This is a Quality Assurance Surveillance Plan (QASP) for the VTC/AV Lifecycle Support contract at Hill Air Force Base that establishes the Government's framework for evaluating and monitoring contractor performance.
The QASP defines six core performance objectives with specific acceptable quality levels (AQLs) and surveillance methods. The Contractor must submit a Monthly Activity Report (MAR) by the 5th business day of each month containing system status, STIG compliance, ServiceNow tickets, and supported organizations, subject to 100% inspection by the Contracting Officer's Representative (COR). A staffing roster must be provided within 10 business days of award with updates submitted within 5 business days of personnel changes, reviewed periodically by the Security Manager and COR. User documentation and training coordination for newly installed systems is monitored through MAR review and customer feedback. Corrective maintenance requests require response within specified timelines: Emergency (4 hours), Routine (2 days), and Minor (3 days), documented in the MAR and verified through ServiceNow reports. Security compliance requires 100% adherence to DD254, security clearance investigations, and non-disclosure agreements with no security breaches, subject to 100% inspection. Personnel must complete all required training (OPSEC, STINFO) for facility and network access, reviewed periodically by the 75 ABW/SC Training Manager. Surveillance methods include 100% inspection of mandatory deliverables, periodic random checks of staffing rosters and compliance reports, and investigation of valid customer complaints. The Government will document performance assessments, and repeated failures may result in an unsatisfactory CPAR rating or further contractual action.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Quality Assurance Surveillance Plan (QASP)
VTC/AV Lifecycle Support - Hill Air Force Base
1.0 Objective
This Quality Assurance Surveillance Plan (QASP) provides the overarching framework for the
Government to evaluate and monitor the Contractor's performance under the VTC/AV Lifecycle
Support contract at Hill Air Force Base. It ensures the Contractor delivers the quality levels specified in the Performance Work Statement (PWS).
2.0 Roles and Responsibilities
• Contracting Officer (CO): Retains overall responsibility for overseeing the Contractor’s performance. The CO is the only individual authorized to make changes to the contract.
• Contracting Officer’s Representative (COR): Responsible for monitoring, assessing, and communicating the Contractor’s performance to the CO. The COR will use this QASP to evaluate services and document findings (e.g., via Contractor Performance Assessment Reports).
• Contractor: Responsible for delivering services in accordance with the PWS and providing routine system and workload status through the Monthly Activity Report (MAR) per PWS section 1.1.
3.0 Performance Requirements & Surveillance Matrix
The following table outlines the core performance objectives, acceptable quality levels (AQLs), and the Government's methods of surveillance, derived from PWS Section 4.0.
Performance Objective
PWS
Reference
Performance Threshold (AQL) Method of Surveillance
Deliver Maintenance Activity Report
(MAR)
1.1, 2.3.1 MAR submitted by the 5th business day of each month containing a full list of systems/status, STIG-compliance, service calls (ServiceNow tickets), and supported organizations.
100% Inspection by
COR
Maintain Staffing Roster
1.2, 3.8 Initial list provided within 10 business days of award. Updates (additions/removals) submitted within 5 business days of the change.
Periodic Review by Security Manager and COR
User Documentation & Training
1.3 Coordinate with customers to provide
digital user manuals and as-needed training for all newly installed systems.
Review of MAR and Customer Feedback
Perform Corrective Maintenance
1.1, 2.3.6 Respond to corrective maintenance requests within identified timelines (Emergency: 4 hrs, Routine: 2 days, Minor: 3 days). Documented in MAR.
Review of ServiceNow Reports
& MAR
Compliance with Security Requirements
3.10 – 3.12 100% compliance with DD254, security clearance investigations, and non-disclosure agreements. No security breaches.
100% Inspection by Security Manager and COR
Maintain Personnel Training & Certifications
3.19 100% of personnel complete required training (e.g., OPSEC, STINFO) for facility and network access.
Periodic Review by
75 ABW/SC
Training Manager
4.0 Surveillance Methods
• 100% Inspection: The COR will review all mandatory deliverables (e.g., the monthly MAR).
• Periodic Inspection: Random checks of the staffing roster, security compliance, and STIG compliance reports.
• Customer Complaints/Feedback: The COR will investigate valid customer complaints regarding VTC/AV functionality or training.
5.0 Performance Evaluation
The Government will document its assessments of the Contractor's performance. When a discrepancy occurs, the COR will notify the Contractor and request corrective action. Repeated failures may result in an unsatisfactory CPAR rating or further contractual action.