About this file

This document contains questions and answers related to solicitation number W15QKN-19-R-0013 for Load Assemble and Pack (LAP) of 155mm Modular Artillery Charge System (MACS) M231 and M232-series Propelling Charges. The solicitation seeks up to two firms to manufacture, load, assemble, pack and deliver the M231 and M232-series propelling charges for 155mm field artillery weapons under indefinite delivery/indefinite quantity production contracts with a maximum total value of $133,212,118.80. Key details include that the M231 is used singularly or in pairs for low zones and the M232-series is used in groups of 3 to 5 charges for high zones, scrap includes any damaged government furnished materials introduced to the production line, the combustible case classification is 1.4C, and lead times for government furnished energetics and combustible cases are as stated in Section H of the solicitation.

Response to Questions from Industry #2

View the file

Other files

File Type Posted
Att_0013_-_Sol_and_Contract_Qual_Requirements_RFP.DOCX DOCX document
W15QKN19R0013-0002.pdf PDF
W15QKN19R0013-0001.pdf PDF
W15QKN-19-R-0013_QA1.docx DOCX document
ACV00076_Square_Bell.pdf PDF
ACV00306_Side_Rail.pdf PDF
4326-50A_Rev_4_M232_Unit.pdf PDF
ACV00561_-_Unit_Load_Marking-F_(10).PDF PDF
ACV00304_Square_Bell_Restraint.pdf PDF
ACV00400_End_Bell_Restraint.pdf PDF
ACV00294_Lifting_Bar.pdf PDF
12972395_Igniter_Core_Bag_(5).pdf PDF
ACV00515_-_Welding_-_rev-_(9).pdf PDF
ACV00293_Lifting_Bar_Support_(7).pdf PDF
4326-20PM1012_Gen_Unit_(1).pdf PDF
12972394_Igniter_Core_and_End_Bag_Assy.pdf PDF
AC200000423_-_CARC_Paint_-_J_(6).PDF PDF
AC200000453_Aligning_Lug.pdf PDF
4326-50A_Rev_4_M232_Unit_(3).pdf PDF
ACV00078_Side_Rail.pdf PDF
ACV00561_-_Unit_Load_Marking-F.PDF PDF
ACV00294_Lifting_Bar_(8).pdf PDF
4326-20PM1012_Gen_Unit.pdf PDF
ACV00293_Lifting_Bar_Support.pdf PDF
12972395_Igniter_Core_Bag.pdf PDF
4326-50_Rev_1_M231_Unit_(2).pdf PDF
ACV00077_Square_Ring.pdf PDF
ACV00068_PA103A2_Adapter.pdf PDF
ACV00515_-_Welding_-_rev-.pdf PDF
AC200000423_-_CARC_Paint_-_J.PDF PDF
ACV00303_Center_Support.pdf PDF
ACV00636_PA161_Adapter.pdf PDF
ACV00249_End_Ring.pdf PDF
12972394_Igniter_Core_and_End_Bag_Assy_(4).pdf PDF
ACV00075_Center_Support.pdf PDF
4326-50_Rev_1_M231_Unit.pdf PDF
ACV00305_Square_Ring_Restraint.pdf PDF
Att_0003_-_DD2345_Militarily_Critical_Technical_Data_Agreement.pdf PDF
W15QKN19R0013.pdf PDF
Att_0002_-_AMSTA_AR_Form_3002_Clearance_of_Technical_Information_for_Public_Release.pdf PDF
Att_0005_-_AMSTA-AR_Form_1350_Technical_Data_Request_Questionnaire.pdf PDF
Att_0008_-_Certificate_of_Destruction.DOC DOC document
Att_0009_-_Scheduled_GFP_Form_.pdf PDF
Att_0006_-_TDP_for_MACS_LAP.docx DOCX document
Att_0004_-_NonDisclosureNonUseAgreement.docx DOCX document
Att_0014_-_Data_Item_Descriptions_(DIDs)_Index.docx DOCX document
Att_0012_-_Additional_Solicitation_and_Contract_Requirements.pdf PDF
Exhibit_A_-_Contract_Data_Requirement_Lists_(CDRLs)_A001-A0015_Index.docx DOCX document
Att_0010_-_Additional_PCCI_Requirements.doc DOC document
Att_0007_-_Past_Performance_Letter-Questionnaire.docx DOCX document
Show 40 more

Latest 50 of 69 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP W15QKN-19-R-0013 Questions and Answers #2

6. Is there an IMS page limit?

RESPONSE: As mentioned within L.3.1, the Integrated Master Schedule (IMS) shall be a separate file. There is no page limit for the IMS; however, it needs to be legible, and should be as brief as possible while consistent with complete submission, given the time limit for the oral presentation (Up to two (2) hours).

7. Need clarification on the statement in L.4.1.1 paragraph A:

"The information and associated documentation for the identified production rate on the prime and any subcontractor facilities, key equipment, and tooling shall be provided."

RESPONSE: This language is asking for information and documentation that demonstrates/justifies how you are going to meet the production rates that are quoted.

8. Section C.3.7 clarify: The contractor shall be responsible for the performance of incineration/disposition of all the scrap or rejected components from the M231 and M232 TYPE production.

Does this include GFM? Does the government differentiate between rejected GFM materials prior to use on the production line vs. Contractors damaged material on the production line?

RESPONSE: Scrap would be any material (including GFM) that’s introduced to the LAP line that is not used (i.e. Propellant remaining in the hopper upon completion of the lot, damaged/rejected igniter bags, damaged/rejected combustible cases and damaged/rejected ammo containers and packaging materials. This requirement does not apply to rejected GFM materials that are identified at incoming inspection, prior to use on the production line, and are not caused by the LAP contractor.

9. Attachment 13, page 3 states “The contractor shall host a post award conference/meeting at the contractor’s facility to include contractor and government contracting, management, quality assurance and technical personnel no later than 30 calendar days after contract award. The contractor shall participate with the government to arrange a schedule and agenda for the post award conference prior to the meeting.”

RFQ Page 46 C.3.14.1 Post Award Meeting: The contractor shall host a post award meeting at the contractor's facility to include contracts, management, and technical personnel no later than 90 days after contract award.

Which one is correct as they are in conflict?

RESPONSE: 90 days is correct. Attachment 0013 shall be updated within Amendment 0002 to revise “30 days” to “90 days”, as stated within Section C.3.14.1.

10. There are several references to 4.1C combustible cases. We believe this should reflect 1.4C combustible cases. Please confirm.

RESPONSE: The Combustible Case hazard classification is 1.4C. All areas of the solicitation where 4.1C was reference will be formally updated to 1.4C within Amendment 0002.

11. "With regard to scheduling, [the offeror] needs to know what to expect from the government for lead time of energetics and combustible cases."

RESPONSE: As stated within Section H of the RFP, for each GFM item, a 2 month supply will be delivered “as early as 30 days after delivery order award but no later than 60 days before Production start-up", with the exception of igniter propellant, which states "as early as 30 days after delivery order award but no later than 120 days before Production start-up."

File details come from the government source that posted it. Updated .