2. SOW - Hangar B1201 Air Handler (1).docx
DOCX document 539 KB Posted
- Attached to
- B1201 Air Handler Replacement Federal contract opportunity
- Solicitation number
- W50S6N25QA011
About this file
This Statement of Work (SOW) outlines requirements for the Alabama Air National Guard 187th Fighter Wing to replace a rooftop air handler on Main Hangar Building 1201 at Montgomery Air National Guard Base. The contractor must provide all personnel, equipment, supplies, materials and supervision to remove the existing 15,000-cfm air handler and install a new one with Johnson Controls that communicates with the Metasys computer in Civil Engineer Building 1801.
The period of performance is 60 days after notice to proceed, with work conducted Tuesday through Friday between 0700-1700 hours except federal holidays. The project requires escort access in controlled areas, disposal of materials off-site, and returning the site to original condition. The contractor must comply with installation security policies and background check requirements. A pre-bid conference and site walk-through with 187th CES personnel is required prior to contract award.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W50S6N25QA011.pdf | ||
| ductwork.jpg | JPG image | |
| Thermostat.jpg | JPG image | |
| Controls.jpg | JPG image | |
| Electrical Panel.jpg | JPG image | |
| Pages from Conformance Documents - drawings 2011 project.pdf | ||
| M0.1-M7.3 Drawings - 2022 renovation project.pdf | ||
| McQuay.jpg | JPG image | |
| W50S6N25QA011 RFI Responses.docx | DOCX document | |
| 2. SOW - Hangar B1201 Air Handler rev1.docx | DOCX document | |
| Site Visit Roster B1201 Air Handler.pdf | ||
| 18. J and A for Brand Name-Sole Source - Air Handler 1 Signed.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Hangar B1201 Air Handler
Alabama Air National Guard
187th FW 5187 Selma Hwy Montgomery, AL 36108
General Information The Air National Guard has a requirement to replace a rooftop air handler on Main Hangar Building 1201 at the 187th Fighter Wing. The work covered by this Statement of Work consists of furnishing all material, labor, equipment, and travel to make the needed repairs.
General Scope of Work:
The project is being managed from the 187th Civil Engineer Squadron (187th CES) and 187th Contracting offices located at Montgomery Air National Guard Base in Montgomery, Alabama. A contracting officer’s representative (COR) will be designated at the 187th CES.
Description of Work:
The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items needed to remove and replace the existing rooftop air handler on the south side of the hangar as defined below:
Remove existing rooftop air hander. See site plan below.
Procure and install new rooftop air hander, in kind. Existing unit is a 15,000-cfm air hander.
Air hander shall include Johnson Controls that communicates to the Metasys computer in the Civil Engineer Building 1801. Existing controls on existing air handler may be reused if compatible with the new air handler.
Procure and install roof flashing and sealants as required to prevent water infiltration.
Startup and check of proper operation once the work is completed.
Dispose of all demolished material and equipment off site.
Period of performance:
The period of performance shall be 60 days after notice to proceed following contract award.
Place and hours of Performance The contractor is responsible for conducting business between the hours of 0700-1700 hours Tuesday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings.
The project location is in a controlled area. The 187th CES will provide an escort for all contractor personnel within the controlled area.
If contractor desires to work on Monday’s prior coordination with the 187th CES will be required to obtain an escort to the work area.
The Contractor must at all times maintain an adequate workforce for the uninterrupted execution of all tasks defined within this SOW when the Government facility is not closed for the above reasons.
Recognized Holidays:
| New Year’s Day |
| Labor Day |
| Martin Luther King Jr.’s Birthday |
| Columbus Day |
| Washington’s Birthday |
| Veterans Day |
| Memorial Day |
| Thanksgiving Day |
| Juneteenth National Independence Day |
| Christmas Day |
Independence Day
Prior to the award of the contract the Contractor will attend a Pre-Bid Conference at a time and date determined by the 187th Contracting Office. During this conference the Contractor will visit the site and conduct a preliminary walk-through with 187th CES personnel. During the site visit, the Contractor will identify any issues that may conflict with or affect the outcome of the work. The Contractor is expected to include any cost required for the accommodation of such items within the original cost proposal.
Disposal Requirements:
The Contractor is responsible for the collection and disposal of all debris, rubble, residue and waste material generated in the execution of work under this contract. All such materials shall be disposed of at an off-base landfill by the CONTRACTOR. The CONTRACTOR is not permitted to deposit any such materials in base trash collection containers or at any on base location without prior approval of the Contracting Officer.
Existing Conditions:
The Contractor is responsible for returning all conditions of the site to the condition it was in prior to work beginning, to include but not limited to soils, grass, pavements, and utilities.
Security Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within Government controlled installation, facility, or area. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
For Contractors that do not require CAC, but require access to a DoD Facility and/or Installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 10-245, AFI 31-101 and AFMAN 31-113), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
Site Map
Air Handler Location image1.png image2.png