications. Aug 2000 hereby reads as follows:

CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)

(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.

(b) The Contractor shall-

(1) Check all drawings furnished immediately upon receipt;

(2) Compare all drawings and verify the figures before laying out the work;

(3) Promptly notify the Contracting Officer of any discrepancies;

(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and

(5) Reproduce and print contract drawings and specifications as needed.

(c) In general--

(1) Large-scale drawings shall govern small-scale drawings; and

(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.

(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are

W50S7626QA0010001

customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.

(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:

Title File

Statement of Work (SOW)

DDPM262101-Alter CP and NDI-SOW (05032026)

Drawings

DDPM262101_Alter CP and NDI_Plans (20260512)

DDPM262101_Alter CP and NDI_Plans (03272026)

(End of clause)

W50S7626QA0010001

IDCode: J
Page: 1
Pages: 3
AmendNo: 0001
EffDate: 13 MAY 2026
ReqNo:
ProjNo: DDPM262101
IssCode: W50S76
AdmCode:
IssuedBy: W7N2 USPFO ACTIVITY TXANG 136

KO FOR TXANG DO NOT DELETE, 200 HENSLEY AVE BLDG 1672

FORT WORTH, TX 76127-1672

UNITED STATES

SHARON KRYWINSKI, EMAIL: SHARON.KRYWINSKI.1@US.AF.MIL TELEPHONE: 874-3308

AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: W50S7626QA001
SolDate: 03 MAY 2026
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: Off
OffrNoEx: 1
NoCopies: 1
ApprData: SEE SECTION G - CONTRACT ADMINISTRATION DATA
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: The purpose of this amendment is to incorporate revision 1 to the B1672 (CLIN 0001) Plans. See the summary of changes. All other terms and conditions remain the same.
ContNameTitle:
CoNameTitle: DONALD CRABTREE
ContDate:
CODate: 13 MAY 2026

File details come from the government source that posted it. Updated .