VOTRAN Transfer Plaza Restroom Renovations Project Manual

This is a project manual for the Votran Transfer Plaza Restroom Renovations (Project PC2868) prepared for Volusia County, Florida, with architectural services provided by Hall & Ogle Architects, Inc. and engineering by Above Group. The project encompasses a comprehensive renovation of existing employee men's and women's restrooms adjacent to the break room, including demolition of existing fixtures and partitions, installation of new plumbing fixtures, improved lighting, updated ventilation, revised ADA-compliant configurations, and durable finishes suitable for high-use staff facilities. Work will be performed in phases to maintain continuity of daily operations within the employee break room, requiring coordination with facility staff to sequence restroom closures, manage temporary access, and minimize disruptions. The Contractor must submit the Schedule of Values and Contractor's Construction Schedule within 10 days after Notice to Proceed, with a pre-construction conference required no later than 10 days after that date. Progress meetings will occur weekly initially and adjust as the project progresses, with monthly review of pay applications during these meetings. Applications for Payment must be submitted monthly with supporting documentation including waivers of lien and digital construction photos, with drafts submitted five days prior to scheduled meetings. The project manual document, dated November 2, 2021, establishes detailed administrative and procedural requirements governing the work.

The contract requires the Contractor to coordinate a comprehensive submittal process including shop drawings, product data, samples, and daily construction reports, all subject to Architect review and approval before fabrication or installation proceeds. Record documents must be maintained throughout construction and converted to CAD format compatible with the Architect's and Owner's systems, with monthly updates required for progress payment approval. Substantial Completion requirements include submission of occupancy permits, warranties, test/adjust/balance records, final cleaning, and instruction of Owner's personnel on equipment operation and maintenance. The Contractor is responsible for all temporary facilities including sanitary facilities, electrical service compliant with NFPA Code 241 and National Electric Code standards, waste disposal, and security and protection measures. The manual specifies that substitutions may be considered only within 30 days after the Agreement date and only when products become unavailable through no fault of the contractor, with the burden of proof on the proposer to demonstrate equivalence; any cost savings from approved substitutions must reduce the Contract Sum. Final payment requires submission of certified completion documentation, evidence of continuing insurance coverage, consent of surety, and a final liquidated damages settlement statement.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VOTRAN TRANSFER PLAZA

RESTROOM RENOVATIONS

PC2868

PROJECT MANUAL

November 2, 2021

OWNER: VOLUSIA COUNTY, FLORIDA

123 West Indiana Avenue DeLand, Florida 32720

(386) 736-5935

ARCHITECTS: HALL & OGLE ARCHITECTS, INC.

208 Magnolia Avenue

Daytona Beach, Florida 32114

(386) 255-6163

ENGINEERS: Above Group 305 East Drive, Suite H

Melbourne, Florida 32904

(321) 345-9026

A/E: 2104

David Text Box July 28, 2025

2104 TABLE OF CONTENTS Page 1 Votran Transfer Plaza Restroom Renovations 2/8/2022

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

010270 APPLICATIONS FOR PAYMENT

010400 PROJECT COORDINATION

010450 CUTTING AND PATCHING

012000 PROJECT MEETINGS

013000 SUBMITTALS

015000 TEMPORARY FACILITIES

016000 PRODUCT REQUIREMENTS

017000 PROJECT CLOSEOUT

2104 APPLICATIONS FOR PAYMENT

Votran Transfer Plaza Restroom Renovations 010270 - 1

SECTION 010270

APPLICATIONS FOR PAYMENT

PART 1 - GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to this Section.

1.02 SUMMARY

A. This Section specifies administrative and procedural requirements governing the Contractor's

Applications for Payment.

1. Coordinate the Schedule of Values and Applications for Payment with the Contractor's

Construction Schedule, List of Subcontracts, and Submittal Schedule.

B. The Contractor's Construction Schedule and Submittal Schedule are included in Section

"Submittals".

1.03 SCHEDULE OF VALUES

A. Coordinate preparation of the Schedule of Values with preparation of the Contractor's Construction Schedule. Correlate line items with other administrative schedules and the forms required for the work, including the following:

1. Contractor's construction schedule.

2. Application for Payment form.

3. List of subcontractors.

4. Schedule of alternates.

5. List of products.

6. List of principal suppliers and fabricators.

7. Schedule of submittals.

B. Submit the Schedule of Values to the Owner's Representative within 10 days after the Notice to Proceed.

C. Format and Content: Use the Project Manual Table of Contents as a guide to establish the format for the Schedule of Values.

D. Identification: Include the following Project identification on the Schedule of Values:

1. Project name and location.

2. Name of the Architect.

3. Project number.

4. Contractor's name and address.

5. Date of submittal.

E. Arrange the Schedule of Values in a tabular form with separate columns to indicate the following for each item listed:

1. Generic name.

a. Related Specification Section.

2. Change Orders (numbers) that have affected value.

3. Dollar value.

F. Provide a breakdown of the Contract Sum in sufficient detail to facilitate continued evaluation of Applications for Payment and progress reports.

G. Round amounts off to the nearest whole dollar; the total shall equal the Contract Sum.

H. For each part of the Work where an Application for Payment may include materials or equipment, purchased or fabricated and stored, but not yet installed, provide separate line items on the Schedule of Values for initial cost of the materials, for each subsequent stage of completion, and for total installed value of that part of the Work.

I. Margins of Cost: Show line items for indirect costs, and margins on actual costs, only to the extent that such items will be listed individually in Applications for Payment. Each item in the

APPLICATIONS FOR PAYMENT 2104

010270 - 2 Votran Transfer Plaza Restroom Renovations

Schedule of Values and Applications for Payment shall be complete including its total cost and proportionate share of general overhead and profit margin.

1. At the Contractor's option, temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown as separate line items in the Schedule of Values or distributed as general overhead expense.

J. Schedule Updating: Update and resubmit the Schedule of Values when Change Orders or Construction Change Directives result in a change in the Contract Sum.

1.04 APPLICATIONS FOR PAYMENT:

A. Each Application for Payment shall be consistent with previous applications and payments as certified by the Architect and paid for by the Owner.

1. The initial Application for Payment, the Application for Payment at time of Substantial

Completion, and the final Application for Payment involve additional requirements.

B. Payment Application Times: Each progress payment date is as indicated in the Agreement.

The period of construction Work covered by each Application or Payment is the period indicated in the Agreement.

C. Payment Application Forms: Use Volusia County Pay Application form and Continuation Sheets G 703 as the form for Application for Payment.

D. Application Preparation: Complete every entry on the form, including notarization and execution by person authorized to sign legal documents on behalf of the Owner. Incomplete applications will be returned without action.

1. Entries shall match data on the Schedule of Values and Contractor's Construction

Schedule. Use updated schedules if revisions have been made.

2. Include amounts of Change Orders and Construction Change Directives issued prior to the last day of the construction period covered by the application.

E. Transmittal: Submit first a draft then 5 executed final copies of each Application for Payment including waivers of lien, digital construction photos, if required, and similar attachments to the Owner's Representative.

F. Payment Approval: Once a month, submit via email a "draft" Application for Payment including waivers of lien, digital construction photos, if required, and similar attachments to the Owner's Representative five days prior to scheduled pay application meeting / field visit. The "draft" will be modified, if required, during the meeting based on "on-site" inspection and proper documentation for materials and items properly stored. Payment will be withheld if record documents including, but not limited to, "as-built" drawings are not current and acceptable to the Architect.

G. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of the first Application for Payment include the following:

1. List of subcontractors.

2. Schedule of Values.

3. Contractor's Construction Schedule (preliminary if not final).

4. Submittal Schedule (preliminary if not final).

5. List of Contractor's staff assignments.

6. List of Contractor's principal consultants.

7. Copies of building permits

8. Copies of authorizations and licenses from governing authorities for performance of the

Work.

9. Initial progress report.

10. Report of pre-construction meeting.

H. Application for Payment at Substantial Completion: Following issuance of the Certificate of Substantial Completion, submit an Application for Payment; this application shall reflect any Certificates of Partial Substantial Completion issued previously for Owner occupancy of designated portions of the Work.

2104 APPLICATIONS FOR PAYMENT

Votran Transfer Plaza Restroom Renovations 010270 - 3

I. Administrative actions and submittals that shall proceed or coincide with this application include:

1. Occupancy permits and similar approvals.

2. Warranties (guarantees) and maintenance agreements.

3. Test/adjust/balance records.

4. Maintenance instructions.

5. Meter readings.

6. Start-up performance reports.

7. Change-over information related to Owner's occupancy, use, operation and maintenance.

8. Final cleaning.

9. Advice on shifting insurance coverages.

10. List of incomplete Work, recognized as exceptions to Architect's Certificate of Substantial

Completion.

J. Final Payment Application: Administrative actions and submittals which must precede or coincide with submittal of the final payment Application for Payment include the following:

1. Completion of Project closeout requirements.

2. Completion of items specified for completion after Substantial Completion.

3. Assurance that unsettled claims will be settled.

4. Transmittal of required Project construction records to Owner.

5. Certified property survey.

6. Proof that taxes, fees and similar obligations have been paid.

7. Removal of temporary facilities and services.

8. Removal of surplus materials, rubbish and similar elements.

9. Change of door locks to Owner's access.

PART 2 - PRODUCTS (NOT APPLICABLE)

PART 3 - EXECUTION (NOT APPLICABLE)

END OF SECTION

2104 PROJECT COORDINATION

Votran Transfer Plaza Restroom Renovations 010400 - 1

SECTION 010400

PROJECT COORDINATION

PART 1 - GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to this Section.

1.02 SUMMARY

A. This Section specifies administrative and supervisory requirements necessary for Project coordination including, but not necessarily limited to:

1. Coordination.

2. Administrative and supervisory personnel.

3. General installation provisions.

4. Cleaning and protection.

B. Field engineering is included in Section "Field Engineering".

C. Progress meetings, coordination meetings and pre-installation conferences are included in

Section "Project Meetings".

D. Requirements for the Contractor's Construction Schedule are included in Section "Submittals".

1.03 COORDINATION

A. Coordination: Coordinate construction activities included under various Sections of these

Specifications to assure efficient and orderly installation of each part of the Work. Coordinate construction operations included under different Sections of the Specifications that are dependent upon each other for proper installation, connection, and operation.

1. Where installation of one part of the Work is dependent on installation of other components, either before or after its own installation, schedule construction activities in the sequence required to obtain the best results.

2. Where availability of space is limited, coordinate installation of different components to assure maximum accessibility for required maintenance, service and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

B. Where necessary, prepare memoranda for distribution to each party involved outlining special procedures required for coordination. Include such items as required notices, reports, and attendance at meetings.

1. Prepare similar memoranda for the Owner and separate Contractors where coordination of their Work is required.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of schedules.

2. Installation and removal of temporary facilities.

3. Delivery and processing of submittals.

4. Progress meetings.

5. Project Close-out activities.

1.04 SUBMITTALS

A. Coordination Drawings: Prepare and submit coordination drawings where close and careful coordination is required for installation of products and materials fabricated off-site by separate entities, and where limited space availability necessitates maximum utilization of space for efficient installation of different components.

1. Show the interrelationship of components shown on separate Shop Drawings.

2. Indicate required installation sequences.

3. Comply with requirements contained in Section "Submittals".

PROJECT COORDINATION 2104

010400 - 2 Votran Transfer Plaza Restroom Renovations

4. Refer to Division-15 Section "Basic Mechanical Requirements" and Division-16 Section "Basic Electrical Requirements" for specific coordination drawing requirements for mechanical and electrical installations.

B. Staff Names: Within 15 days of Notice to Proceed, submit a list of the Contractor's principal staff assignments, including the Superintendent and other personnel in attendance at the site;

identify individuals, their duties and responsibilities; list their addresses and telephone numbers.

1. Post copies of the list in the Project meeting room, the temporary field office, and each temporary telephone.

PART 2 - PRODUCTS (NOT APPLICABLE).

PART 3 - EXECUTION

3.01 GENERAL INSTALLATION PROVISIONS

A. Inspection of Conditions: Require the Installer of each major component to inspect both the substrate and conditions under which Work is to be performed. Do not proceed until unsatisfactory conditions have been corrected in an acceptable manner.

B. Manufacturer's Instructions: Comply with manufacturer's installation instructions and recommendations, to the extent that those instructions and recommendations are more explicit or stringent than requirements contained in Contract Documents.

C. Inspect materials or equipment immediately upon delivery and again prior to installation.

Reject damaged and defective items.

D. Provide attachment and connection devices and methods necessary for securing Work.

Secure Work true to line and level. Allow for expansion and building movement.

E. Visual Effects: Provide uniform joint widths in exposed Work. Arrange joints in exposed Work to obtain the best visual effect. Refer questionable choices to the Architect for final decision.

F. Recheck measurements and dimensions, before starting each installation.

G. Install each component during weather conditions and Project status that will ensure the best possible results. Isolate each part of the completed construction from incompatible material as necessary to prevent deterioration.

H. Coordinate temporary enclosures with required inspections and tests, to minimize the necessity of uncovering completed construction for that purpose.

I. Mounting Heights: Where mounting heights are not indicated, install individual components at standard mounting heights recognized within the industry for the particular application indicated. Refer questionable mounting height decisions to the Architect for final decision.

3.02 CLEANING AND PROTECTION

A. During handling and installation, clean and protect construction in progress and adjoining materials in place. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion.

B. Clean and maintain completed construction as frequently as necessary through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects.

C. Limiting Exposures: Supervise construction activities to ensure that no part of the construction, completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period. Where applicable, such exposures include, but are not limited to, the following:

1. Excessive static or dynamic loading.

2. Excessive internal or external pressures.

3. Excessively high or low temperatures.

4. Thermal shock.

5. Excessively high or low humidity.

2104 PROJECT COORDINATION

Votran Transfer Plaza Restroom Renovations 010400 - 3

6. Air contamination or pollution.

7. Water or ice.

8. Solvents.

9. Chemicals.

10. Light.

11. Radiation.

12. Puncture.

13. Abrasion.

14. Heavy traffic.

15. Soiling, staining and corrosion.

16. Bacteria.

17. Rodent and insect infestation.

18. Combustion.

19. Electrical current.

20. High speed operation,

21. Improper lubrication,

22. Unusual wear or other misuse.

23. Contact between incompatible materials.

24. Destructive testing.

25. Misalignment.

26. Excessive weathering.

27. Unprotected storage.

28. Improper shipping or handling.

29. Theft.

30. Vandalism.

2104 CUTTING AND PATCHING

Votran Transfer Plaza Restroom Renovations 010450 - 1

SECTION 010450

CUTTING AND PATCHING

PART 1 - GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to this Section.

1.02 SUMMARY

A. This Section specifies administrative and procedural requirements for cutting and patching.

1.03 QUALITY ASSURANCE

A. Operational and Safety Limitations: Do not cut and patch operating elements or safety related components in a manner that would result in reducing their capacity to perform as intended, or result in increased maintenance, or decreased operational life or safety.

PART 2 - PRODUCTS

2.01 MATERIALS

A. Use materials that are identical to existing materials. If identical materials are not available or cannot be used where exposed surfaces are involved, use materials that match existing adjacent surfaces to the fullest extent possible with regard to visual effect. Use materials whose installed performance will equal or surpass that of existing materials.

PART 3 - EXECUTION

3.01 INSPECTION

A. Before cutting existing surfaces, examine surfaces to be cut and patched and conditions under which cutting and patching is to be performed. Take corrective action before proceeding, if unsafe or unsatisfactory conditions are encountered.

3.02 PREPARATION

A. Protection: Protect existing construction during cutting and patching to prevent damage.

Provide protection from adverse weather conditions for portions of the Project that might be exposed during cutting and patching operations.

B. Avoid interference with use of adjoining areas or interruption of free passage to adjoining areas.

C. Take all precautions necessary to avoid cutting existing pipe, conduit or ductwork serving the building, but scheduled to be removed or relocated until provisions are made to bypass them.

3.03 PERFORMANCE

A. General: Employ skilled workmen to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time and complete without delay.

1. Cut existing construction to provide for installation of other components or performance of other construction activities and the subsequent fitting and patching required to restore surfaces to their original condition.

B. Cutting: Cut existing construction using methods least likely to damage elements to be retained or adjoining construction. Where possible review proposed procedures with the original installer; comply with the original installer's recommendations.

1. In general, where cutting is required use hand or small power tools designed for sawing or grinding, not hammering and chopping. Cut holes and slots neatly to size required with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use.

2. To avoid marring existing finished surfaces, cut or drill from the exposed or finished side into concealed surfaces.

3. Cut through concrete and masonry using a cutting machine such as a carborundum saw or diamond core drill.

4. Comply with requirements of applicable Sections of Division-2 where cutting and patching requires excavating and backfilling.

CUTTING AND PATCHING 2104

010450 - 2 Votran Transfer Plaza Restroom Renovations

C. Patching: Patch with durable seams that are as invisible as possible. Comply with specified tolerances.

1. Where feasible, inspect and test patched areas to demonstrate integrity of the installation.

2. Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will eliminate evidence of patching and refinishing.

3. Where removal of walls or partitions extends one finished area into another, patch and repair floor and wall surfaces in the new space to provide an even surface of uniform color and appearance. Remove existing floor and wall coverings and replace with new materials, if necessary to achieve uniform color and appearance.

4. Where patching occurs in a smooth painted surface, extend final paint coat over entire unbroken containing the patch, after the patched area has received primer and second coat.

3.04 CLEANING

A. Thoroughly clean areas and spaces where cutting and patching is performed or used as access. Remove completely paint, mortar, oils, putty and items of similar nature. Thoroughly clean piping, conduit and similar features before painting or other finishing is applied. Restore damaged pipe covering to its original condition.

2104 PROJECT MEETINGS

Votran Transfer Plaza Restroom Renovations 012000 - 1

SECTION 012000

PROJECT MEETINGS

PART 1 - GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to this Section.

1.02 SUMMARY

A. This Section specifies administrative and procedural requirements for project meetings including but not limited to:

1. Pre-Construction Conference.

2. Pre-Installation Conferences.

3. Progress Meetings.

B. Construction schedules are specified in another Division-1 Section.

1.03 PRE-CONSTRUCTION CONFERENCE

A. Schedule a pre-construction conference and organizational meeting at the Project site or other convenient location no later than 10 days after notice to proceed. Conduct the meeting to review responsibilities and personnel assignments.

B. Attendees: The Owner, Architect and their consultants, the Contractor and its superintendent, major subcontractors, manufacturers, suppliers and other concerned parties shall each be represented at the conference by persons familiar with and authorized to conclude matters relating to the Work.

C. Agenda: Discuss items of significance that could affect progress including such topics as:

1. Tentative construction schedule

2. Critical Work sequencing

3. Designation of responsible personnel

4. Procedures for processing field decisions and Change Orders

5. Procedures for processing Applications for Payment

6. Distribution of Contract Documents

7. Submittal of Shop Drawings, Product Data and Samples

8. Preparation and maintenance of record drawings ('as-builts')

9. Use of the premises

10. Office, Work and storage areas

11. Equipment deliveries and priorities

12. Safety Procedures

13. First Aid

14. Security

15. Housekeeping

16. Working hours

17. List of Employees, personnel proposed

18. Emergency contact list of primary staff of the general contractor

19. Procedures for Testing and Inspection

20. Procedure for RFI's

21. Responsibility for temporary facilities

22. Construction Meetings

23. Parking Availability

24. Owner Occupancy Requirements

1.04 PRE-INSTALLATION CONFERENCES

A. Conduct a pre-installation conference at the site before each major construction activity that requires coordination with other construction. The Installer and representatives of manufacturers and fabricators involved in or affected by the installation, and its coordination or

PROJECT MEETINGS 2104

012000 - 2 Votran Transfer Plaza Restroom Renovations integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise the Architect of scheduled meeting dates.

B. Review the progress of other construction activities and preparations for particular activity under consideration at each pre-installation conference, including requirements for:

1. Contract Documents

2. Options

3. Related Change Orders and applicable Field Orders

4. Purchases

5. Deliveries

6. Shop Drawings, Product Data and quality control Samples

7. Possible conflicts

8. Compatibility problems

9. Time schedules

10. Weather limitations

11. Manufacturer's recommendations

12. Compatibility of materials

13. Acceptability of substrates

14. Temporary facilities

15. Space and access limitations

16. Governing regulations

17. Safety

18. Inspection and testing requirements

19. Required performance results

20. Recording requirements

21. Protection

C. Record significant discussions and agreements and disagreements of each conference, along with the approved schedule. Distribute the record of the meeting to everyone concerned, promptly, including the Owner and Architect.

D. Do not proceed if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of Work and reconvene the conference at the earliest feasible date.

1.05 PROGRESS MEETINGS

A. Progress meetings, held at a location to be determined, will start out weekly and adjust from there as project progresses. Once a month, a review of the pay application will be addressed during the meeting.

B. Attendees: In addition to representatives of the Owner and Architect, each subcontractor, supplier or other entity concerned with current progress or involved in planning, coordination or performance of future activities shall be represented at these meetings by persons familiar with the Project and authorized to conclude matters relating to progress.

C. Agenda: Review and correct or approve minutes of the previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to the current status of the Project.

D. Contractor's Construction Schedule: Review progress since the last meeting. Determine where each activity is in relation to the Contractor's Construction Schedule, whether on time or ahead or behind schedule. Determine how construction behind schedule will be expedited;

secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.

E. Review the present and future needs of each entity present, including such items as:

1. Record drawings.

2. Interface requirements.

2104 PROJECT MEETINGS

Votran Transfer Plaza Restroom Renovations 012000 - 3

3. Time.

4. Sequences.

5. Deliveries.

6. Off-site fabrication problems.

7. Access.

8. Site utilization.

9. Temporary facilities and services.

10. Hours of Work.

11. Hazards and risks.

12. Housekeeping.

13. Quality and Work standards.

14. Change Orders.

15. Documentation of information for payment requests.

16. Status of Submittals

17. Status of corrections to deficient items

18. Status of Proposal Requests and Change Orders

19. Pending Changes

F. Reporting: No later than 3 days after each progress meeting date, distribute copies of minutes of the meeting to each party present and to other parties who should have been present via email. Include a brief summary, in narrative form, of progress since the previous meeting and report.

G. Schedule Updating: Revise the construction schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue the revised schedule concurrently with the report of each meeting.

PART 2 - PRODUCTS (NOT APPLICABLE)

PART 3 - EXECUTION (NOT APPLICABLE)

2104 SUBMITTALS

Votran Transfer Plaza Restroom Renovations 013000 - 1

SECTION 013000

SUBMITTALS

PART 1 - GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to this Section.

1.02 SUMMARY

A. This Section specifies administrative and procedural requirements for submittals required for performance of the Work including;

1. Contractor's construction schedule

2. Submittal schedule

3. Product Data

4. Daily construction reports

5. Shop Drawings

6. Samples

B. Administrative Submittals: Refer to other Division-1 Sections and other Contract Documents for requirements for administrative submittals. Such submittals include, but are not limited to:

1. Permits

2. Performance and payment bonds

3. List of Subcontractors

4. The Schedule of Values submittal is included in Section "Applications for Payment"

5. Inspection and test reports are included in Section "Quality Control Services"

6. Applications for Payment

7. Insurance certificates

8. Digital Construction Photos, if required

1.03 SUBMITTAL PROCEDURES

A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Transmit each submittal sufficiently in advance of performance of related construction activities to avoid delay.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals and related activities that require sequential activity.

2. Coordinate transmittal of different types of submittals for related elements of the Work so processing will not be delayed by the need to review submittals concurrently for coordination.

a. The Architect reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

3. Processing: Allow sufficient review time so that installation will not be delayed as a result of the time required to process submittals, including time for resubmittals.

a. Allow two weeks for initial review. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. The Architect will promptly advise the Contractor when a submittal being processed must be delayed for coordination.

b. If an intermediate submittal is necessary, process the same as the initial submittal.

c. Allow two weeks for reprocessing each submittal.

d. No extension of Contract Time will be authorized because of failure to transmit submittals to the Architect sufficiently in advance of the Work to permit processing.

B. Submittal Preparation: Place a permanent label or title block on each submittal for identification. Indicate the name of the entity that prepared each submittal on the label or title block.

1. Provide a space approximately 4" x 5" on the label or beside the title block on Shop

Drawings to record the Contractor's review and approval markings and the action taken.

SUBMITTALS 2104

013000 - 2 Votran Transfer Plaza Restroom Renovations

2. Include the following information on the label for processing and recording action taken.

a. Project name.

b. Date.

c. Name and address of Architect.

d. Name and address of Contractor.

e. Name and address of subcontractor.

f. Name and address of supplier.

g. Name of manufacturer.

h. Number and title of appropriate Specification Section.

i. Drawing number and detail references, as appropriate.

C. Submittal Transmittal: Package each submittal appropriately for transmittal and handling.

Transmit each submittal from Contractor to Architect using a transmittal form. Submittals received from sources other than the Contractor will be returned without action.

1. On the transmittal, record relevant information and requests for data. On the form, or separate sheet, record deviations from Contract Document requirements, including minor variations and limitations. Include Contractor's certification that information complies with Contract Document requirements. Submittals without Contractor Certification of compliance will be returned without review.

2. Transmittal Form: Use AIA Document G 810.

1.04 CONTRACTOR'S CONSTRUCTION SCHEDULE

A. Bar-Chart Schedule: Prepare a fully developed, horizontal bar-chart type Contractor's construction schedule. Submit within 10 days of the Notice to Proceed.

1. Provide a separate time bar for each significant construction activity. Provide a continuous vertical line to identify the first working day of each week. Use the same breakdown of units of the Work as indicated in the "Schedule of Values".

2. Within each time bar indicate estimated completion percentage in 10 percent increments.

As Work progresses, place a contrasting mark in each bar to indicate Actual Completion.

3. Prepare the schedule on a sheet, or series of sheets, of stable transparency, or other reproducible media, of sufficient width to show data for the entire construction period.

4. Secure time commitments for performing critical elements of the Work from parties involved. Coordinate each element on the schedule with other construction activities;

include minor elements involved in the sequence of the Work. Show each activity in proper sequence. Indicate graphically sequences necessary for completion of related portions of the Work.

5. Coordinate the Contractor's construction schedule with the schedule of values, list of subcontracts, submittal schedule, progress reports, payment requests and other schedules.

6. Indicate completion in advance of the date established for Substantial Completion.

Indicate Substantial Completion on the schedule to allow time for the Architect's procedures necessary for certification of Substantial Completion.

B. Distribution: Following response to the initial submittal, print and distribute copies to the Architect, Owner, subcontractors, and other parties required to comply with scheduled dates.

Post copies in the Project meeting room and temporary field office.

1. When revisions are made, distribute to the same parties and post in the same locations.

Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in construction activities.

C. Schedule Updating: Revise the schedule after each meeting or activity, where revisions have been recognized or made. Issue the updated schedule concurrently with report of each meeting.

1.05 SUBMITTAL SCHEDULE

A. Prepare a complete schedule of submittals. Submit the schedule within 10 days of the Notice to

Proceed.

Votran Transfer Plaza Restroom Renovations 013000 - 3

1. Coordinate submittal schedule with the list of subcontracts, schedule of values and the list of products as well as the Contractor's construction schedule.

2. Prepare the schedule in chronological order; include submittals required during the first 90 days of construction. Provide the following information:

a. Scheduled date for the first submittal.

b. Related Section number.

c. Submittal category.

d. Name of subcontractor.

e. Description of the part of the Work covered.

f. Scheduled date for resubmittal.

g. Scheduled date the Architect's final release or approval.

B. Distribution: Following response to initial submittal, print and distribute copies to the Architect, Owner, subcontractors, and other parties required to comply with submittal dates indicated.

Post copies in the Project meeting room and field office.

1. When revisions are made, distribute to the same parties and post in the same locations.

Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in construction activities.

C. Schedule Updating: Revise the schedule after each meeting or activity, where revisions have been recognized or made. Issue the updated schedule concurrently with report of each meeting.

1.06 DAILY CONSTRUCTION REPORTS

A. Prepare a daily construction report, recording the following information concerning events at the site. Make reports available to the Owner's Representative upon request.

1. List of personnel, employees, visitors, and subcontractors at the site.

2. High and low temperatures, general weather conditions.

3. Accidents and unusual events.

4. Meetings and significant decisions.

5. Stoppages, delays, shortages, losses.

6. Meter readings and similar recordings.

7. Emergency procedures.

8. Orders and requests of governing authorities.

9. Change Orders received, implemented.

10. Services connected, disconnected.

11. Equipment or system tests and start-ups.

12. Partial Completions, occupancies.

13. Substantial Completions authorized.

1.07 SHOP DRAWINGS

A. Submit newly prepared information, drawn to accurate scale. Highlight, encircle, or otherwise indicate deviations from the Contract Documents. Do not reproduce Contract Documents or copy standard information as the basis of Shop Drawings. Standard information prepared without specific reference to the Project is not considered Shop Drawings.

1. Sheet Size: Except for templates, patterns and similar full-size Drawings, submit Shop

Drawings on sheets at least 8-1/2" x 11" but no larger than 24" x 36".

B. Shop Drawings include fabrication and installation drawings, setting diagrams, schedules, patterns, templates and similar drawings. Include the following information:

1. Dimensions.

2. Identification of products and materials included.

3. Compliance with specified standards.

4. Notation of coordination requirements.

5. Notation of dimensions established by field measurement.

C. Submittal: Submit all shop drawings electronically in PDF format.

013000 - 4 Votran Transfer Plaza Restroom Renovations

1. Maintain one of the marked-up prints returned, as a "Record Document".

2. Do not use Shop Drawings without an appropriate final stamp indicating action taken in connection with construction.

3. Only Final reviewed shop drawings which have been reviewed by the Architect and the design Structural Engineer shall be used for fabrication and the field installation of products or assemblies of products. Modification of reviewed shop drawings by the manufacturer or fabricator for “Field Use” is prohibited unless proposed modifications have been reviewed by the Architect.

D. Coordination drawings are a special type of Shop Drawing that show the relationship and integration of different construction elements that require careful coordination during fabrication or installation to fit in the space provided or function as intended.

1. Preparation of coordination Drawings is specified in section "Project Coordination" and may include components previously shown in detail on Shop Drawings or Product Data.

2. Submit coordination Drawings for integration of different construction elements. Show sequences and relationships of separate components to avoid conflicts in use of space.

1.08 PRODUCT DATA

A. Collect Product Data into a single submittal for each element of construction or system.

Product Data includes printed information such as manufacturer's installation instructions, catalog cuts, standard color charts, roughing-in diagrams and templates, standard wiring diagrams and performance curves. Where Product Data must be specially prepared because standard printed data is not suitable for use, submit as "Shop Drawings."

1. Mark each copy to show applicable choices and options. Where printed Product Data includes information on several products, some of which are not required, mark copies to indicate the applicable information. Include the following information:

a. Manufacturer's printed recommendations.

b. Compliance with recognized trade association standards.

c. Compliance with recognized testing agency standards.

d. Application of testing agency labels and seals.

e. Notation of dimensions verified by field measurement.

f. Notation of coordination requirements.

B. Do not submit Product Data until compliance with requirements of the Contract Documents has been confirmed.

C. Submittals: Submit 6 copies of each required submittal; submit 4 copies where required for maintenance manuals. The Architect will retain two, and will return the other marked with action taken and corrections or modifications required.

1. Unless noncompliance with Contract Document provisions is observed, the submittal may serve as the final submittal.

D. Distribution: Furnish copies of final submittal to installers, subcontractors, suppliers, manufacturers, fabricators, and others required for performance of construction activities.

Show distribution on transmittal forms.

1. Do not proceed with installation until an applicable copy of Product Data applicable is in the installer's possession.

2. Do not permit use of unmarked copies of Product Data in connection with construction.

1.09 SAMPLES

A. Submit full-size, fully fabricated Samples cured and finished as specified and physically identical with the material or product proposed. Samples include partial sections of manufactured or fabricated components, cuts or containers of materials, color range sets, and swatches showing color, texture and pattern.

1. Mount, display, or package Samples in the manner specified to facilitate review of qualities indicated. Prepare Samples to match the Architect's Sample. Include the following:

a. Generic description of the Sample.

Votran Transfer Plaza Restroom Renovations 013000 - 5

b. Sample source.

c. Product name or name of manufacturer.

d. Compliance with recognized standards.

e. Availability and delivery time.

B. Submit Samples for review of kind, color, pattern, and texture, for a final check of these characteristics with other elements, and for a comparison of these characteristics between the final submittal and the actual component as delivered and installed.

1. Where variation in color, pattern, texture or other characteristics are inherent in the material or product represented, submit multiple units (not less than 3), that show approximate limits of the variations.

2. Refer to other Specification Sections for requirements for Samples that illustrate workmanship, fabrication techniques, details of assembly, connections, operation and similar construction characteristics.

C. Preliminary submittals: Where Samples are for selection of color, pattern, texture or similar characteristics from a range of standard choices, submit a full set of choices for the material or product.

1. Preliminary submittals will be reviewed and returned with the Architect's mark indicating selection and other action.

D. Submittals: Except for Samples illustrating assembly details, workmanship, fabrication techniques, connections, operation and similar characteristics, submit 4 sets; one will be returned marked with the action taken.

E. Maintain sets of Samples, as returned, at the Project site, for quality comparisons throughout the course of construction.

1. Unless noncompliance with Contract Document provisions is observed, the submittal may serve as the final submittal.

2. Sample sets may be used to obtain final acceptance of the construction associated with each set.

F. Distribution of Samples: Prepare and distribute additional sets to subcontractors, manufacturers, fabricators, suppliers, installers, and others as required for performance of the Work. Show distribution on transmittal forms.

G. Field Samples specified in individual Sections are special types of Samples. Field Samples are full-size examples erected on site to illustrate finishes, coatings, or finish materials and to establish the standard by which the Work will be judged.

1. Comply with submittal requirements to the fullest extent possible. Process transmittal forms to provide a record of activity.

1.10 ARCHITECT'S ACTION

A. Except for submittals for record, information or similar purposes, where action and return is required or requested, the Architect will review each submittal, mark to indicate action taken, and return promptly.

1. Compliance with specified characteristics is the Contractor's responsibility.

B. Action Stamp: The Architect will stamp each submittal with a uniform, self-explanatory action stamp. The stamp will be appropriately marked, as follows, to indicate the action taken:

1. Final Unrestricted Release: Where submittals are marked "Reviewed," that part of the

Work covered by the submittal may proceed provided it complies with requirements of the Contract Documents; final acceptance will depend upon that compliance.

2. Final-But-Restricted Release: When submittals are marked "Furnish as Corrected," that part of the Work covered by the submittal may proceed provided it complies with notations or corrections on the submittal and requirements of the Contract Documents; final acceptance will depend on that compliance.

3. Returned for Resubmittal: When submittal is marked "Rejected or Revise and Resubmit," do not proceed with that part of the Work covered by the submittal, including purchasing, fabrication, delivery, or other activity. Revise or prepare a new submittal in accordance

013000 - 6 Votran Transfer Plaza Restroom Renovations with the notations; resubmit without delay. Repeat if necessary to obtain a different action mark.

a. Do not permit submittals marked "Rejected or Revise and Resubmit" to be used at the Project site, or elsewhere where Work is in progress.

4. Other Action: Where a submittal is primarily for information or record purposes, special processing or other activity, the submittal will be returned, marked "Review Not Required".

Where a submittal is marked also "Submit Specified Item", further submittal information is required.

PART 2 - PRODUCTS (NOT APPLICABLE).

PART 3 - EXECUTION (NOT APPLICABLE).

2104 TEMPORARY FACILITIES

Votran Transfer Plaza Restroom Renovations 015000 - 1

SECTION 015000

TEMPORARY FACILITIES

PART 1 - GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to this Section.

1.02 SUMMARY

A. This Section specifies requirements for temporary services and facilities, including utilities, construction and support facilities, security and protection.

B. Temporary construction and support facilities required include but are not limited to:

1. Sanitary facilities, including drinking water.

2. Temporary enclosures.

3. Temporary signs and bulletin boards.

4. Waste disposal services.

5. Construction aids and miscellaneous services and facilities.

C. Security and protection facilities required include but are not limited to:

1. Barricades, warning signs, lights.

2. Environmental protection.

1.03 QUALITY ASSURANCE

A. Regulations: Comply with industry standards and applicable laws and regulations if authorities having jurisdiction, including but not limited to:

1. Building Code requirements.

2. Health and safety regulations.

3. Utility company regulations.

4. Police, Fire Department and Rescue Squad rules.

5. Environmental protection regulations.

B. Standards: Comply with NFPA Code 241, "Building Construction and Demolition Operations", ANSI-A10 Series standards for "Safety Requirements for Construction and Demolition", and NECA Electrical Design Library "Temporary Electrical Facilities."

1. Refer to "Guidelines for Bid Conditions for Temporary Job Utilities and Services", prepared jointly by AGC and ASC, for industry recommendations.

2. Electrical Service: Comply with NEMA, NECA and UL standards and regulations for temporary electric service. Install service in compliance with National Electric Code (NFPA 70).

1.04 PROJECT CONDITIONS

A. Conditions of Use: Keep temporary services and facilities clean and neat in appearance.

Operate in a safe and efficient manner. Take necessary fire prevention measures. Do not overload facilities, or permit them to interfere with progress. Do not allow hazardous dangerous or unsanitary conditions, or public nuisances to develop or persist on the site.

PART 2 - PRODUCTS

2.01 EQUIPMENT

A. Electrical Power Cords: Provide grounded extension cords; use "hard-service" cords where exposed to abrasion and traffic. Provide waterproof connectors to connect separate lengths of electric cords, if single lengths will not reach areas where construction activities are in progress.

B. Lamps and Light Fixtures: Provide general service incandescent lamps of wattage required for adequate illumination. Provide guard cages or tempered glass enclosures, where exposed to breakage. Provide exterior fixtures where exposed to moisture.

TEMPORARY FACILITIES 2104

015000 - 2 Votran Transfer Plaza Restroom Renovations

C. Temporary Toilet Units: Provide self-contained single-occupant toilet units of the chemical, aerated recirculation, or combustion type, properly vented and fully enclosed with a glass fiber reinforced polyester shell or similar nonabsorbent material. Godawa is County's current vendor.

D. First Aid Supplies: Comply with governing regulations.

E. Fire Extinguishers: Provide hand-carried, portable UL-rated, class "A" fire extinguishers for temporary offices and similar spaces. In other locations provide hand-carried, portable, UL-rated, class "ABC" dry chemical extinguishers, or a combination of extinguishers of NFPA recommended classes for the exposures.

1. Comply with NFPA 10 and 241 for classification, extinguishing agent and size required by location and class of fire exposure.

PART 3 - EXECUTION

3.01 INSTALLATION

A. Provide each facility ready for use when needed to avoid delay. Maintain and modify as required. Do not remove until facilities are no longer needed, or are replaced by authorized use of completed permanent facilities.

3.02 TEMPORARY CONSTRUCTION AND SUPPORT FACILITIES INSTALLATION

A. Sanitary facilities include temporary toilets, wash facilities and drinking water fixtures. Comply with regulations and health codes for the type, number, location, operation and maintenance of fixtures and facilities. Install where facilities will best serve the Project's needs.

1. Provide toilet tissue, paper towels, paper cups and similar disposable materials for each facility. Provide covered waste containers for used material.

B. Toilets: Install self-contained toilet units. Shield toilets to ensure privacy. Use of pit-type privies will not be permitted.

C. Drinking Water Facilities: Provide containerized tap-dispenser bottled-water type drinking water units, including paper supply.

D. Project Identification Sign: Provide project sign per County sign standard drawing.

E. Temporary Signs: Prepare signs to provide directional information to construction personnel and visitors.

F. Collection and Disposal of Waste: Collect waste from construction areas and elsewhere daily.

Comply with requirements of NFPA 241 for removal of combustible waste material and debris.

Enforce requirements strictly. Do not hold materials more than 7 days during normal weather or 3 days when the temperature is expected to rise above 80 deg F (27 deg C). Handle hazardous, dangerous, or unsanitary waste materials separately from other waste by containerizing properly. Dispose of material in a lawful manner.

3.03 SECURITY AND PROTECTION FACILITIES INSTALLATION

A. Barricades, Warning Signs and Lights: Comply with standards and code requirements for erection of structurally adequate barricades. Paint with appropriate colors, graphics and warning signs to inform personnel and the public of the hazard being protected against. Where appropriate and needed provide lighting, including flashing red or amber lights.

B. Environmental Protection: Provide protection, operate temporary facilities and conduct construction in ways and by methods that comply with environmental regulations, and minimize the possibility that air, waterways and subsoil might be contaminated or polluted, or that other undesirable effects might result.

C. Restrict use of noise making tools and equipment to hours that will minimize complaints from persons or firms near the site.

3.04 OPERATION, TERMINATION AND REMOVAL

A. Supervision: Enforce strict discipline in use of temporary facilities.